TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope TKR Hand-off review for Tower 4 and 5 Hiro Tajima SU-SLAC R. P. Johnson UCSC Hiro Tajima, TKR Tower 4 and 5 hand-ff review 1 TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project Power Consumption • Tower 5 is tested with I&T TEM/TPS which has somewhat higher PS voltages. • Values for MCM measurements account for the increase due to PS voltage itself, not current increase due to voltage increase. Tower 4 Pisa SLAC MCM Tower total 10.17 W 9.86 W 9.26 W Tower + TEM/TPS 18.8 W 19.3 W N/A Pisa SLAC MCM Tower total 9.65 W 10.15 W 9.29 W Tower + TEM/TPS 19.0 W 19.9 W N/A Tower 5 Hiro Tajima, TKR Tower 4 and 5 hand-ff review 2 TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project Bad channels (Tower 4) Laye r Y17 X17 X16 Y16 Y15 X15 X14 Y14 Y13 X13 X12 Y12 Y11 X11 X10 Y10 Y9 X9 X8 Y8 Y7 X7 X6 Y6 Y5 X5 X4 Y4 Y3 X3 X2 Y2 Y1 X1 X0 Y0 Total Fraction Pre ship (Pisa) Handoff (SLAC) disconnect disconnect dead noisy 0 6 0 1 0 2 0 0 0 1 1 0 0 0 0 0 2 0 0 0 0 0 20 0 45 0 1 0 50 0 0 0 1 0 1 1 132 0.24% 0 6 0 1 0 2 0 0 0 1 1 0 0 0 0 0 2 0 0 0 0 0 20 0 46 0 1 0 55 0 0 0 1 0 1 1 138 0.25% 0 4 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 2 1 0 0 0 5 1 1 2 0 0 1 1 0 0 0 0 2 22 0.04% 0 2 0 0 0 0 0 0 0 1 0 1 0 0 0 0 1 0 2 0 0 0 2 1 1 0 2 0 5 0 10 0 0 0 0 0 28 0.05% Hiro Tajima, TKR Tower 4 and 5 hand-ff review others (offline) 0 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 0 0 1 4 0 0 1 1 1 0 0 0 1 13 0.02% total 0 13 0 3 0 2 0 0 0 2 1 2 0 0 0 0 3 0 4 1 0 0 24 6 48 2 9 0 60 2 12 1 1 0 1 4 201 0.36% 3 TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project Band Channels (Tower 5) Laye r Y17 X17 X16 Y16 Y15 X15 X14 Y14 Y13 X13 X12 Y12 Y11 X11 X10 Y10 Y9 X9 X8 Y8 Y7 X7 X6 Y6 Y5 X5 X4 Y4 Y3 X3 X2 Y2 Y1 X1 X0 Y0 Total Fraction Pre ship (Pisa) Layer Handoff (SLAC) disconnect disconnect dead noisy 0 2 3 0 0 4 0 0 5 0 0 0 0 0 0 0 0 1 0 0 1 0 0 0 4 0 10 0 0 0 8 0 0 0 0 7 45 0.08% 0 2 3 0 0 4 0 0 5 0 0 0 0 0 0 0 0 1 0 0 1 0 0 0 4 0 10 0 0 0 8 0 0 0 0 7 45 0.08% 0 0 0 0 0 1 0 0 0 0 0 1 0 0 1 0 0 0 1 0 0 0 3 0 0 0 0 0 0 0 0 0 0 2 1 2 0 0 0 0 6 0 0 2 4 1 3 7 0 2 0 0 0 31 0.06% 2 1 0 0 0 0 0 0 0 2 0 0 0 0 0 1 0 0 0 12 0.02% Hiro Tajima, TKR Tower 4 and 5 hand-ff review others (offline) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 2 0 0 0 1 0 0 0 0 2 6 0.01% total 0 3 3 0 0 8 0 0 5 0 0 1 0 0 1 0 2 4 3 0 1 0 0 6 5 0 16 4 1 3 16 0 3 0 0 9 94 0.17% Y17 X17 X16 Y16 Y15 X15 X14 Y14 Y13 X13 X12 Y12 Y11 X11 X10 Y10 Y9 X9 X8 Y8 Y7 X7 X6 Y6 Y5 X5 X4 Y4 Y3 X3 X2 Y2 Y1 X1 X0 Y0 4 TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project Hit Efficiency Tower 4 Y0 X0 X1 Y1 Y2 X2 X3 Y3 Y4 X4 X5 Y5 Y6 X6 X7 Y7 Y8 X8 X9 Y9 Y10 X10 X11 Y11 Y12 X12 X13 Y13 Y14 X14 X15 Y15 Y16 X16 X17 Y17 average pre-ship 99.4 99.5 99.8 99.8 99.8 99.7 99.6 98.3 99.7 99.4 99.6 98.6 99.6 98.4 99.9 99.8 99.9 99.8 99.9 99.9 99.9 99.8 99.9 99.8 99.7 99.8 99.8 99.9 99.8 99.8 99.9 99.9 99.9 99.9 99.1 99.5 99.63 error 0.07 0.07 0.04 0.04 0.04 0.05 0.06 0.11 0.05 0.07 0.06 0.11 0.06 0.11 0.03 0.04 0.03 0.04 0.03 0.03 0.03 0.04 0.03 0.04 0.05 0.04 0.04 0.03 0.04 0.04 0.03 0.03 0.03 0.03 0.08 0.06 0.01 hand-off 99.4 99.5 99.8 99.9 99.8 99.7 99.5 98.1 99.7 99.5 99.7 98.6 99.5 98.2 99.8 99.8 99.9 99.8 99.9 99.8 99.9 99.8 99.9 99.8 99.7 99.8 99.8 99.9 99.8 99.8 99.9 99.9 99.9 99.9 99 99.5 99.62 error 0.06 0.05 0.03 0.02 0.03 0.04 0.05 0.10 0.04 0.05 0.04 0.09 0.05 0.10 0.03 0.03 0.02 0.03 0.02 0.03 0.02 0.03 0.02 0.03 0.04 0.03 0.03 0.02 0.03 0.03 0.02 0.02 0.02 0.02 0.07 0.05 0.01 delta/error 0 0 0 1 0 0 -1 -1.3 0 1 1 0 -1 -1.3 -1 0 0 0 0 -1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -0.9 0 -1.3 Hiro Tajima, TKR Tower 4 and 5 hand-ff review Tower 5 Y0 X0 X1 Y1 Y2 X2 X3 Y3 Y4 X4 X5 Y5 Y6 X6 X7 Y7 Y8 X8 X9 Y9 Y10 X10 X11 Y11 Y12 X12 X13 Y13 Y14 X14 X15 Y15 Y16 X16 X17 Y17 average pre-ship 99.4 99.6 99.9 99.8 99.8 99.6 99.5 99.5 99.6 99.5 99.8 99.6 99.7 99.8 99.8 99.7 99.9 99.7 99.7 99.9 99.9 99.9 99.9 99.9 99.9 99.9 99.9 99.6 99.8 99.8 99.7 99.9 99.9 99.9 99.5 99.5 99.74 error 0.07 0.06 0.03 0.04 0.04 0.05 0.06 0.06 0.06 0.06 0.04 0.06 0.05 0.04 0.04 0.05 0.03 0.05 0.05 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.05 0.04 0.04 0.05 0.03 0.03 0.03 0.06 0.06 0.01 hand-off 99.4 99.5 99.8 99.7 99.8 99.6 99.4 99.3 99.5 99.4 99.8 99.6 99.6 99.7 99.8 99.8 99.8 99.6 99.8 99.8 99.8 99.8 99.8 99.8 99.8 99.8 99.7 99.6 99.8 99.8 99.7 99.9 99.9 99.8 99.5 99.4 99.68 error 0.06 0.05 0.03 0.04 0.03 0.04 0.06 0.06 0.05 0.06 0.03 0.05 0.05 0.04 0.03 0.03 0.03 0.05 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.04 0.04 0.03 0.03 0.04 0.02 0.02 0.03 0.05 0.06 0.01 delta/error 0 -1 -1 -1 0 0 -1 -2.0 -1 -1 0 0 -1 -1.0 0 1 -1 -1 1 -1 -1 -1 -1 -1 -1 -1 -2 0 0 0 0 0 0 -1 0.0 -1 -5.4 5 TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project Trigger Efficiency Tower 4 trigger combination C0-1-2 C1-2-3 C2-3-4 C3-4-5 C4-5-6 C5-6-7 C6-7-8 C7-8-9 C8-9-10 C9-10-11 C10-11-12 C11-12-13 C12-13-14 C13-14-15 C14-15-16 C15-16-17 Pre ship 98.0 97.1 96.5 95.3 95.4 95.9 97.3 99.1 99.1 99.2 98.9 98.8 98.7 99.0 99.2 98.2 Hiro Tajima, TKR Tower 4 and 5 hand-ff review handoff 98.1 96.8 96.3 95.1 95.3 95.7 96.9 98.9 99.0 99.0 98.8 98.8 98.7 99.0 99.2 98.1 Tower 5 Pre ship 98.0 97.9 97.3 97.2 97.7 98.1 98.4 98.5 98.9 99.0 99.2 98.9 98.8 98.6 99.0 98.4 handoff 97.8 97.6 97.0 96.8 97.3 98.1 98.1 98.5 98.5 98.7 98.6 98.3 98.4 98.5 98.9 98.2 6 TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project NCR 516 for Tower 4 • Tower 4 failed to read out data from GTFEs in clock/DVDD margin tests. – All layers failed @ duty cycle 58% – Layer Y4 low side failed @ duty cycle = 54 and 55%. – Layer Y4 low side failed @ f = 22 MHz. – Layer Y4 low side and Y1 high side @ DVDD = 2.46 V (setting was 2.5 V) • Margin tests performed for all MCMs during burn-in and final test process. (No margin test in Italy.) • Only possible fix: send tower back to Italy and replace Y4. • Recommendation: Use it as is. – It works perfectly at nominal duty cycle with 3% margin. – It can readout all GTFE from high side on Y4 at 55% duty cycle. Hiro Tajima, TKR Tower 4 and 5 hand-ff review 7 TKR Tower 4 and 5 hand-off review – June 8,2005 GLAST LAT Project Other Anomalies • TE701 (Trigger Jitter test) failure on both towers. – This is an issue of requirement interpretation. – Working with trigger group to define clear requirement. • Fit non-convergence for noise and gain test. – Known issue from Italy. – 65 channels on Layer Y13, Tower 4 are affected. – These channels are confirmed to be functioning. • Tower 5 failed clock duty cycle margin test @ 58%. – It passed at 55% (within specification) • Tower 5 passed noise and gain test. – Past 6 towers all failed this test. Hiro Tajima, TKR Tower 4 and 5 hand-ff review 8