Object №1
Technical specifications for carrying out construction and renovation works at the following facility:
Local School Polyova Street, 36, village Kolomyichykha, Svatove district, Luhansk region
These technical specifications include technical descriptions of a number of general construction services
that need to be provided in order to replace the existing wooden windows in the rural school facilities in
the village of Kolomiychykha.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:
To replace wooden windows in the rural school with
reinforced plastic metal windows – 30 items:
 To replace wooden windows, drains, and
windowsill boards with reinforced plastic metal
ones (install a 4-chamber window profiles, and 2or 1- chamber window glass panels with energysaving coating) - 112.9 m2;
2.15 x 1.75 m – 30 items;
 To renovate and paint existing internal window
slopes, up to 30 cm wide, insulating them with
Styrofoam – 182 meters long;
 To take out and dispose of building waste.
Object №2
Technical specifications for carrying out construction and renovation works at the following facility:
School, 65 Lenina Str., village Nyzhnya Duvanka, Svatove district, Luhansk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows in the school facilities.
The current structural characteristics of the • Foundations are prefabricated blocks made of
school building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is soft;
• Windows are wooden;
• Doors are wooden;
• Flooring is mosaic, made of wooden panels and
ceramic tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The school building requires a series of actions in order
to ensure energy conservation. For instance, replacing
the existing wooden window frames with more
energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:


To replace existing wooden frame windows with
fiberglass reinforced plastic window panels, VEKA
type or similar. Also, to replace windowsills and
drip caps; to renovate window slopes
2.20 x 1.9 m – 63 items / 263.34 m2;
(window slopes up to 0.4 m; windowsills up 0.5 m;
drip caps up to 0.25 m; install a 4-chamber window
profiles, and 2- or 1- chamber window glass panels
with energy-saving coating)
To take out and dispose of building waste.
Object №3
Technical specifications for carrying out construction and renovation works at the following facility:
Municipal House of Culture “Kreminna” (MHC), 2B Zhelisnyaka Lane, Kreminna, Luhansk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows and doors in the MHC facilities.
The current structural characteristics of the MHC • Foundations are prefabricated blocks made of
building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is made of slate tiles;
• Windows are wooden;
• Doors are wooden;
• Flooring is mosaic, wooden boards, and ceramic tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The MHC building requires a series of actions in order
to ensure energy conservation. For instance, replacing
the existing wooden window frames and wooden
doors with more energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:


To replace existing wooden frame windows with
fiberglass reinforced plastic window panels, VEKA
type or similar. Also, to replace windowsills and
drip caps; to renovate window slopes:
Windows – 21 items / 45.8 m2, including:
2.2 x 1.35 m – 4 items / 11.88 m2;
1.35 x 1.35 m – 4 items / 7.29 m2;
1.35 x 1.55 m – 2 items / 4.18 m2;
1.7 x 1.15 m – 6 items / 11.73 m2;
1.65 x 1,15 m – 4 items / 7.59 m2;
1.65 x 1.9 m – 1 items / 3.13 m2;
Doors with transoms - 4 items/ 16.82 m2;
3.1 x 1.55 m – 2 items (emergency exit doors);
2.35 x 1.4 m; 2.5 x 1.57 m – tambour doors, main
entrance doors)
(window slopes up to 0.45 m; windowsills up 0.5
m; drip caps up to 0.25 m; install a 4-chamber
window profiles, and 2- or 1- chamber window
glass panels with energy-saving coating)
To take out and dispose of building waste
Object №4
Technical specifications for carrying out construction and renovation works at the following facility:
RKZOZ “Center for medical and sanitary assistance”, 2A Dzerzhyns’kogo Street, B3, the town of
Oleksandrivka, Donetsk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows in the RKZOZ facilities.
The current structural characteristics of the • Foundations are prefabricated blocks made of
RKZOZ building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is made of slate tiles;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of linoleum, wooden boards, and
ceramic tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Коротка характеристика об’єкту:
Brief description of the facility:
The RKZOZ building requires a series of actions in order
to ensure energy conservation. For instance, replacing
the existing wooden window frames with more
energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:


To replace existing wooden frame windows with
fiberglass reinforced plastic window panels, VEKA
type or similar. Also, to replace windowsills and
drip caps; to renovate window slopes:
Windows – 40 items / 151.02 m2, including:
1.75 x 2.05 m – 34 items / 121.96 m2;
1.15 x 1.65 m – 3 items / 5.7 m2;
1.75 x 4.45 m – 3 items / 23.36 m2;
(window slopes up to 0.4 m; windowsills up 0.5 m;
drip caps up to 0.25 m; install a 4-chamber
window profiles, and 2- or 1- chamber window
glass panels with energy-saving coating)
To take out and dispose of building waste
Object №5
Technical specifications for carrying out construction and renovation works at the following facility: KLPZ
“Dobropillya Central District Hospital” (maternity department, obstetrics and gynecology department,
prenatal care department), 3 Gagarina Street, the city of Dobropillia, Donetsk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows in the KLPZ facilities.
The current structural characteristics of the KLPZ • Foundations are prefabricated blocks made of
building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is soft, made of slate tiles;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of linoleum, wooden boards, and
ceramic tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The KLPZ building requires a series of actions in order
to ensure energy conservation. For instance, replacing
the existing wooden window frames and wooden
doors with more energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:

To replace existing wooden frame windows with
fiberglass reinforced plastic window panels, VEKA
type or similar. Also, to replace windowsills and
drip caps; to renovate window slopes:
Maternity department:
Windows – 12 items / 38.31 m2,
Including:
1.75 x 2.05 m – 7 items / 25.11 m2;
1.75 x 1.75 m – 3 items / 9.18 m2;
1.75 x 1.15 m – 2 items / 4.02 m2;
Entrance doors (2 mm metal, insulated): (2.35 Х
1.45) -1 item;
Obstetrics and gynecology department:
Windows – 8 items / 16.99 m2,
Including:
1.35 x 1.35 m – 5 items/ 9.11 m2;
1.35 x 1.95 m – 3 items/ 7.89 m2;
Entrance doors (2 mm metal, insulated, with
transoms): 2.9 x 1.0 m – 1 item;
Prenatal care department:
Windows – 9 items / 28.60 m2,
Including:
1.75 x 2.05 m – 4 items / 14.35 m2;
1.75 x 1.75 m – 4 items / 12.24 m2;
1.75 x 1.15 m – 1 items / 2.01 m2;
Entrance doors (2 mm metal, insulated): 2.1 x 1.3
m – 1 item;
(window slopes up to 0.3 m; windowsills up 0.35
m; drip caps up to 0.25 m; install a 4-chamber
window profiles, and 2- or 1- chamber window
glass panels with energy-saving coating);
 To take out and dispose of building waste.
Object №6
Technical specifications for carrying out construction and renovation works at the following facility:
Children and Youth Creative Centre, 22A Molodizhny Square, Dobropillia, Donetsk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows in the creative center facilities.
The current structural characteristics of the • Foundations are prefabricated blocks made of
creative center building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is soft, made of slate tiles;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of linoleum, wooden boards, and
ceramic tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The creative center building requires a series of actions
in order to ensure energy conservation. For instance,
replacing the existing wooden window frames with
more energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:

To replace existing wooden frame windows with
fiberglass reinforced plastic window panels, VEKA
type or similar. Also, to replace windowsills and
drip caps; to renovate window slopes:
Windows – 13 items / 88.2 m2, including:
0.9 x 5.4 m – 4 items/ 19.44 m2;
1.8 x 5.4 m – 4 items/ 38.88 m2;
1.8 x 1.2 m – 3 items/ 6.48 m2;
1.8 x 5.9 m – 1 items/ 10.62 m2;
1.8 x 7.1 m – 1 items/ 12.78 m2;
Doors – 1 item / 2.9 m2;
2.65 x 1.1 m – emergency exit doors, insulated,
with transoms


To dismantle security window grilles made of
steel:
- indoors – 3 items / 21 m2;
- outdoors – 6 items / 35 m2;
(window slopes up to 0.3 m; windowsills up 0.35
m; drip caps up to 0.15 m; install a 4-chamber
window profiles, and 2- or 1- chamber window
glass panels with energy-saving coating);
To take out and dispose of building waste.
Object №7
Technical specifications for carrying out construction and renovation works at the following facility:
Izmail Central Public Library for Adults name after I.P. Kotlyarevskogo, 41 Admiral Kholostyakov Street,
the city of Izmail, Odessa region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows in the library facilities.
The current structural characteristics of the • Foundations are prefabricated blocks made of
library building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is soft;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of linoleum, wooden boards, and
ceramic tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The library building requires a series of actions in order
to ensure energy conservation. For instance, replacing
the existing wooden window frames with more
energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:


To replace existing wooden frame windows with
fiberglass reinforced plastic window panels, VEKA
type or similar. Also, to replace windowsills and
drip caps; to renovate window slopes:
1.35 x 2.0 m – 11 items / 29.7 m2;
(window slopes up to 0.4 m; windowsills up 0.5 m;
drip caps up to 0.25 m; install a 4-chamber window
profiles, and 2- or 1- chamber window glass panels
with energy-saving coating);
To take out and dispose of building waste.
Object №8
Technical specifications for carrying out construction and renovation works at the following facility:
“Shulhynka House of Culture” (SHC), 12H Lenina Str., village Shulhynka, Starobilsk district, Luhansk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows and doors in the SHC facilities.
The current structural characteristics of the SHC • Foundations are prefabricated blocks made of
building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is soft, made of slate tiles;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of linoleum, wooden boards, and
ceramic tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The SHC building requires a series of actions in order
to ensure energy conservation. For instance, replacing
the existing wooden window frames and wooden
doors with more energy-efficient window and door
units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:
• To replace existing wooden frame windows and
exterior doors with fiberglass reinforced plastic
window panels and doors, VEKA type or similar.
Also, to replace windowsills and drip caps; to
renovate window slopes, including:
Windows – 30 items / 114.38 m2,
Including:
2.1 x 2.36 m – 12 items / 59.47 m2;
2.1 x 1.5 m – 5 items / 15.75 m2;
1.9 x 1.95 m – 7 items / 26.0 m2;
0.9 x 1.95 m – 1 item / 1.71 m2;
0.95 x 0.95 m – 2 items / 0.90 m2;
1.85 x 1.9 m – 3 items / 10.55 m2;
Doors – 2 items/ 7.49 m2;
2.1 x 1.55 m – 2 mm metal doors with insulation;
2.65 x 1.6 m – tambour door systems with
transoms; reinforced plastic;
(window slopes up to 0.45 m; windowsills up 0.5
m; drip caps up to 0.25 m; install a 4-chamber
window profiles and 2-chamber window glass
panels with energy-saving coating);
• To take out and dispose of building waste.
Object №9
Technical specifications for carrying out construction and renovation works at the following facility:
First Aid Obstetric Point, 4A Krasna Str., village Baidivka, Starobilsk district, Luhansk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows in the FAP facilities and to provide the heat insulation of cielings.
The current structural characteristics of the FAP • Foundations are blocks made of reinforced concrete;
building:
• Walls are wooden, cladded with brick;
• Structural slabs are wooden, reinforced with clay;
• Roof is soft;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of wooden panels.
• Walls are finished with plaster coated with latex
paint;
List of engineering systems currently installed in • A stove heating and gas heating systems are
the building:
installed;
• Ventilation is natural;
• Water supply system is local;
• Plumbing system is local;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The FAP building requires a series of actions in order to
ensure energy conservation. For instance, replacing
the existing wooden window frames with more
energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:

To replace existing wooden frame windows with
fiberglass reinforced plastic window panels,
VEKA type or similar. Also, to replace windowsills
and drip caps; to renovate window slopes (the
necessary information in order to make a
decision on the possibility of dismantling the
existing frames in wooden walls and
replacement of window sills need to be collected
from different sources in the city), including:
- 6 items /6.2 m2,
Including:
1.15 x 0.8 m – 5 items / 4.6 m2;
1.15 x 0.35 m – 1 item / 1.55 m2;
(window slopes up to 0.4 m; windowsills up 0.5
m; drip caps up to 0.25 m; install a 4-chamber


window profiles and 2- or 1- chamber window
glass panels with energy-saving coating);
To insulate the ceiling of the building from the
attic side with solid slabs made of 100 mm thick
mineral wool – 48 m2;
To take out and dispose of building waste.
Object №10
Technical specifications for carrying out construction and renovation works at the following facility:
Elementary School, 1B Krasna Str., village Baidivka, Starobilsk district, Luhansk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows and wooden floors in the school facilities.
The current structural characteristics of the • Foundations are prefabricated blocks made of
school building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is made of slate tiles;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of wooden panels;
• Walls are finished with plaster coated with latex
paint, and wallpaper.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is local;
• Plumbing system is local;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The school building requires a series of actions in order
to ensure energy conservation. For instance, replacing
the existing wooden window frames with more
energy-efficient window units.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:

To replace existing wooden frame windows with
fiberglass reinforced plastic window panels, VEKA
type or similar. Also, to replace windowsills and
drip caps; to renovate window slopes:
- 15 items /35.88 m2,
Including:
1.8 x 1.45 m – 5 items / 13.41 m2;
1.45 x 1.45 m – 5 items / 10.51 m2;
1.65 x 1.45 m – 5 items / 11.96 m2;
(window slopes up to 0.45 m; windowsills up 0.5
m; drip caps up to 0.25 m; install a 4-chamber
window profiles, and 2- or 1- chamber window
glass panels with energy-saving coating)


In three classrooms, to replace wooden hardboard
floor panels with new pine panels, 35 mm thick,
including replacement of replacement of floor
joists and painting baseboards. The classrooms
should be painted three times. Dimensions of the
classroom are as follows:
4.15 x 5.8 m;
4,4 x 3.95 m;
6.4 x 5.6 m.
To take out and dispose of building waste.
Object №11
Technical specifications for carrying out construction and renovation works at the following facility:
Children’s Polyclinic, 19А Studentska street, the town of Rubizhne, Luhansk region
These technical specifications include technical descriptions of services that need to be provided in order to
replace the existing wooden windows in the polyclinic facilities.
The current structural characteristics of the • Foundations are prefabricated blocks made of
polyclinic building:
reinforced concrete;
• Walls are made of brick;
• Structural slabs are prefabricated slabs made of
reinforced concrete;
• Roof is soft;
• Windows are reinforced plastic;
• Doors are reinforced plastic;
• Flooring is made of linoleum, mosaic, and ceramic
tiles.
• Walls are finished with plaster coated with latex
paint, and wallpaper; walls in bathrooms are finished
with oil paint and tiles.
List of engineering systems currently installed in • A central hot-water heating system is installed,
the building:
including their own boiler house;
• Ventilation is natural;
• Water supply system is connected to the existing
water grid;
• Plumbing system is connected to the existing grid;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The heating system requires replacements of rusty,
steel heating appliances.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:



To dismantle existing radiators, registers,
convection heaters– 63 items;
To buy and install new cast iron replacement
batteries MS-140-500 into 7 sections, with
Mayevsky valves, to attach them to existing
polypropylene pipes, to paint – 77 items;
To take out and dispose of building waste.
Object №12
Technical specifications for carrying out construction and renovation works at the following facility:
First-aid station (FAS), 2 Polyova Str., the village of Kolomyichykha, Svatove district, Luhansk region
These technical specifications include technical descriptions of a number of general construction services
that need to be provided in the first-aid station facility in the village of Kolomiychykha.
The current structural characteristics of the FAS • Foundations are blocks made of reinforced concrete
building:
strips;
• Walls are made of brick;
• Structural slabs are wooden;
• Roof is covered with slate tiles;
• Windows are wooden;
• Doors are wooden;
• Flooring is made of wooden panels.
• Walls are finished with plaster coated with latex and
oil paints, as well as wallpaper;
List of engineering systems currently installed in • A hot-water heating system, connected to the inthe building:
built gas boiler house. is installed;
• Ventilation is natural;
• Water supply system is connected to the existing
grid;
• Indoor plumbing system is non-existent;
• Energy supply system is connected to the existing
electricity grid;
• Communications system is connected to the existing
grid;
Brief description of the facility:
The facility is in operation. However, the roof is
leaking; the walls and ceiling have with minor cracks;
plaster on the walls is partially broken; the floor needs
to be renovated; electrical appliances are outdated;
indoor plumbing is non-existent, etc.
List of existing facilities and construction services works that need to be provided in accordance with
these technical specifications
General construction works:
To renovate the roof on the FAS building:
 To remove the old roof, made of asbestos and
cement sheets – 230 m2;
 To install a new roof, made of metal tiles or
profiled metal sheeting – 230 m2;
 To replace the wind boards on the gable windows
- 8 meters long;
 To paint wooden elements of the gable windows
and wind boards with oil paints twice -10 m2;
 To install sealing elements for roofing
connections and edges – 35 meters long;
 To install sealing elements where the roof is
adjacent to the gable windows – 9 meters long;
 To reinforce the entrance canopy with profiled
sheeting; to install the ceiling frame - 2.7 m2;
 To reinforce the entrance canopy with wind
boards, 20 cm wide – 3.5 meters long;
 To install roof drainage trays (gutters) Ǿ 125 mm
around the perimeter of the building – 52 meters
long;
 To install roof drainage funnels – 4 items;
 To install roof overflow pipes ø90 mm – 15
meters long;
 To take out and dispose of building waste.
To replace existing windows and entrance doors of the
FAS facility:
 To replace wooden entrance doors with
reinforced plastic metal doors – 2 items/ 4.4 m2
2.3 x 1.0 m, 2.1 x 1.10 m;
 To replace wooden windows, drains, windowsill
boards; to replace windowsills and drip caps; to
renovate window slopes (install a 4-chamber
window profiles and 2- or 1- chamber window
glass panels with energy-saving coating) - 23.4
m2 / 15 items;
1.5 x 1.1 m – 10 items;
0.75 x 1.0 m – 1 item;
1.1 x 0.8 m – 2 items;
1.35 x 1.85 m – 1 item;
1.15 x 1.65 m – 1 item;
 To renovate and paint existing internal window
slopes, 40 cm wide, insulating them with
Styrofoam – 60 meters long;
 To renovate existing external window slopes by
grouting, 15-20 cm wide – 75 meters long;
 To take out and dispose of building waste.