DG Inyorkern Weekly Project Summary 1/17/14 DG Inyokern 1/17/14: Percentage Overview Progress this week Stripped forms and graded around slab Finished hauling out extra dirt Started building installed all heavy steel Completed bolt inspection Dug out for Water , sewer and phone to street Saw cut street for laterals ready to enter Monday Block delivered ready to start Monday Install pipe for sewer ,water and phone Insulate walls and skin exterior walls Block up front wall and build dumpster Start curb and gutter Inspections on street work and phone Backfill ditches • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • Demolition: Pad Prep: 100% Finished and ceriified Footing & Foundation: 100% finished Underground Plumbing: 100% finished under slab Underground Electric: 100% finished underslab Underground Inspections: Back fill: 100% Slab Prep: 100% Pour Slab: 100% Framing:30% Storefront Install: Install Hoods: Install Welded Duct: Plumbing Rough: Install Trench Drains: Electrical Rough: Fire Sprinkler Rough:NA HVAC Rough: Refrigeration Rough: Alarm Rough: Fire & Burg Alarm Rough: Drywall: Spackle & Tape: FRP: Install Walk-ins: Quarry Tile Install: Python Pull Coke/Beer: Acoustical Ceiling: Equipment Install: Light Fixture Install: Front of house Flooring & Wall Tile: Running Trim: Wall Covering: Millwork Install: Paint & Stain: Décor Install: Finish Plumbing: Finish Electric: Finish HVAC: Finish Alarms: Finish Refrigeration: Bathroom partition Install: Furniture Install: Sign Install: Awning Install: Patio Furniture Install: Landscape: Final Inspections: DG Inyokern 1/17/14: Weekly Project Summary DG Inyorkern 1/17/14 : WEEKLY PROJECT SUMMARY PERMIT(S) STATUS: PROJECT START DATE: 12/13/13 ___________________________ PROJECT PUNCH DATE: 3/15/14 IS THE PUNCH DATE OK? Yes IF PUNCH DATE IS NOT ACHIEVABLE, WHAT DATE CAN PUNCH BE DONE? N/A ___________________________ BID COST VS. SITE CONDITIONS: *None known at this time ___________________________ UNRESOLVED ARCHITECTURAL ISSUES THAT ARE CAUSING DELAYS: [INCLUDING MEP ISSUES] *None known at this time UNRESOLVED LANDLORD ISSUES OR DELAYS: IS THERE ANYTHING THAT COULD POTENTIALLY DELAY THE COMPLETION? We did have a problem with the delivery of building insulation . The Insulation company lost the order and missed delivery date. This has to be cut to fit the building so there will be a delay getting it. I should be able to work on areas of building to keep moving the wall insulation will be here Wend and the roof Friday. We will have to put roof on last instead of next POSSIBLE INCOMPLETE ITEMS AT SUBSTANTIAL COMPLETION: *N/A DG Inyokern 1/17/14: WEEKLY PROJECT SUMMARY POSSIBLE INCOMPLETE ITEMS AT CLIENT TURNOVER: *None known at this time PENDING UNRESOLVED ISSUES WITH CLIENT: *None known at this time AWAITING THE APPROVAL ON THE FOLLOWING CHANGE ORDERS: POTENTIAL CHANGE ORDERS: *None known at this time THIS WEEKS MILESTONES ACHIEVED: Start constuction of steel building Start underground utilities NEXT WEEKS PLANNED MILESTONES TO ACHIEVE: 80% completion of steel building Finish 75% underground utilities Start cub and gutter