Eriska Hotel
Jora JK5100 automated composter supplied by Joraform
Introduction
Key features
The Eriska Hotel is a luxurious 25 bedroom 5 Star hotel located on a 300
acre site in rural Scotland. The complex includes a golf course. The
business made a commitment to working in a sustainable way – to
improve environmental performance, minimise waste, reduce resource
use and to raise awareness and adopt sustainable business practices.
Size: 295x117cmx150cm
Spatial requirements: Requires its own building
Weight: 850Kg
Capacity: up to 5kg of catering waste per day
Energy: requires electricity supply
Housing: shed/covered area with a flue pipe
Maintenance: annual service
Output: compost can be used directly on the hotel's golf course and
Nature and quantity of waste treated on site
• The amount of food waste produced by the hotel is around 10-15kg
per day and roughly 100kg per week
• The hotel now composts around 80% of its food waste
• Wood pellets are fed into the mix to maintain balance – the ratio is
about 1 part wood pellets to 10 parts food waste.
flower beds
“We no longer buy compost and it has helped raise the quality of our soil”
Beppo Buchanan-Smith, Co-owner of Eriska Enterprises
Jora JK5100 in housing
Eriska Hotel
Lessons Learnt
• Avoid putting large amounts of citrus fruit peel into the composter as it makes the finished product too acidic
How food is separated for treatment
• The composter is located a short distance from the kitchen
• The kitchen staff have a routine of collecting food preparation waste in
one bucket and plate waste in another
• Once a waste bucket is full someone from the kitchen will take it to the
shed to be emptied into the composter
Use of outputs from treatment
• The hotel has found that the composted material is of a fine
enough quality to be used directly on the hotel’s golf course
greens and flower beds
• The output is also mixed with soil and used for replacing divots
on the golf course.
How the on-site treatment system is managed
• The system is fully automated, requiring little operator time by ground
staff. This amounts to 1 hour a week to empty and reset the chamber
• Food waste is emptied into a shoot with a grinder which chops the waste
into smaller pieces
• The whole process takes around 4 weeks from the food first entering the
composter to it coming out as compost. Compost is often mixed with soil
to produce a mulch
• Maturation isn’t normally required; dependant on how wet the mix is it can
normally go straight on the gardens and mulched with the soil to improve
both.
• If the mixture is starting to smell or become too wet this can be adjusted
by adding wood pellets
• Both sawdust and wood pellets come from the onsite biomass heating
system
• The Jura machine has several in-built safety functions. The chute is locked
during grinding. When the chute is open, the grinder motor is locked
Costs
• Capital costs were in the region of £19,000 for the unit, with no
other costs incurred
• Operating costs - requires to be housed in a shed or covered
area with an electricity supply
• Waste management savings - by composting their food waste on
site they have reduced bin collections costs by 50%. This
equates to a £2000 annual saving
• With the reduction of their waste uplifts the hotel projects that
the composter will have paid for itself in less than ten years
• The hotel no longer buys compost as the compost produced is of
good enough quality to use of the golf course and flower beds.
This case study is part of a series of case studies focussing on the on-site treatment of organic
waste. Other case studies in this series are:
 Dartington Primary school;
 Housing 21;
 Millets Farm Centre;
 University of Southampton;
 University of Bradford; and
 Her Majesty’s Prison Service
www.wrap.org.uk/on_site_treatment
While steps have been taken to ensure its accuracy, WRAP cannot accept responsibility or be held liable to any person
for any loss or damage arising out of or in connection with this information being inaccurate, incomplete or misleading.
This material is copyrighted. It may be reproduced free of charge subject to the material being accurate and not used
in a misleading context. The source of the material must be identified and the copyright status acknowledged. This
material must not be used to endorse or used to suggest WRAP’s endorsement of a commercial product or service.
For more detail, please refer to our Terms & Conditions on our website - www.wrap.org.uk
Waste & Resources The Old Academy
Action Programme 21 Horse Fair
Banbury, Oxon OX16 OAH
Tel: 01295 819 900
Fax: 01295 819 911
E-mail info@wrap.org.uk
Helpline freephone
0808 100 2040
www.wrap.org.uk
Download