CMP### Title

advertisement
Update on Review of Embedded Generation Benefits
Place your chosen
image here. The four
corners must just
cover the arrow tips.
For covers, the three
pictures should be the
same size and in a
straight line.
Andy Wainwright
Background
 Standard Licence Condition C13
 Introduced at BETTA (2005)
 Addressed different treatment of 132kV connected small
generation in Scotland (transmission) with that in England and
Wales (embedded)
 Time limited: due to expire 1st April 2016
 Embedded review needs to consider overall implications on GB
generation
 Informal industry focus group established Spring 2013
2
Objectives of transmission charges
Cost reflectivity
Facilitate competition
Developments in transmission businesses
Recover transmission costs
Non-discrimination
Affected transmission ‘charges’
TNUoS
BSUoS
Losses
Focus Group agreement to consider TNUoS first
3
TNUoS Charges - Locational Element
 Net approach
TNUoS Locational Elements only
30
 Embedded generation nets
with demand
25
Gen
 Therefore subject to a
negative demand locational
signal
Dmd
 Based on output at Triad
20
Tariffs
15
10
5
 Equivalent to generation
signal: zoning limitations
0
-5
A
B
C
Charging Zones
-10
D
E
 Gross approach
 Embedded generation
receives same generation
signal as transmission
connected
 All demand receives
locational signal
4
The effect of the generation residual element
30
Avoidance of
generation
residual charge
25
20
15
Gen
10
Dmd
5
0
-5
A
B
C
D
E
-10
 Embedded generator avoids paying generation residual element
5
The effect of the demand residual element
30
25
20
15
Gen
10
Dmd
5
Netting of
positive
demand
0
-5
A
B
C
D
E
-10

Positive demand can avoid paying the demand residual element if able to net with
embedded generation

Embedded generation therefore has a value equal to the demand residual element
6
Combination of both residual elements
 In summary, embedded generation can receive TNUoS ‘benefit’
through two effects on residual elements;
 netting of positive demand (i.e. reducing demand charge)
 avoidance of generation residual charge
Avoidance of
generation
residual charge
30
25
20
15
Gen
10
Netting of
positive
demand
Dmd
5
0
-5
A
B
C
D
E
2 x Residual
uplift
-10
7
How much benefit should be paid for offsetting +ve demand?
Annuitised demand related infrastructure costs
NGET GSP infrastructure
reinforcement costs
4
3.5
3
£/kW
2.5
2
Average
1.5
1
0.5
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Project
Year
Cost
Residual
2012/13
£1.41/kW
£27.07/kW
2009/10
£1.30/kW
£20.74/kW
(equates to £1.47/kW
in 2012/13)1
(equates to £23.53/kW
in 2012/13) 1
1 RPI
factor for 2009/10 to 2012/13 = 1.132992
8
Should embedded generation pay for transmission?
Average TNUoS charge: £7.57/kW (2013/14)
Comparing transmission and
distribution charges
Note 2013/14 average TNUoS
charge: £7.75/kW
How does embedded generation use transmission?
Transmission Function (Use)
Transmission
connected G
Embedded G
 inject
 Net
Access to Market (s) GB & wider EU


Security / Quality of Supply


Net transfers
9
Other areas under consideration
Exporting GSPs
Impact on >100MW generators
Offshore Transmission Implications
10
Next steps
 National Grid report to be published October
 Include Focus group & bi-lateral discussions
 Three week open letter
 Formal CUSC modification proposal potentially later in
Autumn
11
Download