Water Purification System

 The Lake water purification system by Aeration & floating fountains (4 Nos) were installed and is functioning since 23.01.2009.

10 more floating fountains have been installed in 2013 for beautification and aeration of Anasagar Lake.

Water Purification S ystem

Bio-Remediatio

n

Bio-remediation of drains terminating into Anasagar lake has been taken up since Feb-2013 for treatment of waste water flowing through drains before entering in to the lake. At present work is under

Progress In 7 drains are as under :

 Nagphani(near Mahaveer colony)

 Ramnagar(near R.K marble)

 Ramnagar

 Kazi ka nallah

 Shantipura

 Apsara Mension

 Choursiawas Drain

Bio-Remediation

CHAURASIAWAS DRAIN

RAM NAGAR II

(NEAR R.K. MARBLE)

KAZI KA NALLAH

SHANTIPURA DRAIN

Jetty Platform & Walkway

The work of Jetty Platform near Chaupati and walkway along the hillock below the circuit house with lighting has been completed.

Jetty Platform near Chaupati &

Walkway

Fixing of Steel Grill-Jali to check entry of

Floating impurities into the Lake is being done

.

Grill at Shantipura Drain Jali at Anasagar Lake

Fixing of Steel Grill-Jali

Grill at Ram Nagar II Drain Grill at Chauarsiawas Drain

Different IEC has been taken up to create public awareness & participation which includes showcase of

Jhanki of Anasagar lake on republic day function.

Distribution of pamphlets and cards for awareness of lake conservation

WATER PURIFICATION

JALI FIXED AT ANASAGAR

Bio-Remediation

JETTY PLATFORM & WALKWAY

WORKS PERFORMED UNDER NLCP- ANASAGAR LAKE

• The sanctioned desilting work of the lake in

2,15,000 cum has been completed, The work of

Desilting in 20000 cum on Anted Nallah,

Chaurasiyawas Nallah, Kazi ka Nallah & Bandi

Nadi has been completed.

• Pucca works for construction work of a pilot channel with cement concrete bed in about 308 m length in Anted Nallah has been completed behind the Press club on the Gaurav Path.

• The fencing and Afforestation in 206 Ha & construction of check dam 31 nos have been completed by the forest Dept.

• Water Quality Monitoring by testing of sample monthly is being done regularly in lake and drains.