Ruby Three Forks Corral: II A. Introduction: This project is the result of a partnership between the Ruby Valley Stock Association, the Beaverhead Deer Lodge National Forest, Madison Ranger District and the Ruby Watershed Council. The goal of the project is to improve livestock management to reduce the near stream sediment impacts within a targeted sub-basin in the upper Ruby watershed. Specifically the project seeks to relocate and reclaim an historic 5 acre livestock sorting corral located adjacent to Tributary Creek, harden a livestock water gap and stream crossing sites, and install a new culvert to improve road drainage from a hillside spring site. II B. Statement of Need and Intent: As recommended in the 2006 Ruby River TMDL, the Ruby Watershed Council has identified the Upper Ruby River Area and associated tributaries as a target region for reducing sediment loads related to grazing and livestock management. This area encompasses the three main forks of the Ruby River and many of the smaller, often unnamed tributaries to each of the three forks. Within the TMDL, the primary factors for impairment in most of the listed streams in the upper Ruby area are attributed to sediment sources, with an estimated total of 135,465 tons/year. The largest amount of sediment, 95,531 tons/year documented in the near-stream sediment source inventory cites natural sources such as landslides, slumping, natural stream scour and slope failures as well as wildlife grazing and trampling. The human induced near stream sources account for an estimated 53,083 tons/year of sediment yield and include grazing, roads, mining impacts, irrigation and vegetation clearing. The TMDL targets specifically recommend reducing the overall sediment delivery from each of these sources in the following table: Table 7-6. Summary of Allocations by Sediment Source. Large Sources Sediment yield from grazing sources Reduce sediment delivery from grazing by 51%. Sediment yield from road sources Reduce sediment delivery from roads by 60%. Sediment yield from other near-stream sediment sources Allocations to other sources of sediment such as historic mining impacts, irrigation, vegetation clearing, and stream channelization will be addressed in water body-specific discussions. The allocation for these types of sources cannot be estimated at a scale for the whole Ruby TPA. The TMDL document also specifically states: Addressing upland sediment sources as well as the highest sediment loading near-stream sources would provide a reduction of 51% of the total load attributed to grazing. This estimate assumes management changes will allow grazing in listed watersheds with reasonable land, soil and water conservation practices in place. The overall allocation for all grazing sources (upland plus near-stream) is a 51% reduction in loads. The Ruby Watershed Council Water Quality Technical Advisory Committee is in the process of developing a five year restoration implementation plan based on the TMDL recommendations, and has identified the upper Ruby basin as a critical area for initiating projects that will reduce the human induced impacts and sediment delivery in the area.. The upper Ruby area contains primarily US Forest Service owned lands and as a federal partner the USFS is very motivated to address the TMDL target guidelines. The Madison Ranger district has been working closely with the local livestock producers to identify specific sites and management techniques that will have the greatest impact on near stream grazing sediment allocations. As listed in the TMDL document and in the chart below, the Upper Ruby River is listed as the 3rd largest human induced sediment producing area. Although Ramshorn Creek is listed as the largest source, it has complicating issues with road management, is chronically dewatered and rarely connects with the Ruby River. Regarding Sweetwater Creek, several grazing management and offsite water improvements have been completed since the TMDL was developed and more are being addressed. Thus, the next largest contributing area is the Upper Ruby River. Within the Upper Ruby, the East Fork and Warm Springs basins are identified as contributing the most sediment. (See attached maps, Figure 3 & Figure16) The Forest Service is actively working on the Warm Springs road to address a large amount of the sediment allocation for that identified area. Within this particular area, the three main tributaries, the East Fork, the Middle Fork and the West Fork converge to form the Ruby. The East Fork sub basin was selected based on the willingness of the permittees & partners, the importance of the small tributaries in the arctic grayling reintroduction efforts and the potential for significant, publically visible, improvements for livestock management and BMP’s in the headwaters region. Ramshorn Creek Proportion of Loading from Near Stream Grazing Sw eetw ater Creek Upper Ruby River Warm Springs Alder Gulch Creek Indian Creek Burnt Creek Coal Creek Ruby River Low er Middle Fork Ruby River Wisconsin Creek Cottonw ood Creek Currant Creek East Fork Ruby River Poison Creek Garden Creek Mormon Creek Basin Creek Mill Creek Granite Creek California Creek West Fork Ruby Clear Creek Shovel Creek Haw keye Creek Table 7-14. Sediment Allocations and TMDL for East Fork Ruby River. Current Estimated Load (Tons/Yr) Sediment Load Allocations 1269 51% reduction in loading Natural Background 4876 Not applicable Total Load 6145 11% reduction in loading Sources Anthropogenic Nonpoint Sources Grazing Specifically, the project involves moving the 5 acre sorting corral facility from its current location on the north side of Tributary Creek and constructing a new corral south of the cow camp on a dry sagebrush ridge just off the main Ruby Centennial road. The location of the current facility creates a multitude of management and resource issues. The cattle sorting corral is located upstream from the horse corrals/cow camp and access to the upper sorting corrals is via a problematic road alongside Tributary Creek. The road is used primarily for vehicle access to the corrals and also to trail cattle from the sorting corrals to the cow camp/loading area for shipping. Every October the Ruby Valley Stock Association producers gather all of the cattle (4640 head) from the surrounding allotments and move them to the sorting corrals, many of which cross Tributary Creek and the East Fork of the Ruby with extremely large herds. The corrals cannot accommodate all of the cattle simultaneously, so as the cattle are sorted and separated they are trailed to their respective holding pastures, often crossing the streams again. When the cattle are ready to be shipped many are trailed down the Tributary creek road to the loading corrals where they are loaded onto the semi trucks. Another group of permittees from the Eureka Basin also use the sorting facility and trail in from the south using the same route, crossing Tributary Creek and the East Fork of the Ruby multiple times with their 1524 head of cattle. The total number of cattle crossing the streams multiple times, often in snow or rain, is 6164. The location of the facility and the large number of animals utilizing the area over a short duration, often in wet weather, creates a muddy, sediment laden mess. The new sorting facility would be located on a dry upland site just off of the main Ruby Centennial road. The new location would greatly reduce the number of stream crossings to access the site, as well as provide direct access from the main road for the semi trailers to the facility, reducing the number of times the cattle need to be moved. Many of the cattle could be trailed directly down the Ruby Centennial road to the corral and load out facility, reducing the stream crossings completely. Cattle could be readily separated, sorted and loaded without impacting the adjacent streams and tributaries. The new corral facility would also contain scales for the semi trucks to weigh immediately before and after loading on site, greatly increasing the overall value for the producers. In the current location the cattle must be trailed down the Tributary Creek road to the load out corrals and the trucks park on the main road for loading, creating a safety hazard. Also, the trucks must utilize scales in Alder, MT which is 30 dirt road miles away, thus the cattle are not weighed until they have traveled a good distance. In an effort to address many of the cattle related sediment sources in this region, the project also involves creating a hardened water gap and crossing on Tributary Creek in an area where the crossing and the water gap exist separately, but only a few hundred yards apart. The water gap serves to provide water for cattle that utilize the Burnt Creek allotment to the south of Tributary Creek (See photo). Additionally, there is another crossing site about ¼ mile upstream on Tributary Creek that would be hardened to reduce the sediment. As part of a larger project, the Forest Service is also considering hardened crossings on several small tributaries to the west of the Ruby Centennial Road within this same allotment area, but the NEPA scoping still needs to be completed for those areas. The Ruby Watershed Council has a proven track record of successfully completing watershed restoration and education projects, recently completed a 319 groundwater surface water interaction model, and is actively working on several other watershed grants and projects. The Ruby Watershed Council works very closely with the Ruby Valley Conservation District to provide outreach, education and project implementation to meet the goals of the TMDL and water quality restoration documents. II C. Collaborative Effort: This project is the result of a collaborative planning effort between the USFS Madison Ranger District, the Ruby Valley Stock Association & Eureka Basin Grazing Association; (Bradley Livestock, LC, Silver Spring Ranch, Ashcraft Ranch, Inc., Ostler Ranch, Point of Rocks Angus Ranch, Rick & Jody Sandru, Ladder Canyon Ranch, Hamilton Ranches, Inc and the Ruby Dell Ranch); the Ruby Watershed Council & Ruby Valley Conservation District; and the MT FWP Arctic Grayling Recovery Team. This project provides a great example of how local producers, local agencies and federal land managers can work together to address natural resource concerns that are mutually beneficial. The potential area of impact encompasses over 70,000 acres of Forest Service land, over 6,000 head of cattle, over 20 families and provides positive results for multiple willing partners. II D. Project Planning and Management: Since the project is truly a collaborative effort, each partner is responsible for managing their respective roles in the implementation and successful management of the project. The Ruby Watershed Council will provide the overall project management, will coordinate the various components and partners and will be responsible for ensuring that the project is funded, implemented to its design standards, complies with state procurement guidelines and completed in a timely and efficient manner. The Watershed Council and Ruby Valley Conservation District will also be fiscally responsible for the administration, reporting and will provide public outreach to highlight the benefits of the successful project. The Ruby Stock Association is responsible for the removal and reclamation of the existing corrals and adjacent areas, installation and maintenance of improvements for the new corral facility, and cost and labor share for the new road and culvert replacements. The producers are also responsible for using Best Management Practices to further reduce potential sediment loads in managing livestock throughout their FS allotments. In addition to overseeing management of the allotments and continued cooperation with the producers, the Madison Ranger District will provide cost share for the road and culvert improvements, hardened crossing design and installation oversight, and stream monitoring. The Forest Service will also continue to monitor the range and site conditions to ensure BMP compliance. Section III Project Components III A. Reporting Requirements: The RVCD is experienced in administrative 319 reporting requirements and will comply with the MDEQ reporting format, tracking of budgets, match summaries and schedule for quarterly, annual and final grant administration reports. The RVCD understands the importance of proper grant reporting and will work hand in hand with MDEQ to ensure adequate reporting is provided. The reports will be provided in hard copy and appropriate electronic formats. III B. Education and Outreach: A large portion of the public outreach for this project will be achieved simply through the numbers of partners and families that are directly involved. Many of the producers will provide their own time, energy and money to complete the project and all will benefit from the results. In rural communities such as the Ruby watershed (population 1200), positive results spread quickly. Also, the Ruby Watershed Council is dedicated to education and outreach and will provide monthly progress reports to the watershed council and the Ruby Valley Conservation District. Additionally the project will be located just off of the main Ruby Centennial road that is used by a large number of recreationalists from out of the area. III C. Project Implementation: The partners for this project have been meeting over the course of several months to discuss and plan for the project design and implementation. The specific tasks, responsibilities and costs are outlined in the Scope of Work below, as well as a projected timeline for completion in the Project Milestone table. Most of the project will occur during the summer of 2009 simultaneously. The corral fencing portion will be done by a fencing contractor. The grazing association is responsible for the old site cleanup and should complete the fence removal in a few days once the new corrals are erected. Since the area is remote, it is best to get the equipment on site and complete many of the projects concurrently. Thus, following the clean up and regrading of the corral site, the association will install the road culvert and then install the scale at the new corral site. The forest service will oversee and have the contractor complete all hardened crossings at one time to reduce the mobilization and gravel delivery costs. The Forest Service road crew will build the new corral access road in the late summer. If all goes on schedule the new facility will be operational before fall of 2009. III D. Operation & Maintenance: The Ruby Stock Association members are committed to making this project work and maintaining the facility. They are donating a large amount of time, equipment and money to remove and reclaim the historic facility site, and certainly have a vested interest in maintaining the new corrals. They are also very working hard on integrating best management practices with managing their herds on these allotments and throughout the Ruby TPA. The Association also agrees to provide all of the weed maintenance on the old site for the next 5 years, and at the new site continuously. Maintenance of the hardened crossings and water gap are also a shared responsibility of the association and the forest service. The Forest Service is providing the design specifications, the implementation oversight and will monitor the sites for maintenance issues. The producers and stock riders will also participate in the monitoring and maintenance assurance for the stream sites. III E. Monitoring: Most of the before, after and long term monitoring will be completed by the Forest Service. The local range conservationist is in the area consistently and monitors for grazing compliance for the permittees, but he will also include the project sites for regular inspection and photo monitoring. The local office will also work with the regional FS hydrologist to provide water quality sampling before and after project completion to quantify sediment reduction. Montana Fish Wildlife and Parks also provides regular monitoring of the resident fish populations and have been utilizing the small tributaries for grayling reintroduction efforts for the past several years. They have long term data that will aid in quantifying fish numbers, utilization and habitat improvements for the area. The Ruby Watershed Council also participates in disseminating the information and results at council and conservation district meetings. Section IV Scope of Work: Goal 1: Relocate Corral/Sorting Facility Task 1: New Corral Fencing: Will contract to design and build a new corral livestock sorting facility located at an upland site just off the main Ruby River Road. Responsible Party: Contractor 319 Cost: 50,000.00 Match: 20,000.00 Total: Timeline: Outputs: 70,000.00 Early Summer 2009. New 5 acre livestock corral/sorting facility Task 2: Corral improvements: Provide on site weighing facility and scales for direct livestock loading and truck weighing. Responsible Party: Grazing Association 319 Cost: 0.00 Match: 23,000.00 Total: 23,000.00 Timeline: Mid to late summer 2009 Output: Truck scales and installation for on site weighing Task 3: Build New Corral Road: Design and construct, to Forest Service standards, new access road from the Ruby River Road to sorting facility site, approximately ½ mile long, capable of supporting semi tractor use. Responsible Party: USFS 319 Cost: 0 Match: 7,000.00 (federal) Total: 7,000.00 Timeline: Summer 2009 Output: ½ mile access road from Ruby Centennial road to new corral facility. Goal 2: Remove & reclaim existing corral Task 4:Fencing removal and site reclamation: The association will tear down old corral fences and remove, or burn on site, clean and recontour the site, reseed with native seed and provide annual weed maintenance for 5 years. Responsible Party: Grazing Association 319 Cost: 0.00 Match: 7,500.00 Total: 7,500.00 Timeline: Summer 2009 Output: Clean and reclaimed historic corral site. Goal 3: Reduce livestock/stream bank impacts Task 5: Water Gap/Crossings: Provide 2 hardened livestock crossing sites and combine one of them with a 50’ water gap on Tributary creek. Responsible Party: Contractor/USFS 319 Cost: 8,000.00 Match: 2,000.00 (Federal) Total: 10,000.00 Timeline: Summer 2009 Output: Improved water quality in Tributary Creek and associated water Task 6: Road Culvert: Replace smashed culvert to channel hillside spring water and reduce road sedimentation in Tributary Creek. Responsible Party: Grazing Association 319 Cost: 1,500.00 Match: 1,500.00 Total: 3,000.00 Timeline: Summer 2009 Output: Reduced sediment input into Tributary creek and improved water quality. Goal 4: Project Evaluation Task 7: Monitoring, NEPA and permitting: The Forest Service is responsible for all phases of environmental compliance and site monitoring before, during and after the project completion. They will work with the RWC and the Arctic Grayling team to set up a sampling analysis plan and monitoring to evaluate sediment reduction. Responsible Party: USFS 319 Cost: 0 Match: 10,000.00 (federal) Total: 10,000.00 Timeline: Ongoing Output: Evaluation of project success, monitoring to determine sediment reduction, and environmental compliance oversight. Goal 5: Project Coordination, Outreach, Education & Administration Task 8: Coordination, Outreach & Education: The RWC will coordinate all aspects of project management, outreach and public education highlighting the benefits of the collaborative project, as well as coordinating with the RVCD for fiscal and project administration. Responsible Party: Ruby Watershed Council 319 Cost: 2,000.00 Match: 2,000.00 Total: 4,000.00 Timeline: Ongoing Output: Project coordination, management and outreach among the partners and public. Task 9: Administration Responsible Party: 319 Cost: Match: Total: Timeline: Output: Requested 319 Funds: Non-federal Match: Federal Match: Total Project Cost: RVCD 6,000.00 0 6,000.00 Ongoing Fiscal administration and timely submission of invoices, quarterly and final reports. 67,500.00 54,000.00 19,000.00 140,500.00