WSTA Staffing Models Mechanic Staffing Model The basic formula for the model is listed below: Fleet Mileage for Year ÷ 1,000 x Average hours per 1K ÷ Average Direct Labor Hours (per mechanic) = Number of FTE Mechanics Example: 2,962,850 Miles ÷ 1,000 x 5.4 ÷ 1,440 hrs = 11.11 FTEs In order to use the model you will need three pieces of information: Fleet Mileage for the budget year; your fleet average labor hours (per type of coach) per 1,000 miles; and your average direct labor hours per mechanic. Your Annual Fleet Mileage is provided by your Operations, Budget or Service Development Office by coach type. You will need to apply the formula for each coach type/miles or use and average from the previous year(s). Fleet average hours per 1K miles can be calculated by: Annual Mechanic Labor Hours ÷ Total Annual Fleet Miles x 1,000 Example: 15,997 Mechanic Labor Hours ÷ 2,962,850 Miles x 1,000 = 5.4 hours per 1,000 miles Your Average Direct Labor Hours (per mechanic) is determined by the example on the following page: 1 Technician Availability Average Direct Labor Hours Paid Hours ………………………………..... 2,080 Vacations Holidays Sick Leave Breaks Training & Meetings Awaiting Parts Other (120) (96) (80) (115) (40) (139) (50) Potential Direct Labor Hours ……………… 1,440 Note: Example used is 1,440 Direct Labor Hours. Use the Direct Labor Hour average your organization experiences. 2 Service Technician Staffing Model The basic formula for the model is listed below: Dwell time (minutes) per coach x Number of coaches x Number of time per day x number of days ÷ 60 minutes (1 hour) ÷ Average Direct Labor Hours = FTE Technician Example: Gillig 40’ HF – 19 minutes (dwell) x 100 coaches x 1 time a day x 365 days ÷ 60 ÷ 1,440 hours = 8.03 FTEs In order to use the model you will need four pieces of information: Dwell Time per fleet type; the number of coaches per fleet type; the number of times each day that the service is done; and your average direct labor hours per service worker. Dwell time is the total time it takes to: Fuel; check fluids; sweep; mop; quick clean inside; probe (x times a week); thump tires; outside wash (x times a week); visual inspection; report; and travel time. The number of coaches per fleet type is what you expect to average for the next budget year. The number of times each day that each item in the dwell time is done needs to be averaged, before you multiply times 365 days. For example: many probe only 2 or 3 times a week, while other may do it every day; many only outside wash 2 or 3 times a week and not every day. The process for determining your average direct labor hours per service worker is same as it was for your mechanics. However, the nature of the work may change the averages. 3 Average Direct Labor Hours Paid Hours ………………………………..... 2,080 Vacations Holidays Sick Leave Breaks Training & Meetings Awaiting Parts Other (120) (96) (80) (115) (40) (139) (50) Potential Direct Labor Hours ……………… 1,440 Note: Example used is 1,440 Direct Labor Hours. Use the Direct Labor Hour average your organization experiences. FTEs for Steam Cleaning & Inspections needs to computed separate using total labor hours per year on Work Orders ÷ Direct Labor Hour average for the Service Workers. 4 Inside/Detail Wash Technician Staffing Model The basic formula for the model is listed below: Length of Coach x Number of coaches x Number of cleanings per year ÷ 100’ per day ÷ Number of annual work days = FTEs Example: 40’ x 100 x 6 ÷ 100’ ÷ 182 days = 1.31 FTEs In order to use the model you will need four pieces of information: Coach length (60’ or 40’) (use 40’ for any coach 40’ or <); the number of each type anticipated for the next budget year; how often you are required to conduct a detailed inside cleaning; and the average number of work days your detail wash technicians work. Coach length and number of coaches: Self explanatory Cleaning Cycles every 42/60/75 days = 8.7/6/4.87 x a year. Average number of work days per technician: We used 1,456 direct labor hours ÷ 8 hours = 182 days (your number may vary) 5 Reasons your numbers may be different than the Staffing Models: Fleet Age Facilities Budget WO System Vacancies Work Force Age Parts Availability Backlog Yard Layout PM Program Work Force Experience Tools & Test Equipment Miles between Trouble Call Training Inspections / Frequency Method to compensate for additional staffing: (Inspections; Steaming; Wrecker Operations; Special Projects) Capture all labor hours (Work Orders are the best method) Determine the average annual direct labor hours / day or work for that classification of employees (i.e. 1456 hrs / 182 days) Additional FTEs = Captured Work Order Labor Hours / Days ÷ Average annual direct labor hours (1456) / days (182) Please contact John E. Alley, Assistant VM Manager at King County with any questions you have: john.alley@kingcounty.gov (206) 263-3419 6