Main technical characteristics

advertisement
PARTNERS MAINT COMPANY LTD
DISMANTLING OF BRENNILIS NPP – FRANCE
SPECIFIC EQUIPMENT
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
PARTNERS MAINT COMPANY LTD






DISMANTLING OF BRENNILIS NPP – FRANCE
SPECIFIC EQUIPMENT
BRENNILIS REACTOR
DECOMMISSIONING
SCOPE OF WORK
MAIN REQUIREMENTS
MAIN DESIGN PROBLEMS
DESIGN SOLUTIONS
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
2
PARTNERS MAINT COMPANY LTD

Brennilis reactor is an
experimental reactor
moderated with heavy water
and cooled with carbon dioxide
(HWGCR). The reactor was to
have a power of 70 MW.

The startup occurred in 1967.

In 1985 the reactor was
decommissioned.
BRENNILIS REACTOR
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
3
PARTNERS MAINT COMPANY LTD
DECOMMISSIONING
Brennilis marks the first dismantling of a complete nuclear power station in France.
EDF and CEA announced intention to make a transparent process so that it can be
used as a model for dismantling of other plants later.
The process is divided into 3 phases:
Phase 1
This phase was launched in 1985, similar to a refueling outage the fuel is moved to
the spent fuel pool, but new fuel is not loaded, and the fuel on site is evacuated.
Phase 2
Phase 2 started in 1997, consisting of:
•
decontamination and disassembling of the buildings except for the reactor
itself.
•
evacuation of the nuclear waste.
In 2005 phase 2 officially finished.
Phase 3
Phase 3 which is currently underway, consist of:
•
dismantling of the heat exchangers.
•
dismantling of the Reactor pressure vessel (RPV) – ONET TECHNOLOGIES
leader of consortium ONET TECHNOLOGIES/NUKEM TECHNOLOGIES.
•
demolition of the containment (Reactor building).
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
4
SCOPE OF WORK
PARTNERS MAINT COMPANY LTD
The equipment is designed for operation in a chamber for
treatment of radioactive waste (CDI) and will be installed in place
in the Brennilis nuclear power plant in France. The equipment will
perform specific operations and is designed to comply with the
requirements of individual technical specifications prepared by
consortium
GМЕ
TECHNOLOGIES).
(ONET
TECHNOLOGIES/NUKEM
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
5
PARTNERS MAINT COMPANY LTD
SCOPE OF WORK
The scope of work assigned to PMC by ONET TECHNOLOGIES
is the executive studies, manufacturing, factory acceptance
tests and delivery on site for following equipment:
• Elevator;
• “Renard” trolley;
• 5m3 trolley;
• Characterization trolley;
• Hoisting devices and rack;
• Sorting table.
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
6
PARTNERS MAINT COMPANY LTD
MAIN REQUIREMENTS
The main designing requirements are the following:
• Several types of packages (weight and dimensions);
• Interface with civil construction;
• Low speed for all movements;
• Operations in remote control;
• Maintenance of equipment;
• Life time of equipments;
• Operation in radioactive environment;
• High accuracy of positioning;
• Equipment to be designed in accordance with
Machinery directive 2006/42 and FEM.1.001.
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
7
PARTNERS MAINT COMPANY LTD
•
•
MAIN DESIGN PROBLEMS
Lack of sufficient input data for the civil construction –
considering the specific conditions due to the place of
operation and considering the specific technological
processes due to the functions of the whole system for
treatment of radioactive waste it is necessary to modify
and change the use of some areas of the reactor
building.
Difficulties with limited space – the tight equipment
overall dimensions are predetermined by the limited
space assumed for operation execution and
incorporation of the systems in the design.
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
8
PARTNERS MAINT COMPANY LTD
•
MAIN DESIGN PROBLEMS
High dose rate – operation in environment with high
ionizing radiation, protection of the equipment,
endurance to frequent decontamination treatment,
structure designed form units which are convenient for
maintenance.
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
9
PARTNERS MAINT COMPANY LTD
DESIGN SOLUTIONS
DEVELOPMENT OF THE DESIGN CONCEPTS IN COMPARISON TO THE
ONET TECHNOLOGIES TECHNICAL SPECIFICATIONS
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
ELEVATOR
PARTNERS MAINT COMPANY LTD
ONET TECHNOLOGIES DESIGN
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
11
ELEVATOR
PARTNERS MAINT COMPANY LTD
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
Elevator is designed to carry three types of
containers between four levels in the rector
building.
Main technical characteristics
Load carrying capacity
10 t
Speed of movement
2 m/min
Overall dimensions
2190 x 1600 x 16450 mm
Platform dimensions
1450 x 1450 mm
Platform height from
the floor
860 mm
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
12
PARTNERS MAINT COMPANY LTD
ONET TECHNOLOGIES DESIGN
“RENARD” TROLLEY
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
13
PARTNERS MAINT COMPANY LTD
“RENARD” TROLLEY
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
14
PARTNERS MAINT COMPANY LTD
“RENARD” TROLLEY
“Renard” trolley performs transportation of three types of containers. The
loading/unloading operations are performed by the trolley itself and are controlled
from control room.
Main technical characteristics
Basic trolley “Renard”
Load carrying capacity
10 t
Nominal lifting capacity
5,5 t
Lifting height
2250 mm
Lifting speed
1 m/min
Maximum traveling speed
4,47 m/min
Rail span
1,2 m
Trolley traveling distance
28,7 m
Overall dimensions 3091 х 1430 х 2188 mm
Small trolley “Renard”
Load carrying capacity
10 t
Lifting height
150 mm
Lifting speed
0,13 m/min
Traveling speed
3,76 m/min
Trolley traveling distance 8 m
Overall dimensions 1300 х 1340 х 365,5 mm
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
15
PARTNERS MAINT COMPANY LTD
ONET TECHNOLOGIES DESIGN
5M3 TROLLEY
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
16
PARTNERS MAINT COMPANY LTD
5M3 TROLLEY
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
The 5m3 trolley is designed for operation
with two types of containers: container 5m3
and container R73.
Main technical characteristics
Load carrying capacity
23 t
Lifting height
103 mm
Lifting speed
0,12 m/min
Traveling speed
5 m/min
Rail span
1,4 m
Trolley traveling distance 22 m
Overall dimensions 2555 x 1800 x 1291 mm
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
17
PARTNERS MAINT COMPANY LTD
ONET TECHNOLOGIES DESIGN
CHARACTERIZATION TROLLEY
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
18
PARTNERS MAINT COMPANY LTD
CHARACTERIZATION TROLLEY
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
The Characterization trolley is designed for
operation with seven types of containers.
Main technical characteristics
Load carrying capacity
3t
Platform rotation speed
5 rpm
Traveling speed
5 m/min
Rail span
1,5 m
Trolley traveling distance
4,7 m
Overall dimensions 2151 x 1694 x 1524,5 mm
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
19
PARTNERS MAINT COMPANY LTD
ONET TECHNOLOGIES DESIGN
HOISTING DEVICES
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
Five hoisting devices are designed. Each hoisting device is
designed for operation with a specific type of basket. The
weight of the heaviest basket is 3 t.
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
20
PARTNERS MAINT COMPANY LTD
ONET TECHNOLOGIES DESIGN
RACK FOR HOISTING DEVICES
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
The rack is designed for storage of these 5 hoisting devices and protection lid for
auxiliary coupling mechanism intended for their attaching to the crane.
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
21
PARTNERS MAINT COMPANY LTD
ONET TECHNOLOGIES DESIGN
SORTING TABLE
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
22
PARTNERS MAINT COMPANY LTD
SORTING TABLE
PMC DESIGN IN COLLABORATION
WITH ONET TECHNOLOGIES
The Sorting table is designed for
containing the waste unloaded from the
baskets OT and NUKEM.
Main technical characteristics
Load carrying capacity
1,6 t
Dynamic loading of the grid
1t
Overall dimensions
1200 x 2270 x 600 mm
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
23
PARTNERS MAINT COMPANY LTD



EQUIPMENT CONTROL
The main control mode of the whole equipment during the
process of nuclear reactor dismantling is intended to be from
control room via Ethernet communication.
The reliable and synchronized operation of the devices is
realized by utilization of contemporary technologies and
concepts.
The equipment is also able to operate in maintenance mode
and emergency mode during which the control is accomplished
by local control panels.
International Nuclear Forum "BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY SAFETY “, Varna, 2-4 June 2011
24
PARTNERS MAINT COMPANY LTD
THANK YOU FOR YOUR ATTENTION !