Specification Template - Main Roads Western Australia

advertisement
SPECIFICATION 705
OPTICAL FIBRE INSTALLATIONS
Copyright MAIN ROADS Western Australia
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 1 of 29
SPECIFICATION 705
OPTICAL FIBRE INSTALLATIONS
REVISION REGISTER
Date
Clause
Number
All
MAIN ROADS Western Australia
Contract xxx/xx
Description of Revision
Specification Created
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Authorised
By
MTMO/A
Page 2 of 29
CONTENTS
Clause
Page No
GENERAL ...................................................................................................................... 5
705.01
SCOPE................................................................................................................... 5
705.02
REFERENCES ......................................................................................................... 5
705.03
DEFINITIONS ........................................................................................................ 6
705.04 – 705.05 NOT USED ............................................................................................................ 8
PRODUCT AND MATERIALS ....................................................................................... 8
705.06
GENERAL .............................................................................................................. 8
705.07 – 705.10 NOT USED ............................................................................................................ 9
DESIGN REQUIREMENTS ............................................................................................ 9
705.11
GENERAL .............................................................................................................. 9
705.12
MAINTENANCE CONSIDERATIONS....................................................................... 9
705.13
CONDUIT / DUCT SELECTION ............................................................................. 10
705.14
ROUTE SELECTION ............................................................................................. 10
705.15
SUBDUCTING ..................................................................................................... 10
705.16 – 705.20 NOT USED .......................................................................................................... 11
CABLE INSTALLATION REQUIREMENTS ................................................................. 11
705.21
GENERAL ............................................................................................................ 11
705.22
CONDUIT / DUCT CLEANING .............................................................................. 12
705.23
CABLE HAULING EQUIPMENT ............................................................................ 12
705.24
HAULING EYES.................................................................................................... 12
705.25
ROPES FOR HAULING OPTICAL FIBRE CABLES ................................................... 12
705.26
CABLE CRUSH AND BEND RADII ......................................................................... 13
705.27
INSTALLATION OF NEW CABLES IN OCCUPIED CONDUIT / DUCTS .................... 13
705.28
HAULING – CARE OF EXISTING PLANT ............................................................... 14
705.29 – 705.30 NOT USED .......................................................................................................... 14
CLOSURE / FOBOT INSTALLATION REQUIREMENTS ............................................ 14
705.31
GENERAL ............................................................................................................ 14
705.32
CABLE IDENTIFICATION AND LABELLING REQUIREMENTS ................................ 15
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 3 of 29
705.33
UNDERGROUND SPLICE CLOSURES ................................................................... 16
705.34
FOBOTS AND PATCH PANELS ............................................................................. 18
705.35
OTHER FOBOTS .................................................................................................. 19
705.36
PATCH CORDS AND LEADS ................................................................................. 19
705.37 – 705.40 NOT USED .......................................................................................................... 20
TESTING AND ACCEPTANCE CRITERIA .................................................................. 20
705.41
CABLE ACCEPTANCE........................................................................................... 20
705.42
OTDR LINK LOSS ................................................................................................. 20
705.43
IRREGULARITY CHECK ........................................................................................ 21
705.44
SPLICE LOSS / LOCATION ................................................................................... 21
705.45
LSPM INSTERTION LOSS ..................................................................................... 21
705.46
PRE-TERMINATED CONNECTOR LOSS................................................................ 22
705.47
COMMISSIONING ACCEPTANCE TEST RESULTS ................................................. 22
705.48
EQUIPMENT ACCEPTANCE AND COMMISSIONING ........................................... 23
705.49
INSPECTION AND TEST PLAN ............................................................................. 23
705.50
TESTING SEQUENCE ........................................................................................... 24
705.51 – 705.55 NOT USED .......................................................................................................... 26
AS BUILT AND HANDOVER REQUIREMENTS.......................................................... 26
705.56
AS-BUILT INFORMATION.................................................................................... 26
705.57 – 705.60 NOT USED .......................................................................................................... 26
CONTRACT SPECIFIC REQUIREMENTS................................................................... 26
705.61 – 705.70 NOT USED .......................................................................................................... 26
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 4 of 29
SPECIFICATION 705
OPTICAL FIBRE INSTALLATIONS
GENERAL
705.01
SCOPE
1.
The work under this specification consists of design, supply, installation,
testing and commissioning, documentation and handover requirements of Main Roads
WA Optical Fibre installations.
705.02
REFERENCES
1.
Australian Standards, MAIN ROADS Western Australia Standards and MAIN
ROADS Western Australia Test Methods are referred to in abbreviated form (e.g. AS 1234,
MRS 67-08-43 or WA 123). For convenience, the full titles are given below:
Australian/New Zealand Standards
AS/NZS ISO/IEC 14763.3
Telecommunications Installations – Implementation and
operation of customer premises cabling. Part 3: Testing of
Optical Fibre Cabling (ISO/IEC 14763.3:2011 MOD)
AS/ACIF S009:2013
Installation requirements for customer cabling (Wiring
rules)
AS/NZS 2967:2010
Optical Fibre communication cabling systems safety.
AS/NZS IEC 60825.2
Safety of laser products – Safety of Optical Fibre
Communication Systems (OFCS)
AS/NZS 3084:2003
Telecommunications installation generic cabling for
commercial premises;
AS/NZS 3000
AS/NZS 4251.1
AS 4006-1992
AS 4100
Electrical Installations - Wiring Rules
Electromagnetic Compatibility (EMC), Generic Emission
Standards – Residential, Commercial and Light Industry
Software Test Documentation
Steel Structures
AS/NZS CISPR 22
Information Technology Equipment Radio Disturbance
Characteristics - Limits and Methods of Measurement
AS/NZS ISO 9002
Quality Systems - Model for Quality Assurance in
Production, Installation and Servicing
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 5 of 29
AS/NZS 1768
Lightning Protection
Other Standards
ITU-T G652
Characteristics of a Single-mode Optical Fibre and Cable;
Table4G.652.D Attributes.
IEC 60793-1
Optical Fibres – Measurement Methods and Test
IEC 60793-2-50
Optical Fibres – Product Specifications – Sectional
Specifications for Class B single-mode Fibre.
IEC 60794-3
Optical Fibres – Product Specifications – Outdoor Cable.
MAIN ROADS Specifications
Specification 704
705.03
Cable Conduit for Intelligent Transport Systems
DEFINITIONS
1.
Applicable terms and definitions, in addition to those in Main Roads Glossary
of Terms, are listed below:
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 6 of 29
ACMA
Australian Communications & Media Authority
AMTS
Asset Manager Traffic Systems
ELV
Extra Low Voltage (As defined in AS/NZS 3000:2007)
FIST
Fibre Infrastructure System Technology
FOBOT
Fibre Optic Break Out Tray
FRP
Fibre Reinforced Plastic
ITP
Inspection and Test Procedure
ITS
Intelligent Transport Systems
LSPM
Light Source and Power Meter
MBR
Minimum Bend Radius
NATA
National Association of Testing Authorities
OD
Outside Diameter
OTDR
Optical Time Domain Reflectometer
SMOF
Single Mode Optical Fibre
SZ
Reversed Helical Stranding
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 7 of 29
TCS
Traffic Control System
TOC
Traffic Operations Centre
Backbone
Refers to the Optical Fibre Cable that provides communication connections
between ITS Node Cabinets and / or ITS Communications Cabins to TOC, as well as
communication connections via Branch Cables from ITS Field Cabinets to ITS Node
Cabinets, ITS Communications Cabins and TOC, generally 96 Fibre Cables and greater.
Branch Cable
To describe an Optical Fibre Cable from an Underground Splice Closure or
FOBOT to an ITS Field Cabinet, ITS Node Cabinet, ITS Communications Cabinet or a Link
Cable between Splice Closures, generally from 6 up to 48 Fibre Cables
External Loose Tube Cable
A cable that contains Optical Fibres in loose tubes. Generally, these tubes are
laid up with "SZ" stranding (reversed helical stranding) around the Fibre Reinforced Plastic
(FRP) central strength member for ease of mid span access jointing. Cables generally
consist of 12 fibres per loose tube and where required filler tubes.
705.04 – 705.05
NOT USED
PRODUCT AND MATERIALS
705.06
GENERAL
1.
All Optical Fibre Cables shall be External Loose Tube SMOF
type unless otherwise specified.
Loose Tube
2.
All Pigtails and Patch cord / leads shall be SMOF type unless
otherwise specified.
SMOF
3.
All Pits, Conduits, Optical Fibre Cable and equipment shall:
Specification
704
a)
Comply with MRWA Specification 704 Cable Conduits & Pits
for ITS, and
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 8 of 29
b)
Meet all functional requirements when installed at the
specified locations.
4.
Comply with applicable Australian Standards, or the
appropriate International Standard.
705.07 – 705.10
Australian
Standards
NOT USED
DESIGN REQUIREMENTS
705.11
GENERAL
1.
This section provides supporting information to be taken into
consideration when undertaking the design of the optical fibre system. It aims to
ensure that new fibre routes make best use of existing and new infrastructure to
maintain the integrity of new cables.
2.
For Optical Fibre Backbone Cable installations a minimum 30.0m of
cable shall be stored / coiled in C8 pits no greater than 1,000m apart for future
installation requirements.
Longitudinal
Spare Cable
3.
For Optical Fibre Cables to be entered into an Underground Splice
Closure a minimum 15.0m plus 3.0m of cable for jointing requirements shall be
provided.
Underground
Enclosure
Spare
4.
For Optical Fibre Cables to be entered into a FOBOT a minimum
15.0m of cable shall be stored / coiled in the nearest adjacent pit plus a minimum
3.0m of cable for splicing requirements shall be provided.
FOBOT Spare
5.
For Optical Fibre Cables in each change of direction pit (road crossing
etc.) a minimum of 6.0m of cable shall be stored / coiled in each change of
direction pit.
Change of
Direction
6.
Optical Fibre Backbone Cables shall contain a minimum 120 Fibres.
To extend an existing Backbone Cable, written approval is required from the
MRWA AMTS for the installation of a new Optical Fibre Backbone Cable that has
less than 120 Fibres but the same amount, or greater, fibre cores as the existing
Optical Fibre Backbone Cable.
Backbone Size
7.
Optical Fibre Branch Cables, the design shall include sufficient
capacity so that no more than 50% of the new Optical Fibre Cable cores
shall be used at commissioning.
Branch Size
8.
Field Cabinet, Cable Asset Numbering, Fibre Cores, Switch
Ports and IP Addressing shall be allocated by the MRWA AMTS or MRWA
AMTS nominated representative using the appropriate allocation request
form.
Allocation
Requests
705.12
MAINTENANCE CONSIDERATIONS
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 9 of 29
1.
The following shall be strictly in accordance with this standard;
a)
Route design,
b)
Route marking, (i.e. marker posts and detectable warning
tape),
705.13
c)
Route reinstatement,
d)
Cable type selection, and
e)
Asset Documentation.
CONDUIT / DUCT SELECTION
1.
To minimise the risk of damage to Optical Fibre cables from hauling
cables or removing cables, the following guidelines shall be used in descending
order of preference, for selecting a conduit.
a)
Order of
Preference
Choose a conduit occupied by only Optical Fibre cables.
b)
Choose a conduit occupied by Optical Fibre or copper
communications cables.
c)
705.14
Choose a vacant conduit.
ROUTE SELECTION
1.
When selecting a conduit from a nest of conduits, or from a different
route, mixing Backbone, Feeder / Tie Cables and sub-duct in one conduit shall be
avoided.
2.
The route with the lowest run of conduits shall be selected.
3.
Where there is a choice in alternative conduit routes, the following
guidelines, in order of preference, shall be used for selecting the conduit run for
the installation of an optical fibre cable. The route selected shall have:
705.15
a)
The greatest depth of cover
b)
The shortest distance
Shared Conduit
Lowest Run
Route
Preferences
SUBDUCTING
1.
Subducting as part of Optical Fibre cable installation is not the
standard practice for MRWA Fibre network. Subducting shall only be used after
receiving written approval from the MRWA AMTS or MRWA AMTS nominated
representative to do so.
Approval for
Subducting
2.
When approved, subducting shall only be used in the following
situations:
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 10 of 29
a)
Significant changes in levels, potential damage to the cable
within the pit or duct entry or for security issues
b)
There are no non-subducted Optical Fibre already installed in
the duct
c)
Where approval has been granted for other Government
Departments or Telecommunications carriers to install cables in
MRWA ITS pits and/or conduit.
d)
Significant changes in levels, potential damage to the cable
within the pit of duct entry for security reasons.
e)
There is no non-subducted Optical Fibre already installed in
the duct
3.
Only one Optical Fibre cable shall be installed in an empty sub-duct,
and under no circumstances shall a second cable of any type be drawn into the
same sub- duct, or into any other occupied subduct i.e. overhauling of cables in
sub-duct is not permitted. Subduct shall be white or grey in colour and be clearly
labelled as per Clauses705.32.02 - Splice Closures, FOBOT’s and Cabinet Labelling,
and 705.32.03 - Optical Fibre Hauling and Intermediate Pits Cable Labelling.
705.15.01
Sub Duct
Labelling
FLEXIBLE SECONDARY PROTECTION
1.
Where sub-duct is unsuitable, but the above concerns are present
then flexible conduit shall be installed. Two types of flexible conduit are currently
approved for use within the MRWA TCS Network:
a)
Pipe, Agflow, 50 mm
b)
Conduit, PVC Corrugated White, 25mm
705.16 – 705.20
Flexible
Secondary
Protection
NOT USED
CABLE INSTALLATION REQUIREMENTS
705.21
GENERAL
1.
All external Optical Fibre Loose Tube cables shall:
a)
Loose Tube Fibre
be of dielectric construction (i.e. Non- metallic),
b)
Include a Fibre Reinforced Plastic (FRP) central strength
member,
c)
be water blocked without the use of petroleum based jelly
filling compound to prevent the ingress of water and other
impurities,
d)
Have a blue outer nylon jacket, and
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 11 of 29
e)
Be sheath marked containing the cable information every
1.0m.
2.
Have both the metre mark readings at each end and the Serial / Item
code on the cable sheath recorded at time of installation and submitted with As
Built drawings.
3.
All cables shall be labelled as shown in Clause 705.32 Cable
Identification and Labelling Requirements.
705.22
Cable Labels
CONDUIT / DUCT CLEANING
1.
Before cable installation, conduits / ducts shall be clean and free
from obstructions.
705.23
1.
Metre Markings
Duct Cleaning
CABLE HAULING EQUIPMENT
Only NATA certified cable hauling equipment is to be used.
2.
A winch calibrated to 2kN shall be used for all cables. For cables with
a hauling tension of 2 kN or greater, a winch must be used. It shall be equipped
with a tension monitor and an automatic shutdown device calibrated and locked
to operate when a pre-set maximum tension of 2 kN is reached, thereby stopping
the haul and not exceeding the maximum hauling tension.
NATA
Certification
Hauling Tension
3.
For cables with a maximum hauling tension less than 2 kN, an
approved fusible link with a breaking force less than the stated requirement, as
measured by a NATA certified laboratory, shall be used, providing approval has
been obtained from the Principal. (A copy of the certification for the fuse type
shall be provided with the commissioning and hand over documents).
705.24
HAULING EYES
1.
The minimum tensile rating of all hauling eyes shall be equal to 1.5
times the cable tensile rating.
Hauling Eyes
Rating
2.
If hauling eyes are not fitted and wire grips are used, extreme care
must be taken to avoid cable damage and stripping of the sheath by attaching the
correct sized grip in a proper manner. On completion of the haul at least 2 m of
cable should be removed from the cable end fitted with the wire grip.
705.25
ROPES FOR HAULING OPTICAL FIBRE CABLES
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 12 of 29
1.
Only Kevlar/Spectra braided rope shall be used for mechanical
hauling of Optical Fibre cable. This rope must be manufactured with a braided
core of Kevlar/Spectra fibre cordage, and braided polyester cover, and have an
outside diameter of not less than 8 mm.
Mechanical
Hauling Rope
2.
The Kevlar/Spectra braided hauling rope shall be at least of sufficient
length to always extend between the cable end and the winch with the
immediate cable load.
Haul Rope Length
3.
Where more than one winch is being used on a haul, the rope
between winches and without the immediate cable load, shall be of an approved
type other than the Kevlar/Spectra type hauling rope connected to the cable, e.g.
double braid hauling rope. The connection between the hauling ropes must be
able to withstand a load in excess of 2 kN, and must provide a smooth profile to
avoid any damage to existing cable(s) or ducts.
Multiple Winches
4.
For mechanically drawing in hauling ropes, approved hauling rope
shall be used, e.g. double braided hauling rope.
5.
Polypropylene rope shall not be used for mechanically hauling optical
fibre cable or hauling ropes. It may be used for manual hauling, e.g. over short
sections, for Feeder Cables, and cabling within buildings.
705.26
Mechanical
Drawing
Polypropylene
Rope
CABLE CRUSH AND BEND RADII
1.
Suitable installation equipment such as cable guides, slippers and
wheels (capstan) shall be used so that the dynamic and static bending and crush
performance requirements are complied with.
Bending and
Crushing
Requirements
2.
Cable rollers systems shall be of such design not to exceed the
minimum bending radii (MBR) and crush performance of cables.
Cable Rollers
3.
When housing cables the MBR and Minimum Outside Loop
dimensions, must not be exceeded. Minimum Outside Loop (L) = MBRx2 + 2 x OD.
705.27
Minimum Outside
Loop
INSTALLATION OF NEW CABLES IN OCCUPIED CONDUIT
/ DUCTS
1.
The conduit must be proven with a suitable mandrel prior to
attempting any hauling. As a guide where the conduit capacity is questionable
(e.g. the aggregated existing plus new cable/subduct diameters exceeds 80% of
the internal diameter of the conduit) the conduit must be proven with a suitable
mandrel 1.5 times the size of the cable. If this is successful and it can be
reasonably assumed there will be no damage to any cables, subducts or
infrastructure, the haul can proceed.
Conduit Proving
2.
If at any stage the proving of the conduit becomes difficult or the
conduit cannot be proven and there is a possibility of cable damage, the conduit
Conduit
Upgrading
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 13 of 29
must be upgraded
3.
Once all sections of the proposed haul have been proven the hauling
tensions and lay off points ,if required, shall be determined
4.
Pressure roping shall be used in preference to hand rodding, to
minimise the possibility of intertwining of cables during hauling.
5.
A water based cable lubricant that is Non-Toxic, Non-Flammable and
compatible with all types of cable sheath shall be used, on the cables, rope and
mandrel when hauling over existing cables.
Lay off Points
Pressure Roping
Lubricant
6.
Existing optical fibre cables shall be restrained from moving in the
same direction as the haul.
7.
During the haul supervision shall be provided at entry, exit and
change of direction locations.
705.28
HAULING – CARE OF EXISTING PLANT
1.
The existing MRWA TCS Network must be cared for at all times and
not interfered with during the course of proving conduits, the installation of rope
and/or additional cable.
Existing Network
2.
If the existing cables and/or closures need to be moved during work
tasks, they are to be handled carefully, suitably restrained and replaced correctly
in the pit on completion of the task.
3.
Avoid lacing the rope through existing cable loops, as this will cause
undue pressure to be inserted upon the cables and joints.
4.
Care must be taken to ensure existing cables, identification tags,
joints or other plant are not caught up with and dragged by the hauling rope or
cable being installed.
5.
Existing cables or subduct shall be constantly observed for
movement (through dragging). If there are any significant signs of cable
gathering, or of cable or subduct movement at any location along the route, the
haul shall stop immediately, and action taken e.g. reapply lubricants, restraint to
prevent further movement /dragging of the cable(s) or subduct, before
recommencing the haul.
705.29 – 705.30
NOT USED
CLOSURE / FOBOT INSTALLATION REQUIREMENTS
705.31
GENERAL
1.
Only a recognized Industry / Network Carrier accredited & ACMA
licensed technician shall install any Splicing Joint Closures and FOBOTs. The
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Accreditation
Page 14 of 29
accredited / licensed technician shall have a minimum of 4 year experience in the
Jointing, Splicing, Testing and installation of Optical Fibre cables and associated
equipment.
2.
All cable installation work shall be in accordance with the design
documentation and to a standard that will not unduly shorten the life expectancy
of any of the components.
Life Expectancy
3.
All cables shall be installed in accordance with the design to
facilitate unencumbered maintenance of the modules contained within it.
4.
All installation works shall be coordinated with adjacent works of
any description to ensure cables are installed without damage or are not affected
in any way by the adjacent works activity.
Adjacent Works
5.
If any of the proposed cable works or alterations is not in agreement
with the existing plans, the MRWA AMTS or MRWA AMTS nominated
representative shall be contacted so the problem can be resolved prior to the
commencement of the work. Any active services must be noted. Particular care
must be taken where active Fibre Links to Core, Distribution & Access Switches
are present on the cable as outages on these systems may affect a significant
number of MRWA ITS Asset’s. It is important that identification is carried out at
both ends of a cable to confirm that no unrecorded fibre transpositions or cable
alterations have been made.
Active Services
6.
Prior to commencing work on any live cable, or fibres, a full set of up
to date plans and records must be available, documentation must be forwarded
to the MRWA AMTS for approval 14 days prior to the work commencing, stating
job / project number, location, proposed date & time, expected duration of
outage if any, services affected. Written approval must have been received from
MRWA AMTS prior to carrying out the work described. MRWA TOC must be
notified prior to and on completion of the work described.
Work Notification
7.
All Splicing Joint Closures / FOBOT’s shall be installed in accordance
with the manufacturer’s recommendations.
Manufacturer’s
Recommendation
8.
All Splicing Joint Closure / FOBOT manufacturers specified minimum
bend radius shall not be exceeded.
Minimum Bend
Radius
705.32
CABLE IDENTIFICATION AND LABELLING
REQUIREMENTS
705.32.01
GENERAL
1.
Cable labelling shall consist of rectangular white PVC tag (66mm x
25mm x 2mm).
2.
The details of the cable shall be clearly printed in block letters and
numbers between the ridges of the tag with a permanent black marking pen.
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 15 of 29
3
The tags shall be secured to the cable using PVC cable ties, with the
excess cable tie trimmed off.
705.32.02
SPLICE ENCLOUSRE, FOBOT AND CABINET CABLE LABELLING
1
All cables shall be clearly marked and identified 300mm below all
Splice Closures, 100mm from FOBOT entry and 100mm above the base of
Cabinets.
Cable in Closure
Markings
2.
The tags are to contain the following information as per example
Figure 705.1:
a)
Top line: (Cable size),
b)
Middle line: (MRWA Cable Asset Number), and
c)
Bottom line: (MRWA Asset Number of where the cable
originates).
96F
FC0123
SPL0360
Figure 705.1
705.32.03
OPTICAL FIBRE HAULING AND INTERMEDIATE PITS CABLE LABELLING
1.
All cables shall be clearly marked and identified in all Haul and
intermediate pits, the tag shall be located on the centre of the cable between
each pit entry.
Cable in Pit
Markings
2.
The tags are to contain the following information as per example
Figure 705.2:
a)
Top line: (Cable size),
b)
Middle line: (MRWA Cable Asset Number), and
c)
Bottom line: (MRWA Asset Numbers of where the cable
originates & terminates).
96F
FC0123
SPL0360 - CAB003
Figure 705.2
705.33
UNDERGROUND SPLICE CLOSURES
1.
Underground Splice Closures shall have prior approval for use by the
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Approvals
Page 16 of 29
MRWA AMTS or MRWA AMTS nominated representative.
2.
Underground Splice Closures shall be manufactured and be designed
for external use.
External Use
3.
Product specification data sheets shall be provided to MRWA AMTS
prior to approval.
Specification
Datasheets
4
Underground Splice Closures shall be tested for Mechanical,
Electrical and Environmental performances adequate for the use in the intended
environment.
Performance
Testing
5.
The minimum bend radius, as specified by the manufacturer, of the
optical fibre cable shall not be exceeded throughout the closure system under all
normal conditions of use.
Bend Radii
6.
Underground Splice Closures shall be designed so as no specialised
tools or equipment are required to both open and to seal, and be
environmentally proofed to IP 68 rating when sealed.
IP Rating
7.
The packaging shall be designed to ensure that the Underground
Splice Closure and associated materials are not damaged under normal shipping
and handling. Equipment shall be inspected prior to installation and shall not be
used if damage is evident.
Closure Damage
8.
Metal components shall be resistant and/or protected against
general corrosion and various forms of local corrosion (stress corrosion cracking,
pitting, etc.).
Corrosion
Protection
9.
Underground Splice Closures shall be capable of accepting an
industry-wide range of cable sizes and unit configurations. The housing shall be
capable of accepting cable designs of either loose tube, blown or slotted fibre
cables.
Cable Size and
Configuration
10.
Underground Splice Closures shall be capable of accommodating
splice tray organisers, which accept fusion type optical fibre splices. The splice
closure shall have provisions for storing fibre splices in an orderly manner,
mountings for splice organiser assemblies and space for excess or unspliced fibre.
Splice organisers shall be re-enterable.
Splice Tray
Organisers
11.
Heat shrinkable Splice Protectors with a length of 40mm to be used
unless otherwise specified.
Splice Protectors
12.
Underground Splice Closures shall be capable of accommodating and
terminating the strength members of all cables entered into enclosure.
13.
Each individual Fibre Cable entered into the Underground Splice
Closure shall be secured to the strength member fixation point/s.
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Strength
Members
Fixation Points
Page 17 of 29
14.
Underground Splice Closure re-entry and subsequent re-assembly
shall not require specialised tools or equipment. Further, these operations shall
not require the use of additional parts, other than seals and or heat shrinks.
Closure
Re-entry
15.
Underground Splice Closures and all cables entered into the closure
shall be installed as per the manufactures specifications and installation
guidelines.
705.34
FOBOTS AND PATCH PANELS
1
All Optical Fibre cables to be terminated within FOBOT(s) shall
have a front accessible patch panel.
Patch Panel
2.
FOBOT’s shall be 19” rack mountable, with provision of up to
minimum of 24 Ports and have a front sliding tray access unless otherwise
specified.
19” Rack
Mountable
3
All FOBOTs shall have front patching facilities.
4.
All FOBOTs in the same cabinet shall be of the same make.
Patching Facilities
5.
All FOBOTs shall be capable of accommodating and terminating the
strength members of all cables entered into the FOBOTs.
Strength
Members
6.
Each individual Fibre Cable entered into the FOBOT shall be secured
to the strength member fixation point/s.
Fixation Points
7.
Rubber cable boot / Cable Gland shall be used where cable enters
the FOBOT.
Cable Glands
8.
Sufficient internal capacity shall be provided for the orderly storage
of a minimum one metre length of each fibre end prior to splicing.
Spare Cable
Storage
9.
Each bundle of unsheathed fibres shall be sleeved in PVC tubing.
10.
rings.
All fibre coils shall be wound through internal cable management
Management
Rings
11.
All pigtails shall be PVC sheathed with factory terminated SC
connectors arranged to mate with the SC through adapters / connectors, unless
otherwise specified.
SC Connectors
12.
Connector loss max 0.50db per mated through adapters / connector.
Connector Loss
13.
rings.
All pigtails shall be wound through the internal cable management
14.
All FOBOT’s shall have Duplex SC through adapters / connectors
fitted, unless otherwise specified.
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 18 of 29
15.
Any unused through adapter / connector mounting positions shall be
covered with manufacturers blanking plates.
16.
Blanking Plates
One splicing tray / cassette shall be used for each fibre tube.
17.
Storage of spliced fibres shall only be allowed with no degradation of
either the transmission quality or the fibre itself.
18.
No fibres shall exceed the manufacturer’s specified minimum
bending radius.
Bend Radii
19.
Easy access and removal of individual splice protectors shall be
provided for future rearrangement or maintenance purposes, without disturbing
adjacent fibres.
20.
Heat shrinkable Splice Protectors with a length of 40mm shall be
used unless otherwise specified.
21.
The FOBOT patching ports shall be labelled in order to identify each
fibre that is terminated on the front of the FOBOT.
22.
AMTS.
FOBOT product specification datasheet shall be provided to MRWA
705.35
OTHER FOBOTS
1.
Where 19” rack mountable FOBOT cannot be installed due to Cabinet
capacity, all Optical Fibre cable/s ends shall be terminated on a DIN rail mounted
FOBOT/s which shall provide sufficient ports for termination of at least 6 fibres
and pigtails per fibre cable.
705.36
PATCH CORDS AND LEADS
705.36.01
PATCH CORD AND LEAD LENGTH
1.
All Patch cord / Leads shall have a minimum 1.0m additional length
for storage.
705.36.02
Labelling
Datasheets
DIN Rail
Mounting
Lead Length
PATCH CORD AND LEAD MANAGEMENT
1.
19” rack mountable cable management rails shall be provided above
and below each FOBOT installed in Node Cabinets and SCATS Cabins.
705.36.03
Splice Protectors
Lead
Management
PATCH CORD AND LEAD STORAGE
1.
A 19” rack mountable, front sliding tray Patch cord / leads
Management Tray shall be installed below the lowest FOBOT. Additional Storage
Management Trays shall be installed if specified on design drawings.
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Lead Storage
Page 19 of 29
2.
Patch cords / leads to or from FOBOT (s) shall enter the left hand side
of the Storage Management Trays.
3
Patch cords / leads to or from Communications Equipment shall
enter the right hand side of the Storage Management Trays.
705.37 – 705.40
NOT USED
TESTING AND ACCEPTANCE CRITERIA
705.41
CABLE ACCEPTANCE
1.
Cable Acceptance shall follow the completion of installation of the
end-to-end Optical Fibre link as specified in AS/NZS ISO/IEC 14763.3:2012
Telecommunications installations – Implementation and operation of customer
premises cabling. Part 3: Testing of Optical Fibre Cabling (ISO/IEC 14763.3:2011
MOD).
705.42
AS/NZS ISO/IEC
14763.3
OTDR LINK LOSS
1.
All OTDR Fibre test results shall be recorded and saved with the
correctly assigned MRWA Asset numbers used to describe End A / End B with
cursors correctly aligned.
OTDR Tests
2.
All fibres are to be tested utilising two-way OTDR Link Loss (LL)
measurements. The measurements shall also be carried out on spare fibres within
the cable that either terminate at one end only or are provided between
joint/splice locations.
Two-way
Measurement
3.
An OTDR Link Loss (LL) measurement shall be performed on all fibres
to confirm the integrity of the cable link excluding the performance of the preterminated connector.
Fibre Integrity
1. 4.
On terminated fibres the link loss tests shall be performed after
termination of connector, which would then include the connector loss being
factored in the LL data recording. The link loss shall be tested and recorded in
both directions at wavelengths 1550nm utilising the OTDR (Two-point method i.e.
position the first cursor just beyond the front end attenuation saturation dead
zone where the trace is linear and position the second cursor at the end of the
trace just before the trace begins to rise). The two-way (average) link loss (LL) for
a fibre shall be calculated as the average of the measurements. The two-way
(average) OTDR LL shall not exceed the following:
Link Loss Test
2. Maximum Loss at 1550 nm (LL) = 0.3L + 0.1N + 0.5, where:
Maximum Link
Loss
a)
LL = Maximum allowable Link Loss in dB
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 20 of 29
b)
L = the optical link length in Km
c)
N = number of splices
5.
If a fibre fails the OTDR Link Loss after a number of remeasurements, then a more comprehensive evaluation of the fibre link should be
undertaken to determine the high loss i.e. re-check of any irregularities, splice
losses and fibre attenuation co-efficient (dB/km).
705.43
IRREGULARITY CHECK
1.
All fibres in each section length shall be checked for any irregularities
in both directions at wavelengths of 1310nm and 1550nm. The magnitude of
irregularities (point losses) in length shall be calculated as the average of the
irregularity loss measured in both directions at wavelengths of 1310nm and
1550nm. Irregularities shall not exceed 0.10dB (two way average) for any
wavelength.
2.
The magnitude and distance from each fibre end to an irregularity
shall be recorded on a fibre anomaly sheet to be included in the final report.
3.
Any point loss that exceeds the above criteria shall be rectified with
the fibre subsequently retested.
705.44
Test Failure
Test Wavelengths
Irregularity
Locations
Check Failure
SPLICE LOSS / LOCATION
1.
These measurements shall be undertaken for the purpose of
ensuring the integrity and quality of splice performance and identifying and
documenting optical fibre cable distances to all splice locations to assist in the
future location of faults.
Splice Loss
2.
The optical distance and magnitude of all splices shall be measured
from both directions at wavelengths of 1310nm and 1550nm. The loss of any
splice shall not exceed 0.10dB (two way average) at 1310nm and 1550nm.
Test Wavelengths
3.
Any splice loss that exceeds the above criteria shall be re-spliced. If
the splice does not improve after two attempts at resplicing and OTDR testing
confirms that the splice loss is not consistent with a high point loss within the
splice enclosure then the splice shall be accepted but reported as a high splice
loss. All splice loss/joint measurements shall be recorded and any reported high
splice loss value shall be appropriately marked and reported.
Excessive Splice
Loss
705.45
LSPM INSTERTION LOSS
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 21 of 29
1.
This measurement shall be undertaken on terminated fibres to verify
the overall end-to-end power budget level of the entire fibre link. The Insertion
Loss (IL) for each fibre shall be measured in both directions using a stabilised
LSPM.
Insertion Loss
2.
These results shall be compared with predictions based on the
manufacturer’s SMOF geometrical properties and minimum splice loss criteria.
3.
The maximum two-way (average) Insertion Loss shall not exceed the
following criteria:
a)
Maximum Loss at 1310nm (IL) = 0.4L + 0.1N + 0.50C + 0.5
b)
Maximum Loss at 1550nm (IL) = 0.3L + 0.1N + 0.50C + 0.5
Maximum
Insertion Loss
Where;
a)
IL = Maximum allowable Insertion Loss in dB,
b)
L = optical section link Length in km,
c)
and
N = Number of splices including pre-terminated connector,
d)
C = total number of through Connectors.
4.
If a fibre exceeds the acceptance criteria then the insertion loss value
shall be appropriately marked (e.g. circled, highlighted, etc.).
705.46
Excessive Insertion
Loss
PRE-TERMINATED CONNECTOR LOSS
1.
This calculation is performed to verify the overall performance of the
individual connector / pigtail combination situated at either end of the optical
fibre link.
2.
For each fibre the delta between the maximum Insertion Loss
(average IL).
3.
LSPM Insertion Loss (Clause 705.47) less the OTDR average Link Loss
(LL) (Clause 705.42) shall not exceed 1.0dB. Results for all fibre shall be calculated
and recorded.
4
If the 1.0dB limit is exceeded for any fibre then a more
comprehensive evaluation of the individual pre-terminated connector at both
ends will need to be undertaken to determine the high loss (i.e. investigate the
launch conditions of each pre-terminated connector using OTDR in high
resolution mode.
705.47
COMMISSIONING ACCEPTANCE TEST RESULTS
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 22 of 29
1.
All OTDR Fibre test results shall be recorded and submitted in both
original Trace Format and pdf. Original Trace Format in soft copy (electronically)
with original Trace Format reader and all tested Fibres Trace results, pdf’s in both
hard and soft copies (electronically).
Submission
2.
All LL & IL measurements and calculations shall be recorded and
submitted on completion in both hard and soft copies (electronically). Test result
shall be compiled on an EXCEL spread sheet with the correct values entered in the
required cells.
a)
Insertion loss results - Insertion loss measurement Two-way
and average Insertion Loss results shall be recorded.
b)
Connector/Pigtail performance results – Calculated and shall
be recorded and incorporated along with the tabulated Insertion
Loss results above.
3.
Any issues and steps taken to correct shall be recorded.
4.
All faulty links found during testing shall be replaced in their entirety.
No lengths of damaged or suspect cable or components shall be left in the
system. Cable damaged during installation shall not be reused. All retest and
cable replacement costs where necessary shall be borne by the Contactor.
705.48
Corrections
Faulty Links
EQUIPMENT ACCEPTANCE AND COMMISSIONING
1.
Factory Certification shall be provided for all Optical Fibre equipment
to be supplied and installed and shall be tested in the Supplier’s factory. The
Contractor shall provide a factory quality control testing certificate for all supplied
Optical Fibre equipment, to the MRWA AMTS nominated representative.
2.
Site Acceptance Testing shall demonstrate the compliance of the
Fibre installation after all works have been completed.
3.
The Contractor shall supply all labour, materials and equipment
required to fully test and commission the installation. Commissioning/Acceptance
Testing shall be carried out in the presence of the MRWA nominated
representative. MRWA shall be notified of testing 72 hours in advance of testing
to allow for MRWA AMTS nominated representative to be present at testing.
Factory
Certification
Site Acceptance
Commissioning
4.
Installation and/or equipment will be accepted only after satisfactory
completion of commissioning tests. If a test is unsuccessful the equipment shall
be repaired and re- installed as appropriate and subject to retest until successful.
5.
The cost of any retesting if necessary shall be borne by the
Contractor.
705.49
Retesting Costs
INSPECTION AND TEST PLAN
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 23 of 29
705.49.01 GENERAL
1.
In addition to the Contractor’s own Quality Assurance requirements
the Contractor shall provide a complete ITP. The ITP shall include test schedules
designed to incorporate the following information:
Quality Assurance
a)
Name of Test and its status - original test or repeat (due to a
previous test failure), date, time and location of the test;
b)
Record of all values measured during
installation/commissioning;
c)
List of test equipment used and statement of software and
software version number used;
d)
A description of how the test is to be conducted (connection to
test equipment, configuration of test equipment, test process);
2.
The ITP shall reference back to this specification to confirm
compliance with each individual requirement clause.
705.49.02 DRAFT SUBMISSION
1.
28 days prior to the proposed date for commencement of Inspection
and Testing, the Contractor shall submit a draft ITP for assessment by the MRWA
nominated representative. Update the ITP based on the requirements of the
MRWA nominated representative and conduct Inspection and Testing in
accordance with the Plan.
Draft ITP
705.49.03 UNDERTAKING THE ITP
1.
Inspect, test and tick/cross off each item on the ITP. Each page of the
ITP shall be signed and dated by the person conducting the site inspection and
testing
2.
Where a specific item on the ITP cannot be checked off by the
inspection personnel, place a cross against the incomplete item, note the reason
for the omission and identify the required rectification action.
a)
All crossed items shall be completed before Acceptance
Testing with the MRWA nominated representative.
b)
On completion, the overall ITP shall be signed and dated by the
Contractor.
c)
Forward a scanned electronic copy of the completed signed ITP
to the MRWA nominated representative.
d)
On receipt of the ITP and supporting details, the MRWA
nominated representative will confirm dates for Acceptance Testing.
705.50
TESTING SEQUENCE
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 24 of 29
1.
The Contractor shall undertake Testing and Commissioning in the
following sequence:
a)
Submit draft Inspection and Test Plan (ITP);
b)
Undertake Inspection and Testing;
Testing and
Commissioning
c)
Submit completed ITP for review; complete any additional
items as required
2
Receipt of:
a)
The completed signed ITP;
b)
Supporting details; and
c)
Draft manuals and ‘as-installed’ documentation,
by MRWA nominated representative shall constitute advice by the Contractor that
the installation is complete and ready for Acceptance Testing. MRWA nominated
representative will review the completed ITP and supporting details and will
advise the Contractor if any further work or submissions are required prior to
Acceptance Testing.
3.
Prior to Acceptance Testing, the Contractor shall make all necessary
access arrangements and confirm with the MRWA AMTS nominated
representative of the need for and nature of any necessary site inductions.
4.
Prior to Acceptance Testing, the Contractor shall provide onsite
copies of all relevant Equipment Manuals, Optical Fibre test results and “As Built /
Red line marked up” drawings relating to each specific site. All relevant
Equipment Manuals, Optical Fibre test results and “As Built / Red line marked up”
drawings relating to each specific site shall be placed in a “B4 Clear Case”
document folder and left in the document holder provided in the Cabinet door or
on the Cabinet shelf.
Relevant
Documentation
5.
During Acceptance Testing the Contractor shall attend site and make
available for the use of the MRWA AMTS nominated representative tools, plant,
equipment, operators and escorts as necessary to enable access to all system
components.
Site Access
6.
Acceptance testing with the MRWA AMTS nominated representative
may include repeat of any or all elements of the ITP plus a detailed verification of
the correct operation of each device and function.
7.
Once the Acceptance Testing commences, the MRWA AMTS
nominated representative reserves the right to delay or abort Acceptance Testing
if:
a)
The status of the work does not match the status verified by
MAIN ROADS Western Australia
Contract xxx/xx
Delay or Abort
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 25 of 29
the Contractor on the ITP;
b)
The status of the work does not allow full and complete
operation of the system;
c)
A component failure renders any part of the system
inoperable;
d)
The site owner/operator denies access to any part of the
works;
e)
The works are not accessible due to inadequate or incorrect
access provision being made by the Contractor;
f)
The Acceptance Testing work cannot proceed with reasonable
certainty that the installation is in its final state due to
outstanding/ongoing work by the Contractor.
8.
If the cause of the delay or cancellation is the within the
responsibility of the Contractor as assigned under the Contract, any associated
costs will be borne by the Contractor.
705.51 – 705.55
Delay or
Cancellation
NOT USED
AS BUILT AND HANDOVER REQUIREMENTS
705.56
AS-BUILT INFORMATION
1.
The Contractor shall supply “As Built” drawings conforming to
“MAIN ROADS WESTERN AUSTRALIA – AUTOCAD DRAWING
STANDARDS”.
As-Built Drawings
2.
The Contractor shall make an accurate record of all changes
where the actual installation differs from that shown in the contract
drawings and specification.
3.
Drawings shall be supplied in hard copy and electronic format
(AUTOCAD).
4.
The Contractor shall supply copies of all test results as
described in this specification.
705.57 – 705.60
NOT USED
CONTRACT SPECIFIC REQUIREMENTS
705.61 – 705.70
NOT USED
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 26 of 29
SPECIFICATION 705 GUIDANCE NOTES
DELETE THESE GUIDANCE NOTES FROM FINAL DOCUMENT AFTER USING FOR
REFERENCE
All edits to downloaded TDP documents shall be tracked (most word processing software
allows this to be done automatically). Deletions shall be struck through e.g. example.
Insertions shall be in italics e.g. example. If all information relating to a clause is deleted then
the clause number should be retained and the words "NOT USED" should be inserted.
The proposed documents with tracked changes shall be submitted to the Project Manager for
review, prior to printing the final batch of documents. When this final printing is carried out, the
tracked changes option is to be turned off.
The Custodian of this specification is the Road and Traffic Engineering Electrical Engineer
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 27 of 29
CONTRACT SPECIFIC REQUIREMENTS TO ADD OR DELETE
The following clauses are to be placed under the CONTRACT SPECIFIC REQUIREMENTS as
required.
NONE AT THIS TIME.
MAIN ROADS Western Australia
Contract xxx/xx
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Page 28 of 29
SPECIFICATION AMENDMENT CHECKLIST
Specification Name: No: 705 Revision No: ____Title: OPTICAL FIBRE INSTALLATIONS
Project Manager: Name:
_____________Signature: ___________Date:________
Checked By: Name: _______________Signature: ______________Date:________
Contract No: ______Contract Description: ________________________________
ITEM
DESCRIPTION
SIGN
OFF
All changes/amendments must be shown in Tracked Change mode until
Note:
approved.
1.
Project Manager has reviewed Specification and identified
Additions and Amendments.
CONTRACT SPECIFIC REQUIREMENTS addressed? –
2.
Contract specific materials/products/clauses added? (Refer
Specification Guidance Notes for guidance).
3.
Any unlisted Materials/Products proposed and approved by the
Project Manager? – if “Yes” provide details at 15.
Standard Clauses amended? – MUST SEEK approval from
4.
MCP.
5.
Clause deletions shown as ‘NOT USED’.
Appropriate INSPECTION & TESTING parameters included in
6.
Spec 201 (Test Methods, Minimum Testing Frequencies
verified).
ANNEXURES completed (Refer Specification Guidance Notes).
7.
HANDOVER and AS BUILT requirements addressed.
8.
Main Roads QS has approved changes to SMM.
9.
10.
Project Manager certifies completed Specification reflects intent
of the design.
11.
Completed Specification – independent verification arranged by
Project Manager
12.
Project Manager’s review completed.
SPECIFICATION GUIDANCE NOTES deleted.
13.
TABLE OF CONTENTS updated.
14.
15
Supporting information prepared and submitted to Project
Manager.
Further action necessary:
Signed:
MAIN ROADS Western Australia
Contract xxx/xx
(Project Manager)
Specification 705 Optical Fibre Installations
Document 14/33 Issue 01/08/2014
Date: _______________
Page 29 of 29
Download