Weekly Update Inyokern 1-17-14

advertisement
DG Inyorkern
Weekly Project Summary
1/17/14
DG Inyokern 1/17/14: Percentage Overview
Progress this week
Stripped forms and graded around slab
Finished hauling out extra dirt
Started building installed all heavy steel
Completed bolt inspection
Dug out for Water , sewer and phone to street
Saw cut street for laterals ready to enter Monday
Block delivered ready to start Monday
Install pipe for sewer ,water and phone
Insulate walls and skin exterior walls
Block up front wall and build dumpster
Start curb and gutter
Inspections on street work and phone
Backfill ditches
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Demolition:
Pad Prep: 100% Finished and ceriified
Footing & Foundation: 100% finished
Underground Plumbing: 100% finished under slab
Underground Electric: 100% finished underslab
Underground Inspections:
Back fill: 100%
Slab Prep: 100%
Pour Slab: 100%
Framing:30%
Storefront Install:
Install Hoods:
Install Welded Duct:
Plumbing Rough:
Install Trench Drains:
Electrical Rough:
Fire Sprinkler Rough:NA
HVAC Rough:
Refrigeration Rough:
Alarm Rough:
Fire & Burg Alarm Rough:
Drywall:
Spackle & Tape:
FRP:
Install Walk-ins:
Quarry Tile Install:
Python Pull Coke/Beer:
Acoustical Ceiling:
Equipment Install:
Light Fixture Install:
Front of house Flooring & Wall Tile:
Running Trim:
Wall Covering:
Millwork Install:
Paint & Stain:
Décor Install:
Finish Plumbing:
Finish Electric:
Finish HVAC:
Finish Alarms:
Finish Refrigeration:
Bathroom partition Install:
Furniture Install:
Sign Install:
Awning Install:
Patio Furniture Install:
Landscape:
Final Inspections:
DG Inyokern 1/17/14: Weekly Project
Summary
DG Inyorkern 1/17/14 : WEEKLY PROJECT SUMMARY
PERMIT(S) STATUS:
PROJECT START DATE: 12/13/13
___________________________
PROJECT PUNCH DATE: 3/15/14
IS THE PUNCH DATE OK? Yes
IF PUNCH DATE IS NOT ACHIEVABLE, WHAT DATE CAN PUNCH BE DONE? N/A
___________________________
BID COST VS. SITE CONDITIONS:
*None known at this time
___________________________
UNRESOLVED ARCHITECTURAL ISSUES THAT ARE CAUSING DELAYS: [INCLUDING MEP ISSUES]
*None known at this time
UNRESOLVED LANDLORD ISSUES OR DELAYS:
IS THERE ANYTHING THAT COULD POTENTIALLY DELAY THE COMPLETION?
We did have a problem with the delivery of building insulation . The Insulation company lost the order and missed delivery date.
This has to be cut to fit the building so there will be a delay getting it. I should be able to work on areas of building to keep moving the wall
insulation will be here Wend and the roof Friday. We will have to put roof on last instead of next
POSSIBLE INCOMPLETE ITEMS AT SUBSTANTIAL COMPLETION:
*N/A
DG Inyokern 1/17/14: WEEKLY PROJECT SUMMARY
POSSIBLE INCOMPLETE ITEMS AT CLIENT TURNOVER:
*None known at this time
PENDING UNRESOLVED ISSUES WITH CLIENT:
*None known at this time
AWAITING THE APPROVAL ON THE FOLLOWING CHANGE ORDERS:
POTENTIAL CHANGE ORDERS:
*None known at this time
THIS WEEKS MILESTONES ACHIEVED:
Start constuction of steel building
Start underground utilities
NEXT WEEKS PLANNED MILESTONES TO ACHIEVE:
80% completion of steel building
Finish 75% underground utilities
Start cub and gutter