Homework 2 Solutions IOM580- Project Management Fall 2008 Hiroshi Ochiumi 1) A project has been defined to contain the following list of activities, along with their required times for completion: Activity A B C D E F G H I Immediate Predecessors A A A B C,D E,F D G,H Time(days) 1 4 3 7 6 2 7 9 4 a. Draw the network diagram. (5 points) b. Show the early start and early finish times. (5 points) 5,11 E 1,5 6 B 11,18 G 4 8,10 7 0,1 1,4 A C F I 1 3 2 4 1,8 D 8,17 7 H 18,22 c. Show the critical path. (5 points) The critical path is A-B-E-G-I. d. What would happen if Activity F were revised to take four days instead of two? (5 points) New CP: A-D-F-G-I. Time of completion = 23 days. 2) Following are the precedence requirements, normal and crash activity times, and normal and crash costs for a construction project Required Time (weeks) Activity A B C D E F G H I Preceding Activities A A B B,C C E,F D,E H,G Normal 4 3 2 5 1 3 4 4 6 Crash 2 2 1 3 1 2 2 1 5 Cost ($) Normal 10,000 6,000 4,000 14,000 9,000 7,000 13,000 11,000 20,000 Crash 11,000 9,000 6,000 18,000 9,000 8,000 25,000 18,000 29,000 a. What are the critical path and the estimated completion time? (5 points) Critical path A-B-D-H-I. Normal completion time 22 weeks. b. To shorten the project by three weeks, which tasks would be shortened and what would the final total project cost be? (10 points) Activity A B C D E F G H I Cost per week 500 3000 2000 2000 0 1000 6000 2333.333 9000 Possible decrease 2 1 1 2 0 1 2 3 1 1st week: CP=A-B-D-H-I. Crash A at $500. Critical path stays the same. 2nd week: Crash A again. Critical path stays the same. 3rd week: A is no longer available. It is going to be either B, D, H, or I. We choose D at $2,000. Total cost for the project shortened three weeks is 97,000. If you do not compute cost/week correctly, I took 3 points off. 3) For the network and the data shown: 12 D 10 7 B G 6 10 6 A E I 8 9 C H 14 F a. Determine the critical path and the early completion time for the project. (5 points) A-C-F-H-I, 43 weeks, 6+8+14+9+6. b. Reduce the project completion time by four weeks. Assume a linear cost per day shortened and show, step by step, how you arrived at your schedule. Also indicate the critical path in each step. (10 points) Activity A B C D E F G H I Normal Time (weeks) 6 10 8 12 10 14 7 9 6 Normal Cost ($) 6,000 10,000 8,000 12,000 10,000 14,000 7,000 9,000 6,000 Crash Time (weeks) 4 9 7 10 7 12 5 6 5 Crash Cost ($) 12,000 11,000 10,000 14,000 12,000 19,000 10,000 15,000 8,000 Activity Normal Time (NT) Normal Cost (NC) Crash Time (CT) Crash Cost (CC) NT-CT Cost/week to expedite A 6 $6,000 4 $12,000 2 $3,000 B 10 10,000 9 11,000 1 1,000 C 8 8,000 7 10,000 1 2,000 D 12 12,000 10 14,000 2 1,000 E 10 10,000 7 12,000 3 667 F 14 14,000 12 19,000 2 2,500 G 7 7,000 5 10,000 2 1,500 H 9 9,000 6 15,000 3 2,000 I 6 6,000 5 8,000 1 2,000 Step Activity Cost to crash Weeks reduced Critical Path(s) 1 I $2,000 1 A-C-F-H-I 2 C 2,000 1 A-C-F-H-I 3 H 2,000 1 A-C-F-H-I, and A-B-D-G-I 4 H and D 3,000 1 A-C-F-H-I, and A-B-D-G-I $9,000 4 Total cost There are other ways to achieve this total cost, too. If you do not compute cost/week correctly, I took 3 points off.