Instructions for Submittal of a Large Facility Interconnection Request to the NYISO Introduction The NYISO Standard Large Facility Interconnection Procedures (LFIP), contained in Attachment X of the NYISO Open Access Transmission Tariff (OATT), apply to Generating Facilities that exceed 20 MW and to Merchant Transmission Facilities. The following instructions are for Developers that wish to submit an Interconnection Request to the NYISO under the LFIP.1 Submittal of an Interconnection Request to the NYISO To initiate an Interconnection Request, a Developer must submit all of the following: (i) a $10,000 nonrefundable application fee; (ii) a study deposit of $30,000; (iii) a completed application in the form of Appendix 1 of the LFIP (see attached); and (iv) demonstration of Site Control or a posting of an additional deposit of $10,000. To facilitate processing, NYISO prefers these items to be submitted electronically (fee and deposit(s) via wire transfer, application form and documentation of Site Control by e-mail). The scanned copy of the completed application and documentation should be submitted via email to: NewProject@nyiso.com Wire transfers are preferred for making deposits. Please request wiring instructions via e-mail from: Chelsea Bonesteel Accounting Associate, Finance Phone No. (518) 356-8805 E-mail: cbonesteel@nyiso.com If paying by check, make deposit check(s) payable to: New York Independent System Operator, Inc. A separate Interconnection Request must be submitted for each site and multiple Interconnection Requests may be submitted for a single site. A deposit must be submitted for each Interconnection Request even when more than one request is submitted for a single site. An Interconnection Request to evaluate one site at two different voltage levels shall be treated as two Interconnection Requests. Upon Receipt of an Interconnection Request Within five (5) business days of receipt of an Interconnection Request, the NYISO will: Acknowledge Receipt of the Interconnection Request, Forward a copy of the Interconnection Request to the connecting Transmission Owner(s), Review the Interconnection Request and notify the Developer and connecting Transmission Owner(s) if the request is determined to be invalid and the reasons for such determination, If the Interconnection Request is determined to be valid, provide a form Interconnection Feasibility Study Agreement to the Developer and connecting Transmission Owner(s). Within ten (10) business days after receipt of a valid Interconnection Request, the NYISO will establish a date agreeable to the Developer and connecting Transmission Owner(s) for a Scoping Meeting. S. Corey Revised 2/14/2014 1 Note that if there is anything in these instructions that is inconsistent with the LFIP, it is the effective LFIP that will govern. INTERCONNECTION REQUEST 1. The undersigned Developer submits this request to interconnect its Large Generating Facility or Merchant Transmission Facility with the New York State Transmission System or Distribution System pursuant to the Large Facility Interconnection Procedures in the NYISO OATT. 2. This Interconnection Request is for (check one): ____ A proposed new Large Generating Facility, named ___________________. ____ A proposed new Merchant Transmission Facility, named ______________. ____ An increase in the capacity of an existing Large Generating Facility or existing Merchant Transmission Facility. 3. The type of interconnection service evaluation requested for Class Year Interconnection Facilities Study: ____ Energy Resource Interconnection Service ____ Capacity Resource Interconnection Service ____ Partial Capacity Resource Interconnection Service 4. The Developer provides the following information: a. Address or location or the proposed new Large Facility site (to the extent known) or, in the case of an existing Generating Facility or Merchant Transmission Facility, the name and specific location of that existing facility; b. Maximum summer at _______ degrees C and winter at ______ degrees C megawatt electrical output of the proposed new Large Facility or the amount of megawatt increase in the capacity of an existing facility; c. Megawatt allocation for partial CRIS evaluation; d. General description of the equipment configuration; e. In-Service Date, and Commercial Operation Date (Day, Month, and Year); f. Name, title, company address, telephone number, FAX number and e-mail address of the Developer’s contact person; g. Approximate location of the proposed Point of Interconnection (optional); and h. Interconnection Customer Data (set forth in Attachment A). 1 5. Applicable deposit amount as specified in the LFIP. 6. Evidence of Site Control as specified in the LFIP (check one) ____ Is attached to this Interconnection Request ____ Will be provided at a later date in accordance with the Large Facility Interconnection Procedures 7. This Interconnection Request shall be submitted to the representative indicated below: Name: Title: Address: Phone No.: Fax No.: E-mail Add.: 8. Steven L. Corey Manager, Interconnection Projects 10 Krey Blvd. Rensselaer, NY 12144 (518) 356-6134 (518) 356-7524 scorey@nyiso.com Representative of the Developer to contact: [To be completed by Developer] 9. This Interconnection Request is submitted by: Name of Developer: By (signature): Name (type or print): Title: Date: 2 ATTACHMENT A LARGE GENERATING FACILITY DATA UNIT RATINGS kVA _________ °F ___________ Voltage __________ Power Factor __________ Speed (RPM) __________ Connection (e.g. Wye) __________ Short Circuit Ratio __________ Frequency, Hertz __________ Stator Amperes at Rated kVA __________ Field Volts __________ Max Turbine MW __________ °F __________ COMBINED TURBINE-GENERATOR-EXCITER INERTIA DATA Inertia Constant, H = ____________________ kW sec/kVA Moment-of-Inertia, WR2 = ____________________ lb. ft.2 REACTANCE DATA (PER UNIT-RATED KVA) DIRECT AXIS QUADRATURE AXIS Synchronous - saturated Xdv __________ Xqv __________ Synchronous - unsaturated Xdi __________ Xqi __________ Transient - saturated X’dv __________ X’qv __________ Transient - unsaturated X’di __________ X’qi __________ Subtransient - saturated X”dv __________ X”qv __________ Subtransient - unsaturated X”di __________ X”qi __________ Negative Sequence - saturated X2v __________ Negative Sequence - unsaturated X2i __________ Zero Sequence - saturated X0v __________ Zero Sequence - unsaturated X0i __________ Leakage Reactance Xlm __________ A-1 FIELD TIME CONSTANT DATA (SEC) Open Circuit T’do __________ T’qo __________ Three-Phase Short Circuit Transient T’d3 __________ T’q __________ Line to Line Short Circuit Transient T’d2 __________ Line to Neutral Short Circuit Transient T’d1 __________ Short Circuit Subtransient T”d __________ T”q __________ Open Circuit Subtransient T”do __________ T”qo __________ ARMATURE TIME CONSTANT DATA (SEC) Three Phase Short Circuit Ta3 __________ Line to Line Short Circuit Ta2 __________ Line to Neutral Short Circuit Ta1 __________ NOTE: If requested information is not applicable, indicate by marking “N / A.” MW CAPABILITY AND PLANT CONFIGURATION LARGE GENERATING FACILITY DATA ARMATURE WINDING RESISTANCE DATA (PER UNIT) Positive R1 __________ Negative R2 __________ Zero R0 __________ Rotor Short Time Thermal Capacity I22t = __________ Field Current at Rated kVA, Armature Voltage and PF = __________ amps Field Current at Rated kVA and Armature Voltage, 0 PF = __________ amps Three Phase Armature Winding Capacitance = __________ microfarad Field Winding Resistance = ______ ohms _____°C Armature Winding Resistance (Per Phase) = ______ ohms _____°C A-2 CURVES Provide Saturation, Vee, Reactive Capability, Capacity Temperature Correction curves. Designate normal and emergency Hydrogen Pressure operating range for multiple curves. GENERATOR STEP-UP TRANSFORMER DATA RATINGS Capacity Self-cooled/Maximum Nameplate ___________/__________________kVA Voltage Ratio (Generator Side/System Side/Tertiary) ___________/__________/__________kV Winding Connections (Low V/High V/Tertiary V (Delta or Wye)) ___________/_________/_________ Fixed Taps Available Present Tap Setting IMPEDANCE Positive Z1 (on self-cooled kVA rating) ___________ % _________ X/R Zero Z0 (on self-cooled kVA rating) ___________ % _________ X/R EXCITATION SYSTEM DATA Identify appropriate IEEE model block diagram of excitation system and power system stabilizer (PSS) for computer representation in power system stability simulations and the corresponding excitation system and PSS constants for use in the model. GOVERNOR SYSTEM DATA Identify appropriate IEEE model block diagram of governor system for computer representation in power system stability simulations and the corresponding governor system constants for use in the model. A-3 WIND GENERATORS Number of generators to be interconnected pursuant to this Interconnection Request: ______ Elevation: __________ ________ Single Phase _______ Three Phase Inverter manufacturer, model name, number, and version: List of adjustable setpoints for the protective equipment or software: Note: A completed General Electric Company Power Systems Load Flow (PSLF) data sheet or other compatible formats, such as IEEE and PTI power flow models, must be supplied with the Interconnection Request. If other data sheets are more appropriate to the proposed device, then they shall be provided and discussed at Scoping Meeting. INDUCTION GENERATORS: (*) Field Volts: ________________ (*) Field Amperes: ________________ (*) Motoring Power (kW): ________________ (*) Neutral Grounding Resistor (If Applicable): ________________ (*) I22t or K (Heating Time Constant): ________________ (*) Rotor Resistance: ________________ (*) Stator Resistance: ________________ (*) Stator Reactance: ________________ (*) Rotor Reactance: ________________ (*) Magnetizing Reactance: ________________ (*) Short Circuit Reactance: ________________ (*) Exciting Current: ________________ (*) Temperature Rise ________________ (*) Frame Size: ________________ A-4 (*) Design Letter: ________________ (*) Reactive Power Required In Vars (No Load): ________________ (*) Reactive Power Required In Vars (Full Load): ________________ (*) Total Rotating Inertia, H: ___________ Per Unit on KVA Base Note: Please consult the NYISO prior to submitting the Interconnection Request to determine if the information designated by (*) is required. MERCHANT TRANSMISSION FACILITIES: Note: Please consult with the NYISO prior to submitting the Interconnection Request for guidance on the information required for Merchant Transmission Facilities. A-5