LINE OF BALANCE (LOB) Miguel CABEZUDO Nicolas LAFLESSELLE DEFINITION A line of balance diagram comprises a series of inclined lines which represent the rate of working between repetitive operations in a construction sequence. It's the best planning method for a repetitive work such as a housing. It's a visual display of the rate of working of different activities on a program. PRINCIPLES A B LOGIC DIAGRAM C LOB DIAGRAM WITH A NON-PARALLEL WORKING Buffer A B C Overall duration Number of units Activity B slower than A Activity C slower than B Duration Minimum Buffers LOB DIAGRAM WITH A PARALLEL WORKING / IDEAL RELATIONSHIP A B C Overall duration Number of units Same rate of construction Duration Minimum Buffer PRINCIPLES B A D C LOGIC DIAGRAM FOR SEQUENCE LOB DIAGRAM OPERATION B AND C BEGINNING TOGETHER A B C D Overall duration Number of units Duration LOB DIAGRAM OPERATIONS B AND C ENDING TOGETHER A B.C D Overall duration Number of units Duration EXAMPLE – Access Deck Project Operation 1 : Install piles – 2 days (gang of 3 labours) Operation 2 : In situ beams– 4 days (gang of 4 carpenters) Operation 3 : Precast concrete deck – 1 day (gang of 2 labours) EXAMPLE – Access Deck Project Install piles 1 2 days In situ beams 2 4 days Precast deck 3 LOGIC DIAGRAM 1 day 4 EXAMPLE – Access Deck Project Buffer 6 Piling 10 12 In situ beams 23 27 28 29 Precast deck 5 Completion day 29 4 Bay number 3 2 1 0 2 4 Buffer 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 Duration (days) EXAMPLE – Access Deck Project LABOUR RESOURCES 7 6 Pile caps/beams 5 Deck Labour 4 3 2 Pile caps/beams Piling Deck 1 0 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 Duration (days) EXAMPLE – Access Deck Project 6 Piling 5 4 In situ Buffer beams 10 12 13 17 18 19 Precast deck Completion day 19 Bay number 3 2 1 0 2 4 Buffer 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 Duration (days) EXAMPLE – Access Deck Project REVISED LABOUR RESOURCES 12 11 10 9 Labour 8 7 6 5 4 3 2 1 0 Caps and beams Gang 2 Deck Caps and beams Gang 1 Piling 0 2 4 6 Deck 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 Duration (days) EXAMPLE CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) Operation Duration per unit in weeks Number of gangs Foundations 2 2 External walls 4 3 Roof construction 1 1 Internal finishes 4 3 External works 2 2 NUMBER OF UNITS : 10 CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) Foundations 1 2 External walls Internal walls Roof 3 4 SEQUENCE LOGIC FOR OPERATIONS External works 5 6 CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) Number of unit less 1 x duration of operation Number of gangs used Foundations : Start unit 1 : week 0 Finish unit 1 : week 2 (2 weeks duration) Start of unit 10 = 0 + (10 units – 1) x 2 = 18/2 = week 9 2 gangs Finish of unit 10 = week 9 + 2 weeks = week 11 CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) Foundations 9 11 10 Number of houses units 1 0 2 4 6 8 10 12 14 16 18 20 Duration (weeks) CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) External walls : Duration per unit : 4 weeks Number of gangs : 3 We need to consider the rate of construction between the 2 operations : Slope of the fondation balance line = duration =1 Number of gangs Slope of the external walls balance line = 1.33 CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) External walls : Duration per unit : 4 weeks Number of gangs : 3 Start unit 1 : week 2 + 1 week buffer = week 3 Finish unit 1 : week 3 + 4 weeks duration = week 7 Start of unit 10 = week 3 + (10 units – 1) x 4 = 3 + 36/3 = week 15 3 gangs Finish of unit 10 = week 15 + 4 weeks = week 19 CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) External Foundations walls 9 11 15 19 10 Number of houses units 1 0 3 7 10 12 14 16 18 20 Duration (weeks) CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) Roof Construction : Duration per unit : 1 week Number of gangs : 1 Slope of the external walls balance line = 1.33 Slope of the Roof Construction balance line = 1 The relationship will begin at the finish of the external walls balance line. CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) Roof Construction : Duration per unit : 1 week Number of gangs : 1 Start unit 10 : week 19 + 1 week buffer = week 20 Finish unit 10 : week 20 + 1 week duration = week 21 Start of unit 1 = week 20 - (10 units – 1) x 1 = 20 - 9 = week 11 1 gang Finish of unit 1 = week 11 + 1 week duration = week 12 CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) External Foundations walls Roof 9 11 15 19 20 21 10 Number of houses units 1 0 3 7 11 12 14 16 18 20 22 24 26 28 30 32 34 36 Duration (weeks) CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) Internal walls : Duration per unit : 4 weeks Number of gangs : 3 External works : Duration per unit : 2 weeks Number of gangs : 2 CONSTRUCTION OF 10 HOUSES (5 CONSTRUCTION OPERATIONS) External Foundations walls Roof 9 11 15 19 20 21 10 Internal Internal walls works 25 29 30 31 Number of houses units 1 0 3 7 11 12 13 17 21 23 26 28 30 32 34 36 Duration (weeks) REFERENCES Cooke, Brian, & Williams, Peter. Construction, planning, programming & control. Blackwell Publishing