Chapter 10 1 1. Apply lag relationships to project activities. 2. Construct and comprehend Gantt charts. 3. Understand the trade-offs required in the decision to crash project activities. 4. Develop activity networks using Activityon-Arrow techniques. 5. Understand the differences in AON and AOA and recognize the advantages and disadvantages of each technique. 2 The logical relationship between the start and finish of one activity and the start and finish of another activity. Four logical relationships between tasks 1. Finish to Start 2. Finish to Finish 3. Start to Start 4. Start to Finish 3 Most common type of sequencing Shown on the line joining the nodes ◦ Added during forward pass ◦ Subtracted during backward pass 0 A 6 Spec Design 6 6 B 11 Design Check 5 15 C 22 Blueprinting Lag 4 days 7 4 Two activities share a similar completion point ◦ The interior construction cannot happen until wiring, plumbing, and HVAC installation are complete 30 R Wiring 6 36 31 S 33 Plumbing 2 Lag 3 days 33 T HVAC 3 39 39 U 45 Interior Const. 6 5 Often two or more activities must start at the same time 30 R Wiring 6 36 Lag 3 31 S 33 Plumbing 2 33 T HVAC 3 36 36 U 42 Inspection 6 6 Least common type of lag relationship Successor’s finish dependent on predecessor’s start 30 R Wiring 6 36 Lag 3 22 S 28 Plumbing 6 28 T HVAC 5 33 33 U 34 Inspection 1 7 A graphical representation of the project schedule that illustrates how work flows over time Shows activity start and end dates and durations Links project activities to a project schedule baseline Can be used as a tracking tool Benefits of Gantt charts 1. Easy to create, read, and comprehend 2. Identify the project network and schedule baseline 3. Allows for updating and control 4. Useful to identify resource needs and assigning resources to tasks 8 Create a Gantt chart Task Time Predecessor based on the Z 8 -activities listed in Y 5 Z the table. X 8 Z W 4 Y,X V 5 W U 3 W T 6 V S 7 U,T R 9 S 9 R Task Z Y X W V U T S R Start 0 8 8 16 20 20 25 31 38 Duration 8 5 8 4 5 3 6 7 9 S T U V W X Y Z 0 10 20 30 40 50 http://office.microsoft.com/en-us/excel/HA102382531033.aspx 10 Critical path in red 11 Accelerating a project by committing more resources. Principal options for crashing Improving existing resources’ productivity Changing work methods used Increasing the quantity of resources 12 The initial schedule may be too optimistic. Market needs change and the project is in demand earlier than anticipated. The project has slipped considerably behind schedule. The contractual situation provides even more incentive to avoid schedule slippage. 13 1. Compute the crash cost per time period. If crash costs are linear over time: (Crash cost – Normal cost) Crash cost per period = (Normal time – Crash time) 2. Using current activity times, find the critical path and identify the critical activities. 14 3. If there is only one critical path, then select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. 4. If there is more than one critical path, then select one activity from each critical path such that (a) each selected activity can still be crashed, and (b) the total crash cost of all selected activities is the smallest. Note: the same activity may be common to more than one critical path. 15 5. Update all activity times. 6. If the desired due date has been reached, stop. If not, return to Step 2. 16 Activity Cost Crash Point $34,000 — Crash Cost/Wk = Crash $33,000 — Cost $30,000 — Normal Cost $34,000 – $30,000 3–1 $4,000 = = $2,000/Wk 2 Wks = $32,000 — $31,000 — Crash Cost – Normal Cost Normal Time – Crash Time How far do you need to speed up the process? Normal Point — | 1 Crash Time | 2 | 3 Normal Time Time (Weeks) 17 Formula Slope = crash cost – normal cost normal time – crash time Example – calculating the cost of crashing Suppose: Normal activity duration = 8 weeks Normal cost = $14,000 Crashed activity duration = 5 weeks Crashed cost = $23,000 The activity cost slope = 23,000 – 14,000 8–5 or, $9,000 3 = $3,000 per week 18 Determine activity fixed and variable costs The crash point is the fully expedited activity Optimize time-cost tradeoffs Shorten activities on the critical path Cease crashing when ◦ the target completion time is reached ◦ the crash cost exceeds the penalty cost 19 Activity Pred Normal Time Min Time Normal Cost Crash Cost A -- 14 9 500 1500 B A 5 2 1000 1600 C A 10 8 2000 2900 D B, C 8 5 1000 2500 E D 6 5 1600 1900 F D 9 6 1500 3000 G E, F 7 4 600 1800 H G 15 11 1600 3600 20 What is the lowest cost to complete this project in 53 weeks? Times are in weeks and costs in dollars. 21 Activities represented by arrows Event nodes easy to flag Forward and backward pass logic similar to AON Two activities may not begin and end at common nodes Dummy activities may be Event required label Task Description Earliest Event Time (ES) Latest Event Time (LF) Duration 22 Figure 10.18 3 B 1 A 2 C 4 23 E B H A F C D K G 24 Activity on Node (AON) (a) A Activity Meaning C B A comes before B, which comes before C A (b) C B A and B must both be completed before C can start Activity on Arrow (AOA) A B C A B C B (c) A C B and C cannot begin until A is completed B A C 25 Activity on Node (AON) A C B D (d) A C (e) B D Activity Meaning C and D cannot begin until both A and B are completed C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA Activity on Arrow (AOA) A C B D A C Dummy activity B D 26 Activity on Node (AON) A B (f) C D Activity Meaning B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA. Activity on Arrow (AOA) A Dummy activity B D C 27 1. Please give examples of circumstances in which a project would employ lag relationships between activities using: 1. 2. 3. 4. Finish to start Finish to finish Start to start Start to finish 2. The advantage of Gantt Charts lies in their linkage to the project schedule baseline. Explain this concept. 3. What are the advantages in the use of Gantt charts over PERT diagrams? In what ways might PERT diagrams be advantageous? 4. Under what circumstances might you wish to crash a project? 28 5. In crashing a project, we routinely focus on those activities that lie on the critical path, not activities with slack time. Explain why this is the case. 6. What are some of the advantages in the use of AOA notation as opposed to AON? Under what circumstances does it seem better to apply AON methodology in network development? Explain the concept of a “dummy variable.” Why are they employed in AOA notation? Why is there no need to use dummy variables in an AON network? 7. Explain the concept of a “dummy variable.” Why are they employed in AOA notation? Why is there no need to use dummy variables in an AON network? 29