DELHI WATER SUPPLY & SEWERAGE SECTOR Reform Project Delhi Jal Board J u ly , 2 0 0 4 Table of Contents List of Abbreviations...………………………………………………………………………...…….…........1 1. Executive Summary ............................................................................... 2 2. Background............................................................................................. 6 3. Present Status & Need for Reforms ..................................................... 7 4. Objectives of the Proposed Reform Project ........................................ 9 5. Strategic Context .................................................................................. 10 6. Proposed Reform Project Components ............................................. 11 7. Expected Outcome ............................................................................... 19 8. Institutional Framework for Implementation................................... 20 9. Stakeholder Concerns & Mitigation Measures ................................. 22 10. Summary Matrix of the Reform Project ........................................... 25 11. Annexure ............................................................................................... 31 Delhi Water Supply & Sewerage Project – Identified Projects i. Map for Water Supply Component ii. Map for Wastewater Component Delhi Water Supply & Sewerage Sector Reform Project List of Abbreviations CAD CEO CETP CSC DDA DJB HRD ICB IT JJ KRA LCB MCD MGD MIS MoUD&PA NCT NDMC NRW NWP O&M PMoU PPE RWA SCADA STP WHO WSP WSS WTP Delhi Jal Board Computer Aided Design Chief Executive Officer Common Effluent Treatment Plant Customer Service Centre Delhi Development Authority Delhi Jal Board Human Resource Development International Competitive Bidding Information Technology Jhuggi Jhopri Key Result Areas Local Competitive Bidding Municipal Corporation of Delhi Million Gallons per day Management Information System Ministry of Urban Development & Poverty Alleviation National Capital Territory of Delhi New Delhi Municipal Council Non Revenue Water National Water Policy Operations and Maintenance Performance Memorandum of Understanding Personal Protective Equipment Resident Welfare Association Supervisory Control and Data Acquisition Sewage Treatment Plant World Health Organization Water and Sanitation Program, South Asia Water Supply and Sanitation Water Treatment Plant 1 Delhi Water Supply & Sewerage Sector Reform Project 1. Executive Summary DJB is the primary service provider of water supply & sewerage services in Delhi. Even though Delhi has access to adequate availability of water as well as sufficient wastewater treatment capacity, the actual service delivery is sub-optimal. The current service level in the sector suffers from serious deficiencies which need to be addressed urgently. These include: Gaps in Service delivery – Water Supply – bulk supply uncertainty; intermittent and inequitable supply, significant Non Revenue Water, absence of bulk metering, ineffective customer metering, and inefficient operations Gaps in Service delivery – Sewerage – inadequate coverage of sewer network, silted sewer lines, routine overflow of untreated wastewater into drains, underutilized treatment capacity, interconnection of sewer lines and storm water drains Operational – lack of infrastructure and operational records; inadequate “crisis” maintenance Institutional – significant overlap in the role of policy formulation, service delivery and regulation, lack of adherence to service standards, inefficient customer interface, lack of performance orientation, inadequate use of IT & MIS, inadequate service provision to the poor Financial – very low tariff; low cost recovery forcing DJB to rely on excessive loan assistance from the Government, high costs, particularly energy usage. The obvious manifestation of the above situation is poor reliability, increased health risks due to inadequate water supply and management of wastewater, huge copings costs and low customer satisfaction. Given this context, the Government of NCT of Delhi recognizes the need for comprehensive reforms in the WSS sector to ensure providing a significantly higher level of service in a sustainable manner by DJB. To facilitate the same, DJB had recently commissioned the Delhi Water Supply and Sewerage Project Preparation Study which has identified certain critical areas and strategic reform measures. Subsequently, workshops were held for developing the Vision and Reform Implementation Strategy for the sector. The Workshops brought together representatives from DJB management and staff, Central and State Government, Resident Welfare Associations, multilateral and bilateral development agencies, NGOs and experts from progressive water utilities on a common platform to deliberate on the issues facing the sector, share best practices, and develop the strategy and implementation mechanism. The recommendations of the study as well as deliberations during both the workshops have stressed on the need for urgent interventions. The Government’s Vision for the sector is ‘Provision of universal 24/7 safe water supply and sewerage services in an equitable, efficient and sustainable manner by a customer oriented and accountable service provider’. The strategy to achieve this Vision includes a phased programme towards full service coverage and high quality service provision in an efficient and financially sustainable manner. Although the DJB Vision sets a 10 year time-frame upto 2015, a comprehensive reform process is proposed to be launched immediately with the objective of achieving visible & replicable improvements in various aspects of the WSS services in Delhi. DJB plans to undertake first phase of implementation of the reform project as an essential part of a comprehensive improvement in the services. This Reform Project document is for Phase I of the reform process and details out the concrete action plan for the next five years. The document incorporates the recommendations Delhi Jal Board 2 Delhi Water Supply & Sewerage Sector Reform Project of the Project Preparation Study, results of stakeholder consultation and gives on a macro level a blueprint for immediate capital investment requirements, the possible sources of funding and assistance. The objectives include addressing the city wide urgent infrastructure needs for service improvement, enhanced capacity building and internal efficiency improvement plan, introduction of pilot projects in selected areas for preparation of roll out programme for the next phase of the reform process. The specific components of the project are as follows: First phase of comprehensive distribution improvement to move towards Continuous Supply. This includes outsourcing of water supply and sewerage services in two DJB operational zones and a portion of the NDMC distribution area, covering about 12% of the connections, through Management Contract(s) for five years. The objective will be to gradually move from an intermittent supply system to a continuous supply system. The technical and managerial expertise of the private sector would be used to achieve significant efficiency gains and to train the DJB employees in modern utility management best practices. Bulk supply and sewerage infrastructure improvement for city wide improvement in services. This will include rehabilitation of selected water supply and sewerage system to address priority bottlenecks as identified in Batch I projects of the Project Preparation Study, an energy audit for enhanced efficiency, measures for comprehensive collection of wastewater and conveyance to treatment plants, and for improved water quality to promote Environmental Sustainability Consultancy studies for rationalization of trunk systems for changeover to continuous supply regimes and preparation of a system upgrade roll-out plan Organisational strengthening measures to improve DJB’s internal efficiency and for better consumer focus and responsiveness. The focus will be on enhancing performance orientation, training, staff rationalization, single point customer interface, effective use of MIS & IT etc. Targeted interventions including pilot projects for improved services to the poor Roll out programme for scaling up of services and replication across the entire city based on the lessons learnt in this phase. While it is essential to identify the urgent works and implement them in Phase I of the reform project, it is proposed to undertake an immediate study for developing a comprehensive system infrastructure development and roll out plan simultaneously based on a detailed assessment of the lessons learnt from the Phase I interventions for effective replication across the entire city. It is proposed to develop the roll out plan within 2 years of the commencement of Phase I of the reform project. Based on the roll out plan, further measures for comprehensive improvement in the services shall be identified by Year 3 of the Phase I and implemented subsequently. The same is depicted below. Delhi Jal Board 3 Delhi Water Supply & Sewerage Sector Reform Project Study for rationalisation of trunk infrastructure- Roll out plan Trunk Infrastructure improvements – Water & Sewerage (Batch 1 projects) Phase I Distribution Reforms Year 1 2 3 4 5 Trunk Infrastructure improvements – Water & Sewerage (Batch 2 projects) Phase 2 Distribution Reforms Year 6 7 For effective implementation of the reform programme, it is proposed to have a Performance Memorandum of Understanding between the Government and DJB. The objective will be to move from a resource plan to a reform plan with release of funds linked to performance. The success of any reform initiative will critically hinge on mutually agreed commitments from DJB and Government, which will be embodied in the MoU. While commitments from DJB will include demonstrating quantifiable increase in the key performance indicators with respect to quality of services and service coverage, the Government will need to commit to creation of an enabling environment through independent regulatory framework, tariff increases and rationalization, establishing minimum governance requirements and adequate financial support. The objective will be to achieve financial sustainability through gradual phasing out of Government subsidies by the end of the MoU period and recovery of full efficient O&M costs. Independent monitoring of the MoU and public disclosure of performance is also proposed for effective implementation. The success of the reform programme will critically depend upon its acceptance by the Government, DJB employees, customers and potential private players. It is essential that their fears and apprehensions, the risks perceived with respect to the reform project are suitably addressed. For this purpose, it is essential to launch a comprehensive Communication Strategy, which addresses the concerns of all stakeholders, both in the external environment and within the organization. While it is recognized that the process of reforming the water supply and sewerage sector may be difficult initially, and it may take sometime before the full benefits of the reforms become apparent, nevertheless it is essential to ensure sustainability of the sector. It is envisaged that the Reform Project shall be the driving force in Delhi to turn around the current situation of general poor performance into sustainable high quality services for all. The objective at this stage is to initiate the reform process, deliver substantial improvement on various aspects of the WSS services in Delhi in the envisaged time period, and develop a strategy for replication across the Delhi Jal Board 4 Delhi Water Supply & Sewerage Sector Reform Project entire city to ensure that the Government’s visionary agenda for sustained and secure water future does not remain on paper. The summary table of the projects, time frame, tentative costs and source of funding is given below: Goal Reform Component Time Frame Tentative Cost1 (US$ million) Source of Funding2 Continuous Supply Phase I Distribution Reform Project Consumer Metering Bulk Meters & Leak detection equipment Trunk Infrastructure improvement – Water Water quality Trunk Infrastructure improvement – Sewerage 2004 – 09 From 2004 2004-06 60 6.5 3.3 World Bank DJB Plan Funds DJB Plan Funds 2004-06 26.5 DJB Plan Funds 2004-05 2004-06 To be estimated 66.2 DJB Plan Funds DJB Plan Funds – US$ 14.8 mln World Bank – US$ 50.5mln JBIC – US$ 0.9mln Energy Audit & Implementation of Measures proposed Performance Appraisal System, Delegation of Powers Training From 2004 16.7 DJB Plan Funds / USAEP - Staff Rationalization 2004-05 0.5-1% of Plan budget per annum To be estimated Computerized CSCs Modern MIS & IT Communication Plan Assessment of needs of the poor using CBIS Pilot Projects Infrastructure Development Plan & Tender documents From 2004 2004-05 2004 2004-05 4 To be estimated To be estimated DJB Plan Funds/ World Bank DJB Plan Funds World Bank World Bank 2004 - 06 2004-06 To be estimated 1.5 World Bank World Bank Operating Efficiency & Environmental Sustainability Customer Orientation & HRD Improved Services for the Poor Roll Out TOTAL 1 2 2004-05 From 2004 - DJB Plan Funds 184.7 Excludes the cost of price & physical contingencies, taxes Actual quantum of funding from World Bank to be finalized in discussion with World Bank Delhi Jal Board 5 Delhi Water Supply & Sewerage Sector Reform Project 2. Background The National Capital Territory of Delhi (NCT) covers an area of 1486 sq km, of which the urban area accounts for 525 sq km. Of the total urban area, the area under Municipal Corporation of Delhi (MCD) accounts for 94% while New Delhi Municipal Council (NDMC) and Delhi Cantonment Board (DCB) cover 3% each. The Government reconstituted the erstwhile Delhi Water Supply and Sewerage Undertaking into the Delhi Water Board (DJB) in 1998, with the Chief Minister as its Chairperson. DJB is responsible for complete water supply and sewerage services to areas under the jurisdiction of MCD. DJB also provides bulk supply services for NDMC and DCB areas and the internal water distribution and sewage collection is taken up by these agencies. DJB serves a total population of nearly 14 million through 1.47 million water connections. DJB’s water resources consist of both surface and ground water. The water allocation from the surface water resources – Yamuna, Bhakra and Ganga rivers is 940 MGD (4272 Mld) which translates into an actual availability of 820 MGD (3726 Mld) due to losses from canal system and capacity limitation in the raw water transmission. The groundwater resources add an estimated 63 MGD. Most of the surface water is treated at five plants; Chandrawal, Wazirabad, Haiderpur, Bhagirathi and Nangloi having a combined treatment capacity of 640 MGD (2911 Mld) of water. With respect to sewerage services, around 73% of the population is connected to the sewer network. There are 17 wastewater treatment plants with nominal capacity of 512 MGD (2337 Mld). This is more than adequate for an estimated present day volume of 406 MGD of wastewater for treatment. Even though Delhi has access to adequate availability of water as well as sufficient treatment capacity, the actual service performance is poor. To identify the core issues confronting the sector, DJB had recently commissioned the Delhi Water Supply and Sewerage Project Preparation Study with funding from International Bank for Reconstruction and Development. The study commenced in 2002 and focuses on both technical and institutional aspects. The study gives a complete snapshot of the existing infrastructure and institutional arrangements. It has identified certain areas requiring critical intervention. An immediate investment plan for addressing urgent infrastructure needs has been drawn up. Apart from this, certain changes in the institutional arrangements have been recommended which include measures for organizational restructuring, corporate governance, regulatory mechanism HR management systems, IT plan, etc. A Workshop was held in March 2004 to formulate a Sector Vision and to set an agenda for the reform process. The Workshop brought together representatives from DJB’s management and staff, Central and State Government, Resident Welfare Associations, multilateral and bilateral development agencies, NGOs and experts from progressive water utilities on a common platform to deliberate on the issues facing the sector, share best practices and reach a consensus on the proposed Vision. While the Project Preparation Study covered a wide range of reform areas, several important and complementary aspects have been identified during the Vision workshop, which also need to be addressed. To take the Visionary agenda forward, another Workshop was held in May 2004 to develop a Reform Implementation Strategy. The objective was to bring together various stakeholders to deliberate on the strategy and implementation mechanism and develop a concrete action plan for undertaking reforms in the next five years. Delhi Jal Board 6 Delhi Water Supply & Sewerage Sector Reform Project The recommendations of the study, as well as deliberations during both the workshops, have stressed the need for interventions to ensure provision of a significantly higher level of service in a sustainable manner. Despite concerted efforts and the initiatives undertaken so far, it is felt that a lot more needs to be done in a focused manner, setting out short term and medium term implementation targets. 3. Present Status & Need for Reforms The current service level in the sector suffers from serious deficiencies which necessitate the need for reforms. These are discussed below: Gaps in Service Delivery – Water Supply The actual water supply available to the residents is intermittent and inequitable. Despite concerted efforts the demand-supply gap is on the rise. This imbalance is further exacerbated by the high level of Non-Revenue Water – including both technical and commercial losses – estimates of which range around 40-50%. The ability to identify the losses is further constrained due to lack of bulk metering for transmission and distribution systems except for supply to NDMC and DCB. The present zoning arrangements are not conducive for effective monitoring and control. Customer metering is ineffective under the prevailing condition of intermittent supply. Under these conditions, there is little incentive to economies on the use and wastage of water. The intermittent supply further leads to increased health risks from possible contamination of leaking pipes. There are shortcomings at treatment works and the equipment is inefficient. The obvious manifestation of the poor supply situation is high customer coping costs and low level of customer satisfaction. Positive initiatives are being taken by DJB to augment the water supply. These include additional capacity of 140MGD from the new Sonia Vihar WTP and commissioning of Nangloi WTP to its full capacity of 40 MGD by end 2004. WTPs at Dwarka and Okhla are planned for customers at the extremities of the system. There are plans for introducing recycling of wastewater from existing WTPs. Additional tubewells are being commissioned in the Palla area for augmenting water availability. However, these will only go a limited way towards bridging the future demand supply gap. The gross demand (including losses) is estimated to be in the range of 2096 MGD in 2021 at the present level of losses and reduced to 1463 assuming losses to be in the range of 20%. It is also clear that any incremental addition to water availability now through big dam projects is an extremely expensive proposition. Hence, much of the gap will have to be met by giving priority to improved management of water distribution, resulting in reduced losses, rather than capacity augmentation or ‘filling a leaking bucket’. Gaps in Service Delivery – Sewerage Presently, the coverage of the sewer network is inadequate with only 73% of the population connected to the sewer network. With 80% of the water consumed discharged as wastewater, presently the wastewater generated is 406 MGD. However, the wastewater collected for treatment is only 321 MGD due to the problem of large unsewered areas, silted sewer lines and inefficient pumping. There is overflow of wastewater from sewers into drains due to blocked or settled sewers as well as interconnection of sewer lines and storm water drains. In addition, the configuration of some pumping stations causes sewer surcharging that results in continuous overflows of crude sewage to the environment. As a result, a significant share of the collected raw wastewater is directly discharged into drains and nallahs. The treatment capacity is underutilized and the effluent quality at most treatment works does not consistently meet the current standards. Delhi Jal Board 7 Delhi Water Supply & Sewerage Sector Reform Project The present hydraulic capacity of the treatment plants of 513 MGD is sufficient for treatment of collected wastewater (321 MGD) and an atypically high volume of infiltration (114 MGD). However, to meet the future demand, as well as reduce unsafe disposal of wastewater in the environment, it will be necessary to give immediate priority to rehabilitate the existing pipelines, to reduce infiltration, to improve pumping station operation and ensure conveyance of the collected wastewater to the treatment plants. The extension of the local network, collector sewers and increase in sewage treatment capacity shall be undertaken subsequently. Institutional DJB's institutional arrangements are not geared to promote managerial autonomy and accountability. The role of the Government is significant as reflected in the current composition of the Board. DJB is mandated to frame its own regulations (with approval from the Government) with respect to tariffs and service quality and enforcing them, thereby reflecting an inherent conflict. The management responsibility is diffused leading to lack of accountability. The annual performance appraisal system does not explicitly recognize Key Result Areas and hence absence of monitoring performance against them. Human resource development in the organization needs particular attention, wherein there is a clearly defined incentive structure for all level of employees which recognizes and rewards performance. There is a pressing need for effective training programmes for skill set enhancement of employees at various levels including training on modern management and leadership skills. The organization is overstaffed as reflected in the high ratio of staff per thousand connections (20) compared to the industry norms. There is little use of Information Technology (IT) and there is a lack of a modern Management Information System (MIS), both essential for effective management. The customer interface is a clear weak link. DJB is clearly supply-oriented whereas a service should be demand oriented, recognizing the importance of the customer and of good relations with them. There is no strict adherence to the Citizen’s Charter, the customer has limited options for bill payment, is not aware of the existing service standards, and there is no effective grievance redressal mechanism. Though initiatives have been taken for enhancing citizen partnership through the ‘Bhagidari’ scheme, there is a need to strengthen it. Thus, there is a need for institutional mechanism for enhanced autonomy, improving organizational efficiency and altering the ethos of the organization from being supply oriented to customer oriented. Improving water supply and sanitation services to the poor also remains an urgent priority. Most poor people reside in the resettlement colonies, urban villages, rural villages, JJ clusters and unauthorized colonies. Many of these are only partially covered by the water distribution system. Even though efforts are being made to improve this situation, it is difficult to plan for service delivery in these areas as they are hampered by lack of adequate information on coverage and a monitoring system. There are a number of isolated pockets such as unauthorised colonies and JJ clusters that are not sewered. People who do not have access to water and sanitation services resort to a variety of coping measures to meet their needs viz. private handpumps & tubewells, private vendors, soak pits, open defecation imposing substantial cost – financial, health and time. Hence, there is a need for targeted interventions to cater to the water and sanitation needs of the poor. Financial Sustainability With respect to the financial situation, even though Delhi has the highest national per capita income, it has the lowest water tariffs among all metros in India. There is a persistent deficit on Delhi Jal Board 8 Delhi Water Supply & Sewerage Sector Reform Project the revenue account over the years. Despite the fact that the DJB Act mandates full cost recovery3, this philosophy has not been reflected in the tariff-setting decisions taken by the DJB. In addition to the average monthly bill of Rs 50, the present coping costs already range between Rs 200-350 per month for the residents of Delhi. Contrary to the common perception, a recently conducted Willingness to Pay survey in Delhi indicates a positive response with respect to a willingness to pay for enhanced service quality. Operation is inefficient – and maintenance is at far lower levels than is needed - with energy and establishment costs accounting for 42% and 45% of the O&M costs (excluding debt charges) respectively. Presently, the revenue deficit is being funded through loans from the Government (approx. Rs 350-400 crore annually). However, given DJB’s envisaged pipeline of projects, funds required (Rs 5000 crore)4 for system rehabilitation, as well as limited capacity of the Government as the sole funding source, there is a need to progressively revise water charges accompanied with improved services whilst gradually phasing out the Government subsidy, with the objective of achieving full recovery of costs of efficient O&M. Thus, against this backdrop, and the initiatives undertaken notwithstanding, a lot more needs to be done if the sector is to become financially self-sustaining. 4. Objectives of the Proposed Reform Project The Government of NCT of Delhi recognizes the need for comprehensive reforms in the sector to ensure a significantly higher level of service provided in a sustainable manner by DJB. The approach of the Government for embarking on the reform process has been to develop a: - Long term Vision and a step wise approach to reforms though setting out medium term implementation targets. Focus on physical improvements, demonstration projects, policy framework and internal reforms for capacity building of DJB in medium term Adequate participation of stakeholders and beneficiaries in the reform project The Government’s Vision for the Delhi water supply and sewerage sector in Delhi is: “Provision of universal 24/7 safe water supply and sewerage services in an equitable, efficient and sustainable manner by a customer oriented and accountable service provider”. Embedded in the Vision are six thrust areas as depicted overleaf. The defined performance indicators and key milestones as outlined in the proposed Vision are presented in Annexure 1. Section 55(2), DWB Act, 1998 states that DJB is empowered to ‘recover all the costs of operation, maintenance, repayment of debt and a return not less than 3% on net fixed assets’ 4 Tenth Five Year Plan (2002-07), DJB 3 Delhi Jal Board 9 Delhi Water Supply & Sewerage Sector Reform Project Financial Sustainability & Accountability Operational Efficiency Continuous Supply Vision Customer Orientation & HRD Environmental Sustainability Improved Services To the Poor The strategy to achieve this Vision is to carry out a phased programme towards full service coverage and high quality service provision in an efficient and financially sustainable manner. Although the Vision document sets a time-frame upto 2015, it is proposed to launch the reform process immediately with the objective of achieving visible and replicable improvements in various aspects of the WSS services in Delhi. The objectives of the reform project are: - - Adoption of a phased implementation approach, incorporating experience from initial work for replication and scaling up Implementation of an initial city wide service improvement programme for substantial improvement of reliability, sustainability and affordability of WSS services to benefit all citizens of Delhi including the poor Implementation of comprehensive organizational measures for enhanced capacity building and internal efficiency Specific pro-poor interventions to address the needs of the poor Preparatory measures for the next phase of the reform program to roll out continuous water supply and sewerage services to the entire city Effective Institutional Framework for implementation and sustenance of the reform programme To realize the above objectives, specific projects have been identified and a concrete action plan has been developed for the next 5 years. 5. Strategic Context Embedded in the proposed reform project are principles of various policy pronouncements in the water supply and sewerage sector to facilitate reforms. The proposed reform project is in consonance with the National Water Policy, 2002 Government of India which advocates an integrated and multidisciplinary approach towards water resource planning, development, Delhi Jal Board 10 Delhi Water Supply & Sewerage Sector Reform Project conservation and management. The NWP 2002 lays emphasis on formulation of state water policies backed with an operational action plan in a time bound manner in two years. With respect to the policy aspects, the NWP lays emphasis on the need for the paradigm shift from development to effective management of water resources through recognition of water as an economic good with well targeted and transparent subsidies for the poor, adoption of scientific water management techniques, participatory approach to water sector management and encouraging private sector participation. These principles have been incorporated in the proposed reform project. The project is also in line with the 74th Constitutional Amendment which aims at devolution of enhanced financial and functional powers to the urban local bodies to enable them to function as effective self-governing institutions. The project is consistent with India’s Tenth Five Year Plan, which recognizes that infrastructure bottlenecks have become a major constraint on growth, and therefore poverty alleviation. Access to safe water has been declared as a basic human right by the United Nations and is widely recognized to directly contribute to poverty alleviation. The project would also contribute to achieve the Millennium Development Goals adopted at the world summit on sustainable development in Johannesburg in 2002, which lay emphasis on provision of safe drinking water, improved sanitation services and sustainable environment management. 6. Proposed Reform Project Components The various project components derived on the basis of comprehensive analysis of the system requirements, proposed benefits and cost effectiveness which shall be undertaken in the next five years are discussed below. The detailed action plan, proposed benefits and the tentative costs have been presented in Section 10. 6.1 Phase I of Comprehensive Distribution Improvement Objectives: It is proposed to move towards continuous water supply to promote a virtuous circle in respect of increased supply reliability, operational efficiency and water quality, resulting in greater customer satisfaction, willingness to pay and enhanced cost recovery. The focus will be on distribution management aspects and efficient utilization of currently available resources before considering augmentation of resources. Preliminary analysis and discussion has shown continuous water supply to be cost effective and affordable. A phased implementation approach is proposed for gradual introduction of continuous supply systems. In Phase I, it is proposed to initiate distribution system improvements in 2 operational zones of DJB and one operational zone of NDMC with an objective to demonstrate that 24/7 is achievable as well as to set a realistic strategy for continuous supply. Framework for Action DJB plans to undertake first phase of implementation of continuous supply as an essential part of a comprehensive improvement in the distribution services in two of its own operational distribution zones – South II and South III having 91,000 and 72,000 connections respectively. It is understood that NDMC will also undertake a similar upgrading of distribution in a zone within its own jurisdiction and this will be included in the Phase I project with the overall project responsibility resting with DJB. Apart from the suitability of their size covering 12% of the total DJB connections and the range of social and economic conditions they exhibit, they receive water from the new Sonia Vihar WTP thereby ensuring optimum use of the water produced by the plant. Delhi Jal Board 11 Delhi Water Supply & Sewerage Sector Reform Project In order to introduce best water service industry operational standards into DJB, it is proposed to award 5-year Management Contract(s) to implement the first phase of distribution improvement. Specialist contractors will be procured on a competitive bidding basis for each zone and they will be required to work with the management and staff of the two Zones to meet performance targets. Independent technical and transaction advisors will be appointed during the preparation stage and for selection of the contractor. The role of the technical advisor will include assessment of the existing situation with respect to the quantum of investment required to achieve realistic performance standards. The objective would be to reduce uncertainty and have the required system information in place to serve as a basis for informed discussions with the potential private contractors. The transaction advisor will be responsible for analysis of legal aspects, economic and financial analysis, gauging the interest of potential private sector contractors and, accordingly, determining the project structure, as well as preparing the bid documents and providing assistance during the bidding process. The Management Contracts will cover the operation and maintenance of the water supply and sewerage services in the selected distribution zones as well as rehabilitation works required to bring about the changes necessary for continuous supply. The operator will be paid fixed management fee plus certain incentives (or imposed penalties) depending upon performance and achievement of output-based milestones. An independent monitoring of the performance of the contractor will be done. The principal objectives of the Phase 1 work in the two Zones will be to: - - - - - Improve all aspects of the water supply and sewerage services including distribution system, equity in bulk supply, MIS, billing and collection, customer interface by selected capital investments and introduction of best operational practices. Use it as a ‘Showcase’ project to demonstrate that 24/7 supply is an achievable vision. Harness technical and managerial expertise to achieve efficiency improvements. Provide an “on-the-job training ground” in best water industry practices for the management and staff of the 2 Zones, and their colleagues seconded from other Zones, so that the DJB may progressively introduce and replicate them in the remaining areas. Provide an incentive structure for the DJB staff involved in the work for enhanced motivation and acceptance by employees. Be a proving ground for optional approaches for restructuring distribution systems within the zones, bulk and customer metering, detection of illegal connections, leak detection and repair, system rehabilitation and maintenance. Establish the lessons learnt and identification of issues which may be expected while introducing 24/7 supply throughout Delhi. Generate data on the cost and rehabilitation requirements for roll-out of continuous supply throughout Delhi and to facilitate cost benefit analysis in terms of savings on account of reduction in NRW. Recommend any institutional reforms required in parallel to supplement the technical efforts e.g. billing and revenue collection, strict enforcement against illegal connections, training, etc. In addition to the work in these two zones, consideration will be given to the installation of high quality customer meters which can operate accurately in other zones that will continue to experience intermittent supply for much of the transition phase. Preliminary estimates show the payback period for installing these to be around six months. A systematic programme of illegal connection detection and legalisation for their incorporation into the system or their removal will also be undertaken. Delhi Jal Board 12 Delhi Water Supply & Sewerage Sector Reform Project 6.2 Bulk Supply and Sewerage Infrastructure Improvement Objectives: City wide improvement in service will require a re-structuring of the bulk transmission system and distribution networks combined with reduction of losses and equitability in bulk supply. The focus at this initial stage, however, will be on enhancing the operational efficiency and effectiveness of the present infrastructure through refurbishment of the existing bulk supply and treatment infrastructure rather than creating additional water resource and treatment capacity. The environmental issues of declining water quality and pollution are also an integral part of environmental management. With respect to sewerage system, measures will be taken to optimize the carrying capacity of existing infrastructure – rehabilitating and replacing it as necessary – before embarking on extensions to the sewerage system. Attention will also be given to improving the utilization of existing wastewater plants including treatment and disposal of sludge. Framework of Action: Based on an assessment of the present situation, certain project components critical to meet the immediate requirements have been identified and prioritized in the DJB Project Preparation Study. These shall be undertaken in the next 2 years for city-wide improvement in water supply and sewerage services. The priority works which have been identified are as follows. Bulk Supply Metering Metering – both bulk and customer metering - is essential to reduce water losses and encourage prudent utilization of water. The installation of bulk meters will be undertaken on the transmission and distribution systems to facilitate improved operational efficiencies and to ensure transparency and accountability of water supplied to different parts of the city. Effort will also be made to meter supplies supplied through standposts and tankers. The DJB Project Preparation Study has already identified the locations where bulk meters are required on the transmission mains. Replacement of customer meters will be an integral part of the Phase 1 distribution improvements. Once the pace of the full roll-out programme has been defined, a decision will be taken as to whether to install customer meters capable of functioning under intermittent supply conditions in areas where 24-7 supply will not be available for some time. Restructuring transmission main system, rehabilitation of WTPs Based on the DJB Project Preparation Study, rehabilitation of selected elements of the water supply infrastructure has been identified. It is proposed to restructure the transmission main system, including relaying of sections of transmission mains to rectify joint problems caused by surge pressures in the system. Measures for upgrading pumping station efficiency, construction of new booster pumping stations and ground level reservoirs to serve new areas, identification of tappings and unauthorised distribution off-takes in the transmission mains, and their removal will be also undertaken. For better utilization of the existing capacity, rehabilitation of existing WTPs will be undertaken including measures for provision of minimum instrumentation, improved intake desilting facilities, renewal of existing motors and replacement of pump impellers. Pilot projects to introduce best industry practices for efficiency improvements and training of employees in select treatment plants and pumping stations shall be undertaken in the next phase. Delhi Jal Board 13 Delhi Water Supply & Sewerage Sector Reform Project While the above interventions are not expected to add much new capacity to existing treatment plant capacity, the main benefit is likely to be in terms of reduction in real losses, i.e. losses at the water treatment plants and water transmission mains, rationalization of water supply, and extension of supply areas in few cases Detailed designs have been prepared for the projects to be undertaken as part of the DJB Project Preparation Study. The details of the project and cost estimates are given in the Annexure 2 Refurbishment of existing wastewater collection, treatment and disposal system The focus during this stage will be on improvement in the sewerage network through desilting, rehabilitation and relining of critical sections of trunk sewers, better utilisation of existing wastewater treatment plant capacity, upgrading efficiency of pumping stations, rather than measures for additional capacity. The cost-effectiveness of local, decentralized treatment of wastewater for discharge to local nallahs and drains will be compared with its longer conveyance distances by means of interceptor sewers and pumping stations to larger regional treatment plants. In accordance with the DJB Project Preparation Study, a set of measures capable of being executed in the next two years have been identified for enhancing sewer carrying capacity and for reducing the discharge of untreated wastewater into the drains. The prioritisation of the various components involved has taken account of the immediate need as per the current situation and a range of other factors such as cost per capita, environmental impact, health benefits, water usage and planning. The details of the project and cost estimates are given in the Annexure 3. Detailed designs have been prepared as part of the DJB Project Preparation Study. Measures for water quality Comprehensive and systematic monitoring of water quality supplied is proposed. The concentration of residual chlorine is closely monitored at the treatment plants and to a lesser extent in the distribution system. More attention will be given to ensure reasonable water quality in the distribution system. Even though the results of such checks indicate water of a potable quality being delivered to customers, however, it is highly likely that some contamination of the water takes place in the distribution system due to the intermittent supply situation. Poor water quality may be also attributable to leaking pipes, proximity of water lines and sewer lines, user of boosters etc. Even though, the tests conducted reveal that quality of treated and distributed water meets the requisite standards, however the customer is often dissatisfied with the quality of water. This apparent disparity may be explained by the deficient sampling methods, timing, testing and location of procedures being followed. A specific programme on water quality monitoring improvement is proposed to be launched taking the command area of one treatment plant from the plant through to the customer, using international best practices. As part of this initiative, a comprehensive programme of laboratory upgradation, improvement in sampling techniques and water quality analysis and reporting mechanism is to be undertaken. Energy Audit An energy audit of major installations will be done to judge the efficiency of the existing equipment and their operating environments in order to identify measures that are required to reduce energy consumption. A preliminary assessment of the energy consumed by various facilities of DJB has concluded that there is significant potential of substantial energy savings. Based on the outcome of such audits, further steps will be taken to improve efficiency and the operational aspects. These measures include use of energy-efficient motors, regular monitoring of pump efficiency, calibration of measuring instruments at regular intervals, say every two years, altering the operational environment; establishing a proper yearly preventive maintenance programme for major and medium size pumping stations, and strictly adhering to it. Delhi Jal Board 14 Delhi Water Supply & Sewerage Sector Reform Project 6.3 Organizational Improvements Objective: Customer orientation and capacity building shall be the foundation for enabling the entire reform process. The focus will be on HRD aspects for harnessing the potential of all employees as well as building and sustaining core skills essential to the growth of the organization in the changing operating environment. Various measures shall be taken to improve DJB’s internal organizational efficiency and for better consumer responsiveness including development of a comprehensive CRM package. . Framework for Action: Restructure performance appraisal system It is proposed to restructure the performance appraisal system through identification of clear objectives and Key Result areas. A list of indicative KRAs across various functions and levels has already been identified as part of the DJB Project Preparation Study. Measures will be taken to incorporate them in the annual Appraisal Process after consultation with the employees. The objective will be to institutionalize a performance oriented culture that explicitly rewards and recognizes merit. Training The DJB Project Preparation Study has proposed a comprehensive training plan across various levels. Further detailed Training Needs Assessment shall be done based on the performance review of the individuals in relation to the present and envisaged role. Suitable arrangements including collaborating with some institutions to impart training will be made. The focus will be also on developing management and internal leadership skills for facilitating effective change management. ‘Training the trainers’ approach will be also adopted for knowledge management. This might first be implemented in the Phase I distribution improvement projects. Managers and staff who have received training and gained implementation experience will be given the means to share their knowledge and expertise with others for replication of the same across various other zones. Enhanced delegation of powers The financial delegation of powers will be reviewed for enhanced empowerment at appropriate levels for decision making. The objective will be enhanced decentralization of powers and matching of resources with responsibility for effective and efficient decision making. Staff rationalization It is proposed to determine appropriate staffing requirements for all levels at DJB in context of the proposed sector reforms. An assessment of the current job description, age profile, liabilities on account of employee benefits e.g. pension, gratuity and benchmarking against laid down norms will be done. Measures will then be taken for dealing with the excess manpower. These include Voluntary Retirement Scheme for DJB employees and redeployment through training. Computerized Customer Service Centres Computerized Customer Service Centres (CSCs) are proposed as a one stop customer interface for all key aspects of customer services - provision of information, processing of applications for connections, billing and collection services and handling of customer grievances. It is proposed to Delhi Jal Board 15 Delhi Water Supply & Sewerage Sector Reform Project set up the CSCs in 21 locations and also to set up centres with provision for enhanced options for payment collection in 21 other locations across Delhi. In line with the Government’s intention to move towards an e-Delhi, web based interactions viz. downloading of forms, making bill payments online, registering of complaints and checking status online etc. will be facilitated. To implement this, it is proposed to outsource the development, installation, operations and maintenance to a service provider along with other IT applications detailed out in the next section on a Build-Own-Operate basis for a period of five years. The contractor shall be selected on a competitive bidding basis and will need to adhere to the defined performance standards. It is proposed to pay the service provider on the basis of fees per transaction for the Customer Service aspects and fixed monthly fees for all other aspects viz. Personnel Information system, Project Monitoring system and Groupware. A Project Management Consultant will be appointed to facilitate the selection of the service provider and bring in the technical expertise for effective implementation of the above IT applications, Modern MIS & use of IT Presently, DJB has operational revenue billing system, website, and backbone for the HQ LAN in place at HQ, and limited usage of PCs in some departments and divisions for day to day working. The new initiatives undertaken by DJB include implementation of computerized Financial Accounting, Costing and Fixed Asset systems as part of DJB Project Preparation Study, gradual use of GIS with the assistance of NIC for digital mapping, development/procurement of systems such as Payroll and Contract Recording. There is a proposal to prepare an Action Plan for Hydraulic network modeling and gradual use of a SCADA system. In order to improve efficiency across various departments, and facilitate effective and informed decision through inter and intra-office communication, an IT strategy has been developed as part of the DJB Project preparation Study. During this stage, the key application areas that are critical to DJB operations from the perspective of Customer Service and Operational Efficiency will be undertaken. These include - An integrated Personnel Information and Payroll Management System to maintain all employee related information and facilitate better planning and management with respect to the human resource development. The PIS would maintain all employee-related information such as salary records, personal details, appraisal information etc., and would enhance the working of the HR function. - Project Monitoring System for effective Project and contract management. The application would assist DJB in monitoring projects, tracking the work item-wise progress of projects, assessing adherence to contractual obligations and in managing allocation of resources to various projects - Groupware to facilitate communication, coordination, and collaboration. The groupware for DJB would comprise of e-mail system for both intra-office and inter-office communication with no limits on the geographic coverage and a Workflow Application i.e. enable the automation of operational processes, managing the movement of information as it flows through the sequence of steps that make up the work procedure by maintaining changes in status and the state of the document or transaction. The development, installation, operations and maintenance of the above applications shall be outsourced to a service provider on a Build-Own-Operate basis for a period of five years. The software shall be owned by DJB along with all its rights. The service provider would be selected on a competitive bidding basis. A Project Management Consultant will be employed to select the service provider and provide technical expertise in the initial stages of design, development, Delhi Jal Board 16 Delhi Water Supply & Sewerage Sector Reform Project installation, implementation and initial operations of the various systems envisaged. DJB has already taken steps to facilitate this. The use of other IT applications such as Computer Aided Design, Inventory Management, Document Management System, Integrated MIS, effective use of existing GIS, SCADA shall be undertaken in the next phase. Enhanced Communication The thrust of the proposed reform project is also getting the stakeholders together and building consensus. The objective is to ensure clear public understanding of the reform measures and their benefits, encourage transparency, and build support for reform process. A communication plan will be designed and implemented for DJB to address the concerns of various stakeholders – internal and external. The stakeholders include DJB management and staff, consumer associations and representatives, NGOs catering to the low income groups, Indian and international WSS industry, international development agencies, media etc. The Communication Plan shall include dissemination of information and making stakeholders aware of the existing constraints, identification of the main concerns of the various stakeholders, measures/ clarifications to alleviate the same, identification of appropriate media to convey, and soliciting and analyzing the feedback from various stakeholders. 6.4 Targeted Services to the Poor Objectives: In the present situation, the poor are particularly hard hit with inadequate access and huge coping costs. All institutional and technical interventions shall be designed with a clear obligation to improve the service to the poor. The objective will be to ensure access to the economically weaker sections of the society through specific pro-poor measures. Framework for Action: Assessment of the needs for the Poor using CBIS Presently, development of strategy for improved services to the poor is constrained by the lack of data on their situation. Further efforts will be focused on understanding and explicitly addressing the conditions under which the poor gain access to water supply and sanitation services before designing any specific pro-poor interventions. The information required includes identification of areas where they reside, the actual population who are ‘water vulnerable’ – do not have adequate access to services, current coping mechanism and costs, capacity and willingness to pay as well as preferred mechanism to meet their needs. Measures such as conduct of baseline surveys, use of tools such as Community Based Information System, public consultative processes through forging partnerships with representatives of NGOs and community organizations will be encouraged. The objective will be to solicit feedback in design of realistic objectives, targets and interventions to improve the services to the poor. For the zones selected for Phase I continuous supply, a rapid assessment including updating and integrating CBIS with existing DJB database, dialogue with poor community aided by NGOs shall be done to obtain the requisite information. Pilot Projects for Community Mobilization Pilot projects will be undertaken for improving water and sanitation services to the poor. The objectives shall be to analyze the potential of community mobilization to cater to the needs of the poor and collaboration with NGOs, communities to better serve the needs of the poor. This will also include assessment of the use of cost effective arrangements for linking the poor to the Delhi Jal Board 17 Delhi Water Supply & Sewerage Sector Reform Project mainstream e.g. through use of community contracts, water kiosks, decentralized STPs etc. and cost benefit analysis of the present supply of water through tankers vis-à-vis supply through piped water, tanks etc. The model will be selected based on the technical feasibility, financial viability, legal aspects, ability to mobilize and management capacity of the communities etc. and then be institutionalized based on the lessons learnt. 6.5 Roll out Programme Development Objective: Given the significant infrastructure investment required, it needs to be set in context of a development plan. While it is essential to identify the urgent works and implement them, there is a need to develop a roll out plan simultaneously based on a detailed assessment of the existing situation and lessons learnt from the Phase I interventions for effective replication across the entire city. Framework for Action: An immediate study will be undertaken for developing a comprehensive system infrastructure development plan with the objective to outline a water supply and sewerage system for Delhi to cope with the expected future demand and translate the vision of universal service coverage and 24/7 water supply into a reality. The main components shall include: - Water resources planning for a horizon of 50 years - Water supply and sewerage infrastructure planning and programme for implementation – rehabilitation and extension for a horizon of 20 years - Water and wastewater service objectives and levels - Outline of a comprehensive water supply system for Delhi based on a restructured distribution system, enable equitable supply conducive to effective monitoring and control - Social and Environmental Management Plan - Outline of a comprehensive wastewater system for Delhi, comprising full coverage by sewer networks and collector sewers, storm drainage management, sewage and sludge treatment and disposal/beneficial reuse - Cost estimates and affordability analysis leading, in combination with definition and implementation of priorities to a staged programme of implementation Based on the lessons learnt from Phase I distribution improvement, a roll out programme for progressive city wide implementation will be developed. It shall include - Action Plan and agenda for reduction of the various components of Non Revenue Water - Reorganization of DJB’s operational zones so that each zone is discrete in all aspects of its operations viz. incoming water, distribution, maintenance and repair, non-revenue water control, billing and revenue collection and customer services - Identification of a strategic infrastructure investments needed to meet medium and long-term goals and specifications, in terms of costs and further design requirements The pace of implementation should be linked to affordability as well as keeping in mind the social and environmental needs. The development of the plan will require credible base data regarding population and water demand projections, system mapping on GIS base, metering of bulk and sewage flows, hydraulic modeling and network analysis to identify the required improvements and extensions. It is proposed to involve the planning, design and operational staff Delhi Jal Board 18 Delhi Water Supply & Sewerage Sector Reform Project DJB staff throughout the preparation of the Infrastructure Development and roll out Plan to facilitate a good understanding of issues and its effective implementation. 7. Expected Outcome Addressing the water supply and sanitation sector has a visible impact on multiple fronts such as poverty alleviation, environmental sustainability, public health, life expectancy, participatory development and good governance. Even though the net benefits are difficult to quantify, they can be expected to be positive. It is envisaged that the Reform Project shall be the driving force in Delhi to turn around the current situation of general poor performance into sustainable high quality services for all. The target beneficiaries of the various components of the reform measures shall be the urban population of Delhi, totaling about 14 million. Tangible economic benefits should result from technical interventions by leveraging capital investments. The improvements in services are expected to provide the foundation for DJB to increase tariffs for all beneficiaries and thereby improve cost recovery levels. The provision of improved services through the proposed interventions will lead to positive economic impact in terms of - reduction in coping costs; - positive fiscal impact on the state finances in the medium to long term since the project envisages gradual phasing out of subsidies from the Govt. - broader access to adequate water supply on a reliable basis would also benefit industrial consumption and thus support economic development - other indirect economic benefits such as increase in value of real estate in areas with adequate access to water supply and sewerage services, increase in employment, increase in income from tourism. With respect to water supply, tangible improvements can be expected to be achieved including: - city wide improvement in quality of services - improved equity and security of bulk supply - upgraded water transmission system - reduced health risks with better quality monitoring - improved operational efficiency For the Phase I zones the impact will be significant in terms of: - continuous water supply and improved sewerage services to around 12% of DJB’s connections - significant reduction in non-revenue water - improved cost efficiencies and staff productivity - 100% customer metering - improved customer satisfaction and revenue collection - improved service levels to the poor With respect to the environmental impact the significant positive impact includes: - improved capacity utilization of the STPs - reduced pollution and contamination of River Yamuna - possible improvement in water quality and improved health and hygiene due to reduction in overflows to drains and cross contamination by sewer lines; - better control and management of environmental issues due to effective monitoring Delhi Jal Board 19 Delhi Water Supply & Sewerage Sector Reform Project The organizational reforms are expected to result in: - Improved efficiency - Enhanced staff productivity through training across all levels - Increased motivation of DJB employees through performance incentives - improved accountability and transparency of operations - improved customer interface In Phase I zones also, the employees will significantly benefit through training in modern water operational management practices as well as share of performance-related bonuses awarded to Operator The desired social development outcomes expected out of the project interventions are: - improved and equitable coverage of un-served and under-served poor households at reasonable cost; and - substantial positive effect on women (time and effort) and better health for the entire family through assured supply of safe water in adequate quantity made available to the households - empowerment of users through encouraging stakeholder participation and adequate consultative mechanism 8. Institutional Framework for Implementation As a backdrop to the reform process and for its effective implementation, a Performance-based Memorandum of Understanding (PMoU) is proposed. It is proposed to reorient the plan financing into a mechanism of flow of funds linked to improvement in DJB’s performance. A PMoU should be signed between the Government and DJB, for a period of five years initially, by means of which the release of funds would be benchmarked to operating performance and agreed milestones. The performance targets to be met by DJB over the duration of the Reform Project as well as the required commitments from the Government for creation of an enabling environment will be embodied in a Performance MoU agreed by both the Government and DJB. The PMoU shall include: - Performance Indicators with their baseline benchmarks, and progressive improvement targets which DJB is committed to achieve. In case baseline data is not available, a time plan for data generation and improvement plan shall be considered - Commitments on part of the Government - Capital expenditure plan for project implementation during the horizon of the PMoU. This shall be firm for one year and tentative for subsequent years (annually revised based on the availability of data and previous year’s performance ) - Defining linkage between performance improvement & funds from GoNCTD - Monitoring mechanism - performance (DJB) and reforms (GoNCTD) The PMoU shall specify the following mutually agreed commitments during the transition period for smooth implementation of the reform project. On behalf of DJB - demonstrating quantifiable increase in the key performance indicators it is committed to achieve with respect to quality of services, service coverage, services to the poor, etc. - Improving efficiencies to reduce costs - the evolution of key financial indicators it is committed to achieve On behalf of the Government of NCT of Delhi Delhi Jal Board 20 Delhi Water Supply & Sewerage Sector Reform Project - - initial tariff hike and the evolution of DJB’s tariff level and structure with improved services (in absence of regulator) creation of an enabling environment through independent regulatory body to regulate tariffs and set and enforce service standards Establishing minimum governance requirements through improving operational autonomy, delineation of the role of the Government as the policy maker with increased powers of management of affairs to be vested with the Board. The Government may ensure adoption of the same through amendment of the existing DWB Act Financial Support - The Government may consider one time writing off of the old debt liability to allow DJB to start with clean books of account. Also, for sustainability of DJB it may consider grant funding to meet the approved capital investment needs. The provision of subsidy for O&M expenditure should gradually decline based on performance improvement The objective will be ‘gradual phasing out of Government subsidies by the end of the initial PMoU period and recovery of the costs of efficient O&M’ as reflected in the diagram. Independent monitoring of the PMoU and public disclosure of performance is also proposed for effective implementation. Annexure-4 sets out two scenarios of required government support. T2 Phasing out of Govt. subsidies based on Performance MoU Current O&M costs Reduction in Govt. subsidy T1 Tariff - Government Subsidy Efficient O&M Cost Phase wise increase in Tariffs Current Tariff T0 For smooth co-ordination and 0 1 2 3 4 5 Year implementation of the Reform Programme, a high level, multi disciplinary task force headed by the Chief Secretary and comprising the Principal Secretary (Urban Development), Principal Secretary (Finance), external advisor may be set up. The task force shall be responsible to play a lead role in the development of the PMoU as well as provide oversight and advisory role during the reform process. The task force will also facilitate interface with other agencies such as MCD, NDMC and other government departments for synergizing efforts towards achieving a common objective. Deep engagement and participation of DJB staff would be important to gain ownership of the reform project. A Project Management Group will be constituted within DJB headed by a Project Director and comprising of officers drawn from different areas of DJB to coordinate the activities relating to the reforms. The objective would be to have champions to keep the momentum for this comprehensive initiative. The Project Management Group will also: Facilitate coordination and procurement of various studies and activities under the reform project Facilitate prior approval and clearances from relevant authorities Monitor through feedback from consumers, NGOs At the ground level, specific working groups/ task forces may be constituted in various areas to collect and consolidate required data and information and facilitate implementation of the reform programme. Delhi Jal Board 21 Delhi Water Supply & Sewerage Sector Reform Project 9. Stakeholder Concerns & Mitigation Measures The success of the reform programme will critically depend upon its acceptance by the DJB employees, customers and potential private players. It is essential that their fears and apprehensions, the risks perceived with respect to the reform project are addressed and doubts clarified. The risks perceived by the various stakeholders as well as the mitigation measures are outlined below: PERCEIVED CONCERNS/ RISKS GOVERNMENT Lack of political acceptance due to perceived decline in the role of the Government MITIGATION MEASURES - - Resistance by Government to increase tariffs since: - Water a merit good with high service obligation - To make it affordable to the poor - DJB MANAGEMENT & EMPLOYEES Resistance by employees to Management Contract in Phase I zones – perceived ‘privatization’/ fear of losing jobs - Lack of private players forthcoming - Increased capital costs due to high cost estimates by the private player Increased costs due to involvement of the private player - Employees resistance to VRS Lack of adequate capacity within DJB to design and implement various projects Lack of capacity of DJB employees to undertake the new role Delhi Jal Board - Need to convince that the proposed reform process does not envisage a decline in the role of the government but shift towards a facilitator and enabler role Need for initial discussions with the Government regarding the reform measures and incorporation in the Performance MoU Need to convince that high universal obligation justifiable but paradoxical if this results in lack of access to services Main objective of reform project to improve efficiency, viability which does not go against social commitment prerogative Subsidies for poor to continue but to be made transparent Phase increase in tariffs in part linked to improved services Independent regulator to ensure increase in tariffs with improved services subsequently Deployment of DJB employees as well as continued service conditions to be essential as part of the Management contract Explain why operator involvement essential to success of Phase 1 distribution improvement Enhanced internal communication to demonstrate the perceived benefits – opportunity for training, share of performance related bonuses Need to gauge the interests and involve the private players to understand & address their concerns during preparation of the project structure and bid criteria Independent technical pre-feasibility study by DJB for estimates of the capital investment required Need to compare the proposed costs when realised with efficiency gains to the cost of continuing with the existing situation Determine sustainability of efficiency gains without operator involvement Need to design an attractive package DJB to undertake efforts for redeployment of employees affected by VRS Effective internal communication strategy Use of professional advisory firms with requisite experience for assistance in selection of contractor Continuous capacity building and training of employees Training by the operator to be an essential component of any activity contracted out 22 Delhi Water Supply & Sewerage Sector Reform Project PERCEIVED CONCERNS/ RISKS Legal hassles for extension of services to the poor CUSTOMERS Tariff hike – Low willingness to pay - - - Poor service quality & standards PRIVATE PLAYERS Unrealistic expectations by DJB Lack of basic information precluding the ability of the private player to bid - - Transparency in selection of private player - MITIGATION MEASURES In case of services to the poor, need for forging partnership with NGOs Need for interface with other agencies such as MCD to synergies efforts for common objectives Need for enhanced measures for dissemination of information to public to show it justifiable to recover costs of ‘efficient O&M’ Tariff hike to be accompanied by improvement in services subsequently for improved acceptance Independent regulator to set tariffs with increased consumer consultation Explain benefit of phasing out customer coping costs Independent regulator to ensure service standards Performance obligations to be integral part of any management contract Need for adequate consultation/ gauging of interest by DJB during formulation of bid criteria Independent technical studies by DJB to generate adequate information Sufficient time during the bidding process for conduct of due diligence by the private player Selection of contractor through PQ process and competitive bidding Standard guidelines/ evaluation criteria for evaluation to be mentioned in the bid document DJB to specify the capital investment required and performance standards to be adhered to. The implementation strategy proposed should be at a broad level leaving some flexibility with respect to implementation plan with the private contractor Clear contract specifications with respect to all relevant clauses on performance & default and independent monitoring Timely funding assurance by DJB/ Use of escrow account Stringent Capital Investment & Implementation Plan by DJB - Operational hassles i.e. - delay in payment by DJB - procurement delays - Lack of operational control e.g. - employees of DJB - policy measures for taking stringent actions against delinquent customers Issues in interfacing with other agencies, delays in approvals - DJB to ensure effective powers to the private contractor & matching of responsibility with authority - DJB to provide adequate support to facilitate interface with government agencies - While identifying the projects, emphasis has been on reducing the potential direct negative impact of the project on the environment and the people. The social components were carefully addressed in the project design, along with technical, environmental and economic considerations. The major concerns include not only minimizing negative impacts especially displacement but also extending and enhancing positive impacts on the affected communities and large population of Delhi. Delhi Jal Board 23 Delhi Water Supply & Sewerage Sector Reform Project With respect to the social impact, there are insignificant adverse social issues at most sites. Land acquisition requirements have been minimized to the maximum possible extent consistent with the technical and economic feasibility of the system. There is no direct negative impact of project components. There are no encroachers/ squatters, litigation, disputes and grievances of any type. Income restoration is also not necessitated, as the livelihood and income generating activities are not affected except to very a few shopkeepers, hawkers/ vendors temporarily for a limited number of days during the rehabilitation works of water supply and sewerage projects (for whom adequate compensation has been assessed and proposed). There is no demolition of structure and dislocation of people. Measures will be taken to minimize traffic congestion, inconvenience in mobility to public etc. by the diversion of traffic with adequate signage for the facility of transport movement and to avoid any accident. Similar safety measures will be taken for the rehabilitation of transmission mains having traffic congestion and public disruption. The earnings of hawkers, vendors etc. impacted due to rehabilitation works will be minimized by working in late evenings with an adequate number of machines and manpower to complete the task in less duration. With respect to environmental impact, it will be ensured that all government and funding agency requirements and procedures relating to Environmental Assessment are complied with. The following measures shall be also taken to minimize the adverse impacts and enhance beneficial impact. - Construction during daylight hours to avoid noise in residential colonies. Barricading the work site with proper signage for smooth traffic movement. Use properly maintained equipments for excavation / digging / emergency power. Appropriate design for embankments of excavated earth. Provide appropriate dewatering and drainage facility to avoid formation of water pools. All noise emitting and polluting machinery to conform to noise / emission limits prescribed by Pollution Control Board. Confined space working protocol and enforcing PPE for hazardous operations. Disposal of waste / grit / solid waste to be at designated site. Oil Grease to be dry mopped. Storage of diesel / oil to be in a designated protected area. Use of PPE for site workers to be strictly followed. Wiring and Electrical works to follow State (NCR) Electricity Regulations. Routine analysis of waste and maintaining records. Occupational Health and Safety awareness, use of PPE, safety signage. Maintenance of measuring instrument. Adequate training of operators. Detailed Social Assessment and Environmental Management Plan has been prepared as part of the DJB Project Preparation Study. Delhi Jal Board 24 Delhi Water Supply & Sewerage Sector Reform Project 10.Summary Matrix of the Reform Project GOAL REFORM COMPONENT CONTINUOUS SUPPLY Phase I Distribution Reform Project EFFICIENCY & ENVIRONMENTAL SUSTAINABILITY Consumer Metering 5 6 Bulk Supply & Sewerage Infrastructure Improvements ACTION PLAN TIME FRAME - Choice of zones for Phase I implementation - Data Collection by DJB - Procurement of Consultants - Technical Advisor - Transaction Advisor - Draft Bid Documentation - Pre-qualification - Bid Process commences - Completion of Evaluation - Negotiations & Award of Contract Installation of high quality consumer meters which can operate accurately in areas of intermittent supply April 2004 Procurement and Installation of bulk meters Procurement of Leak detection equipment Rehabilitation of WTPs, Pumping stations, restructuring transmission mains, construction of UGRs, BPS for equitable supply (Batch 1 projects) - Finalization of tender documents & contract packages - Procurement of contractor & Project Implementation EXPECTED OUTCOME TENTATIVE COSTS5 SOURCE OF FUNDING World Bank Substantial improvement in services categorized by - Continuous supply for 12% of the connections - Improved cost efficiencies - Significant reduction in NRW - Bulk metering & 100% consumer metering - Improved billing and collection efficiency - Improved customer satisfaction - High quality & effective consumer metering - Reduction in NRW US$ 60 million US$ 6.5 million DJB Plan Fund 2004 – 2006 - Equitable distribution of bulk supply US$ 3.3 million DJB Plan Fund 2004 - 06 - City wide improvement in water supply, service coverage Reduction in unauthorized tappings Improved capacity utilization Reduction in NRW Improved operating efficiency US$ 26.5 million DJB Plan Fund6 May – July 2004 July 2004 Aug 2004 Nov 2004 Dec 2004 Jan 2005 Sept 2005 Oct 2005 Commence in July 2004 - Assuming 1$ = Rs 46 Refer to Annexure 2 for details Delhi Jal Board 25 Delhi Water Supply & Sewerage Sector Reform Project GOAL REFORM COMPONENT ACTION PLAN Water quality – Study for better testing & sampling procedures 7 8 TIME FRAME EXPECTED OUTCOME - Improved drinking water and public health Improved institutional capacity for water quality management Cost to be estimated after study - Improved capacity utilization of STPs Reduction in overflows to drains Enhanced operational efficiency Total7 - US$ 66.2 million for total trunk WW investments LCB – US$ 14.8 million ICB – US$ 50.5 million JBIC – US$ 0.9 million (under YAP II & III) - Increased cost efficiencies Study – US$ 0.20 million Implementatio n Measures8 – Water- US$ 5.5 million Wastewater – US$ 11 million By Sept 2004 - Upgrading laboratory facilities & institutionalizing lessons learnt Refurbishment of existing wastewater collection, treatment & disposal system - Finalization of tender documents & contract packages - Procurement of contractor - Projects Implementation By April 2005 Energy Audit of major installations Develop Plan for Energy Conservation Implementation of measures for reducing energy costs By March 2004 April 2005 2004 -06 April 2005 onwards TENTATIVE COSTS5 - SOURCE OF FUNDING DJB Plan Fund LCB - DJB Plan Fund ICB – World Bank JBIC DJB Plan Fund/ USAEP Refer to Annexure 3 for details Tentative costs. Actual to be determined based on study Delhi Jal Board 26 Delhi Water Supply & Sewerage Sector Reform Project GOAL REFORM COMPONENT Organizational Improvements – Human Resource Development ACTION PLAN - - CUSTOMER ORIENTATION & HRD EXPECTED OUTCOME TENTATIVE COSTS5 SOURCE OF FUNDING Performance Appraisal System - Define KRAs for functions Discussions with employees & revising the KRAs Modify Performance appraisal system Train & communicate to employees Implement new system Monitoring & Evaluation Training - Training needs assessment - Identification & tie up with institutes providing training - Develop Training Plan - Initiate training roll out - Linking training with PA - Monitoring & Evaluation Staff Rationalization - Analysis of age profile of employees - Review of current role, job description, work processes - Study of staffing pattern in other utilities/ benchmarking against laid down norms (by CPHEEO etc.) - Determine proposed staffing pattern & number - Assessment of the current employee liabilities through actuarial valuation - Design of suitable VRS package Delhi Jal Board TIME FRAME Sept 2004 Oct-Nov 2004 - Improved accountability Enhanced motivation & improved staff productivity Dec 2004 Jan 2005 Mar 2005 Continuous By Sept 2004 By Sept 2004 World Bank/ DJB Plan Funds - Improved staff productivity Enhanced cost effectiveness Enhanced skills and performance potential of all employees - Increased cost efficiencies Oct 2004 Nov 2004 Dec 2004 Continuous 0.5 – 1% of the Plan Budget per annum Aug 2004 Aug 2004 Oct 2004 Nov 2004 Nov 2004 Dec 2004 27 Delhi Water Supply & Sewerage Sector Reform Project GOAL REFORM COMPONENT ACTION PLAN Delegation of Powers - Review & revision of the delegation of powers Customer Orientation Modern MIS & IT Communication Delhi Jal Board Computerized Customer Service Centres - Hiring of Project Management Consultant for CSC - Short listing of potential bidders - Due diligence, Submission of proposal by private player - Bid evaluation, Negotiations & Award of contract - Commencement of operations of CSCs PIS, PMS & Groupware - Hiring of Project Management Consultant - Short listing of potential bidders - Due diligence, Submission of proposal by private player - Bid evaluation, Negotiations & Award of contract - Systems in place Design of Communication Plan - Identification of concerns of stakeholders - Clarifications to address the concerns - Identification of appropriate & dissemination of information - Monitoring & Evaluation TIME FRAME EXPECTED OUTCOME June 2004 - Improved accountability Matching of resources with responsibility June 2004 - End June 2004 Aug 2004 - Enhanced consumer responsiveness & speedy redressal of customer grievances Training of employees by the contractor TENTATIVE COSTS5 SOURCE OF FUNDING US$ 4 million DJB Plan Funds Sept 2004 May 2005 June 2004 - End June 2004 Aug 2004 - Sept 2004 Improved operating efficiency across various departments Capacity building/ training of employees Effective and informed decision through inter and intra-office communication May 2005 By July 2004 Sept 2004 Nov 2004 Continuous Reduced resistance from stakeholders Increased customer awareness, commitment and ownership for reforms Effective implementation of the reform process World Bank 28 Delhi Water Supply & Sewerage Sector Reform Project IMPROVED SERVICES TO THE POOR GOAL REFORM COMPONENT Targeted Services to the Poor – Demand Assessment ACTION PLAN Assessment of needs of Poor using CBIS - Development of partnerships (NGOs & other stakeholders) - Information gathering - Phase I of Continuous Supply - Entire Delhi TIME FRAME EXPECTED OUTCOME - July 2004 Oct 2004 March 2005 TENTATIVE COSTS5 Better understanding of the existing coping mechanism & who constitute the ‘poor’ Design of realistic objectives, targets, & interventions for improved services to the poor SOURCE OF FUNDING World Bank World Bank Pilot Projects ROLL OUT Roll Out Programme Delhi Jal Board Pilot Projects - Development of partnerships (NGOs & other stakeholders) - Testing appropriate models - Guidelines for Services to Poor - Formulating phased approach - Start Rolling out interventions - Monitoring & Evaluation - Capacity Building of DJB staff Infrastructure Development Plan - Preparation of System Development & Roll Out Plan based on system study & learning’s from Phase I distribution reforms - Tender documents for planning rationalization in trunk infrastructure for Continuous Supply regime July 2004 By Dec 2005 By Dec 2005 By Dec 2005 April 2006 Continuous Continuous - By Dec 2006 Improved service quality, coverage to the poor Reduced revenue losses to DJB by linking the poor to the mainstream Institutionalizing of lessons learnt for replication and improved services to the poor City wide improvement in services and effective plan for realization of the Vision US$ 1.5 million World Bank 29 Delhi Water Supply & Sewerage Sector Reform Project GOAL REFORM COMPONENT ACTION PLAN TIME FRAME EXPECTED OUTCOME TENTATIVE COSTS5 SOURCE OF FUNDING INSTITUTIONAL FRAMEWORK FOR IMPLEMENTATION EFFECTIVE IMPLEMENTATIONOF THE REFORM PROJECT Tariff Rationalization Performance MoU - - Corporate Governance - Regulatory Body - Delhi Jal Board June 2004 Based on improvement in services - Formation of committee by Govt. for development of MoU Establishment of baseline Setting of realistic performance indicators & Govt. commitments Signing of Performance MoU between the Govt. & DJB Independent Monitoring Review of Composition of Board & delegation of powers Amendment to DJB Act Adoption of Corporate Governance principles e.g. commercial accounting, publishing of Annual Performance Report, external audit July 2004 - Aug 2004 Sept 2004 - Dec 2004 Mar 2005 - Passing of Delhi Water Regulatory Commission Bill by Govt. Finalization of Service terms & conditions of Members Constitution of Selection Committee Selection of Chairman & Members Notification of Establishment of Regulatory Body Finalization of organization structure, service rules & appointment of staff Fixing of initial tariffs & service standards by the regulator July 2004 - Sept 2004 - Sept 2004 Dec 2004 Dec 2004 - Initial tariff hike by Govt. Subsequent rationalization of tariffs - Oct 2004 Continuous Sept 2004 - Phase wise recovery of O&M Costs linked with improvement in services Enhanced financial sustainability Effective implementation of reform projects Increase performance orientation & accountability of DJB Positive fiscal impact in medium term due to gradual phasing out of government subsidies Enhanced managerial autonomy & accountability of the Board Increased transparency & accountability Depoliticisation of tariff decisions Effective monitoring of service standards Enhanced customer consultation Balance of interests of all stakeholders March 2005 April 2006 30 Delhi Water Supply & Sewerage Sector Reform Project 11. Annexure Annexure 1: Roadmap for Reforms – Key Milestones 2005 2006 2007 2007-15 2015 Delhi Jal Board DJB embraces the principles of Corporate Governance Integrated revenue and engineering zone management Setting up of Computerized Customer Service Centres Bulk metering & progressive introduction of better functioning consumer meters Commence introduction of 24/7 supply in the Phase 1 zones for approx 12% of connections Establish sound and transparent management, accounting and performance monitoring measures through Key Result Areas Independent water regulator in place Financially transparent DJB Accountable operational zones managing both revenue and operations and facilitate comparative benchmarking Measures for demand management in place Progressive introduction of 24/7 supply in Phase 1 zones; Introduction of industry best service practice in Phase 1 zones Recovery of entire O&M costs for areas with 24/7 water supply and phased recovery in other areas with progressive improvement in water supply Institutionalising arrangements for enhanced interface between DJB, community organizations, representatives of the poor Infrastructure Development Plan of Delhi ready and efforts for restructuring of the water supply and sewerage system based on the IDP to commence Setting of service standards and tariffs by regulator Progressive introduction of pilot operations of 24/7 & comprehensive roll out plan with performance targets Considerable improvement in quality of water supply in each zone including poor areas with progressive introduction of 24/7 supply Annual reports published by regulator on DJB’s performance with enhanced measures for efficiency, financially sustainability and grievance redressal Wastewater service to be progressively improved to entire service area including addressing needs of the poor areas DJB transformed into an efficient and customer oriented utility 24/7 water supply and wastewater service to the whole of Delhi including slum areas Universal access to water and sanitation services to be provided by a customer oriented, accountable service provider in an efficient, equitable and sustainable manner 31 Delhi Water Supply & Sewerage Sector Reform Project Annexure 2: Proposed Interventions for Water Supply (DJB Project Preparation Study) S. No. 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Projects Construction of new UGRs and BPSs with feeder mains Janakpuri Palla MBR Nilothi Sultanpur Dabas Bawana Burari Kirti Nagar Avantika Pitampura Rohini- Sector-7 Rehabilitation of Booster pumping stations G K (North) G K (South) Deer Park Khyala I Khyala II Than Singh Nagar Ramlilla Ground Punjabi Bagh Pahari Dheeraj (Old) Subhash Park (Old) Laxmi Nagar Okhla Phase II Jal Vihar Jhandewalan Naya Bazar Patel Nagar Rehabilitation of transmission mains 1 2 3 4 Existing Naraina main from Kukreja Hospital to Rajagarden to be replaced by MS pipe line of the same diameter First km d.s. Haiderpur I WTP of Khyala main; replacement of the existing PSC with MS of the same diameter First km d.s. Haiderpur I WTP of Mangolpuri main; replacement of the existing PSC with MS of the same diameter First km d.s. Haiderpur I WTP of North West main; replacement of the existing PSC with MS of the same diameter Delhi Jal Board Costs in Type of contract millions (INR) Construction 705.25 92.70 79.92 167.82 16.38 71.92 39.96 63.93 52.74 62.33 57.54 Construction 705.25 LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB 60.70 0.20 22.50 0.20 3.13 3.13 0.10 10.25 2.20 1.00 0.80 1.20 1.00 0.20 9.60 0.50 4.70 Construction Type of Total Costs Contract in millions (INR) 60.70 LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB LCB 235.96 235.96 25.01 LCB 13.81 LCB 17.87 19.51 LCB LCB 32 Delhi Water Supply & Sewerage Sector Reform Project S. No. Projects Costs in Type of contract millions (INR) Type of Total Costs Contract in millions (INR) 5 First km d.s. Haiderpur I WTP of West Delhi main; replacement of the existing PSC with MS of the same diameter 19.51 LCB 6 First km d.s. Haiderpur I WTP of Civil Lines main; replacement of the existing PSC with MS of the same diameter. 19.51 LCB 7 Replacement of existing Pitampura main along WYC 24.72 LCB 37.51 LCB 20.01 LCB 38.50 LCB Replacement of existing PSC pipe from Mother Dairy to Mandavli BPS with MS pipe of the same diameter Replacement of existing PSC pipe line 9 with MS pipe line of the same diameter (Bodella main) Lining and overall rehabilitation of 10 existing PSC pipe line (Hasthal Main) Rehabilitation of WTPs Turn-key 1 HP I & II 2 Wazirabad 3 Bhagirathi New process installations at WTPs Turn-key 1 HPI &II 2 Bhagirathi 3 Chandrawal 4 Okhla Recycling plant Turn-key 1 Wazirabad Equipment Leak detection equipment Bulk flow meters 8 Total Delhi Jal Board 60.00 60.00 LCB LCB LCB 95.00 95.00 LCB LCB LCB LCB 60.00 60.00 152.92 50.00 102.92 60.00 LCB 152.92 LCB LCB 1370 33 Delhi Water Supply & Sewerage Sector Reform Project Annexure 3: Proposed Interventions for Wastewater (DJB Project Preparation Study) SI No Zone Projects Costs in millions (INR)) LCB/ ICB 31.3 LCB Design 142.7 LCB Design 45.0 LCB Design 21.0 LCB Design Type Construction of new pumping stations 1 KS Construction of 12.5 mgd ( 57 mld) Jeevan Park WWPS 2 SH Construction of 48 mgd (218 mld) Preet Vihar pumping station 3 KS 4 CP 5 6 OK OD 6a OD 7 OD 7a OD 8 SH 9 SH Construction of 7 mgd (32 mld) Punjabi Bagh WWPS Construction of 7 mgd (32 mld) Roshanara WWPS or Anand Vihar WWPS Construction of new treatment plant Construction of new WWTP with tertiary treatment Mini treatment plant with sewerage system Decentralised mini treatment plant at Bawana with population 23000 and area approx 1 sq km Sewer network at Bawana with population 23000 and area approx 1 sq km Decentralised mini treatment plantfor Barwala population of 5000 and area less than 1 sq km 500 500.0 ICB 10 RR Provision of Inlet chamber for Rithala Phase II treatment plant and 10a RR Rehabilitation of aerators, digestors and mechanical bar screens for Rithala Ph I plant Turnkey 40 30.0 Turnkey LCB Design 10.0 Turnkey LCB Sewer network for Barwala population of 5000 and area less than 1 sq km New sewers (No of tenders depending location of 8) Proposed sewer leading to Jagriti WWPS Proposed sewer leading to Kalyanpuri WWPS Rehabilitation of existing treatment plant Total Costs in millions (INR) 240 Design 29.8 19.8 LCB Design 10.0 LCB Design 67.1 7.2 Turnkey LCB 59.9 115.1 Rehabilitation of pumping station & pumping main 11 11a OK OK Replacement of 1100 dia Kilokri pumping main for 300 m Rehabilitation of Ring Road pumping station Delhi Jal Board 5.0 Design LCB 20.0 34 Delhi Water Supply & Sewerage Sector Reform Project 12 OK Rehabilitation of Nigambodh pumping station and replacement of 750 dia Nigambodh pumping main 34.1 LCB Design 13 RR Rehabilitation of Haiderpuri pumping station 2.0 LCB Design 14 RR Rehabilitation of Bharat Nagar pumping station and replacement of rising main 10.0 LCB Design 15 CP Replacement of rising mains of SGT nagar, Panchawati, Azadpur, Tagore Park, BP colony pumping stations 25.0 LCB Design 16 CP Rehabilitation of Mukherjee Nagar pumping station 12.0 LCB Design 17 SH Rehabilitation of Preetvihar pumping station 7.0 LCB Design 146.5 Desilting of sewers 18 OK Desilting of 1050 dia Subhash Marg sewer 18a OK Desilting of gravity ducts no 2 & 3 from Kilokri to Okhla WWTP 18a KS Desilting of Vidya Marg Sewer 18a SH Desilting of 1400-1600 dia Trunk Sewer No 4 20.0 Term 18a SH Desilting of 1600-2100 dia Jhilmil colony to Jagriti pumping station 13.6 Term Desilting of secondary and internal sewer Desilting of secondary and internal sewers in CP-catchment 19 CP 20 RR Desilting secondary and internal sewers in Rithala- Rohini catchment 21 SH 22 23 4.5 Term 104.4 Term 4.0 ICB Term 498.3 80.0 ICB Term 140.0 ICB Term Desilting of secondary and internal sewers in Shahdara catchment 16.7 ICB Term KS Desilting of secondary and internal sewers in Keshopur catchment 201.6 ICB Term OK Desilting of secondary and internal sewers in Okhla catchment 60.0 ICB Term 1219.1 Desilting and Rehabilitation of trunk sewers 24 OK Desilting and rehabilitation of gravity duct No 1 from Kilokri to Okhla WWTP 80.0 24a OK Desilting and rehabilitation of 600x900 Sewa Nagar sewer 14.8 24b OK Desilting and rehabilitation of 900 dia Press Enclave Road Sewer 33.5 Delhi Jal Board Turnkey ICB Turnkey Turnkey 35 Delhi Water Supply & Sewerage Sector Reform Project 25 KS Desilting and rehabilitation of 1650 dia West Delhi trunk sewer 303.0 ICB Turnkey 26 OK Desilting and rehabilitation of 12002700 dia Ring Road trunk sewer 303.0 ICB Turnkey 27 KS 29.1 ICB Turnkey 27a KS 40.9 JBIC Turnkey 27b RR 121.9 ICB Turnkey 27c RR 42.6 ICB Turnkey 27d SH 18.3 ICB Turnkey 27e SH 16.3 ICB Turnkey 27f CP 215.6 ICB Turnkey Desilting and rehabilitation of 900-1200 dia Patel Road sewer Desilting and rehabilitation of 900-1100 dia Ring Road sewer from Naraina to Raja Garden flyover Desilting and rehabilitation of 1050 dia sewer from Old Rohtak Road to Bharat Nagar PS along Daryai Nallah Desilting and rehabilitation of 825 dia Tri Nagar to Bharat Nagar sewer along Najafgarh drain Desilting and rehabilitation of 2100 dia Trunk Sewer No 5 Desilting and rehabilitation of 900-1100 dia Mother Dairy Road sewer to Mandawali pumping station Desilting and rehabilitation of 600-1200 dia University trunk sewer 40 Reconstruction of settled sewers 28 RR Reconstruct settled sewers in Pitampura, Saraswati Vihar and Shalimar Bagh area 40.0 LCB Term 150 Automation of pumping stations 29 GEN Automate pump start/ pump stop for terminal wastewater pumping stations: Total 150.0 LCB Turnkey 3045.9 Costs are tentative based on similar projects or works Delhi Jal Board 36 Delhi Water Supply & Sewerage Sector Reform Project Annexure 4: Scenarios of Government Support Delhi Jal Board 37 Delhi Water Supply & Sewerage Sector Reform Project Delhi Jal Board 38 Delhi Water Supply & Sewerage Sector Reform Project Delhi Jal Board 39 Delhi Water Supply & Sewerage Sector Reform Project Delhi Jal Board 40 Delhi Water Supply & Sewerage Sector Reform Project Delhi Jal Board 41