Integrated Power System Spreads over thousands of square kilometers Hundreds of Generating Units Thousands of Circuit Kilometers of Lines Tens of Thousands of Devices SINGLE LARGEST COMPLEX MACHINE 100% Reliability IMPOSSIBLE NORMAL RESTORATIVE A L E R T EMERGENCY RESTORATION OBJECTIVES RESTORING NORMAL SYSTEM OPERATION AS QUICKLY AS POSSIBLE SYNCHRONISING OF AT LEAST ONE UNIT AT ALL POWER STATION RESTORING ESSENTIAL LOADS ESTABLISHING ALL INTERCONNECTIONS STARTING ECONOMIC DISPATCH STARTING ALLOCATION OF C. S SHARE MINIMIZING AMOUNT OF UNSERVED ENERGY RESTORATION PROBLEMS IMPAIRED COMMUNICATIONS, LIMITED INFORMATION. RE-ASSEMBLING TIE ELEMENTS OF POWER SYSTEM. UNFAMILIARITY WITH THE SITUATION (DOES NOT OCCUR REGULARLY) TIME CONSTRAINTS INFORMATION TO BE FURNISHED TO AUTHORITIES- PRESSURE ON OPERATOR SYSTEM STATUS DETERMINATION EXTENT OF BLACK OUT AND ACTUAL REQUIREMENT IDENTIFICATION OF BOUNDARIES OF ENERGISED AREAS ASCERTAINING FREQUENCY & VOLTAGE OF ENERGISED AREA STATUS OF GENERATING PLANTS(HOT/COLD/HOUSELOAD ) NON AVAILABILITY OF ELEMENTS(LC/FAULT ETC) OVERLOADING OF ELEMENTS LOADS INTERRUPTED BY UNDER- FREQUENCY RELAY OPERATION OR DIRECT TRIPPING STATUS OF BREAKERS PLANT SURVIVAL AND START UP CONSIDERATION OF TIME-CRITICAL BOILERTURBINE START-UP CHARACTERISTICS (FOR PREDOMINANTLY THERMAL SYSTEMS) SURVIVAL POWER SUPPLY TO THE PLANTS AT THE EARLIEST WITH AVAILABLE ARRANGEMENT (DG SETS) FOR Turbine emergency oil pump . Jacking oil pumps . Barring gear of the turbine . Lubricating oil pumps . Emergency lighting . Battery charger Compressor for CB THUMB RULES PLANT SURVIVAL AND START UP ALL DG/GT’S TO RUN TO PROVIDE START UP POWER. ESTIMATION OF TOTAL START UP POWER REQUIRED TO RUN AT LEAST ONE MACHINE OF EACH POWER STATIONS. TAKING CARE NOT TO LOAD THE GENERATOR SUPPLYING START-UP POWER BEYOND 80% OF ITS CAPACITY. RELEASING AUXILIARY POWER IN STEPS. THE CAPACITY (I.E. FAULT LEVEL) OF ISLAND (SUPPLYING START UP POWER) TO SUSTAINSTARTING CURRENT 0F BFP ETC. TO BE CHECKED. NETWORK PREPARATION CLEARING ALL DE-ENERGISED BUSES GLOBAL OPENING OF ALL THE BREAKERS ELSE:-SELECTIVE BREAKER CAREFUL CONSIDERATION OPERATION AFTER SECTIONALISING A SYSTEM INTO SUB-SYSTEMS TO ENABLE PARALLEL RESTORATION OF ISLANDS AUTOMATICALLY SWITCHED CAPACITORS AND UNDER FREQUENCY RELAYS MAY HAVE TO BE KEPT OUT OF SERVICE AT THE INITIAL STAGE NETWORK ENERGISATION • IDENTIFY THE IMPORTANT AND ESSENTIAL LOADS TO BE RESTORED FIRST • AT EVERY STAGE WE SHOULD BE ABLE TO SATISFY – REACTIVE POWER BALANCE – LOAD GENERATION BALANCE – PROTECTION AND PLANT CONTROL SYSTEM REQUIREMENTS • HVDC IMPORT – ONLY WHEN MIN FAULT LEVEL IS AVAILABLE. • AVOID PARALLELING ISLANDS THROUGH WEAK LINKS THUMB RULES NETWORK ENERGISATION PLANT CONTROL SYSTEM CHARACTERISTICS A) MECHANICAL CONSIDERATIONS REGULATION OF RATE OF CHANGE OF TEMPERATURE TO BE KEPT MANUAL CONTROL FEED WATER WITH THE SOLE OBJECTIVE OF MAINTAINING DRUM LEVEL AT SET POINT PLANTS HAVING FEED WATER REGULATING VALVES PREFERABLE TO THOSE HAVING TURBINE-DRIVEN FEED PUMPS TWO FUEL SUPPLY SYSTEMS - ONE (OR NONE) AUTOMATIC AND ONE (OR BOTH) IN MANUAL. NETWORK ENERGISATION B) ELECTRICAL CONSIDERATIONS VOLTAGE REGULATOR TO BE SWITCHED TO AUTOMATIC CONTROL (FROM MANUAL) ONLY WHEN THE UNIT REACHES A MIN. OPERATING POINT AND A SUFFICIENT VAR GENERATION 1S ESTABLISHED PROTECTIVE RELAYS SUCH AS VOLTS PER HZ, OUT OF STEP, UNDER EXCITATION, DISTANCE, FREQUENCY & FIELD. FORCING CAN INITIATE AN UNDESIRABLE REGULATOR RESPONSE GENERATOR TRIP DURING START UP OR NETWORK ENERGISATION STRUCTURAL SYSTEM SIZE METROPOLITAN OR RURAL COMPACT OR EXTENSIVE GENERATION TRANSMISSION VOLTAGE LEVELS TYPES AND SIZES OF LOAD BLOCKS AVAILABILITY OF INTERCONNECTION ASSISTANCE NETWORK ENERGISATION DYNAMICS REACTIVE CAPABILITIES OF GENERATORS /SYNCHRONOUS CONDENSERS UNDER NORMAL AND EMERGENCY OPERATING CONDITIONS. SHUNT REACTOR AND CAPACITOR LOCATIONS AND MODES OF CONTROL. SIZES, CHARGING CURRENTS AND MAXIMUM SUSTAINABLE OVERVOLTAGE, TRANSFORMER REACTANCES, TAP RANGES AND MODES OF CONTROL GENERATOR MAXIMUM AND MINIMUM OUTPUTS UNDER DIFFERENT CONDITIONS NETWORK ENERGISATION REACTIVE POWER BALANCE SOURCE GENERATION ABSORPTION GENERATOR YES YES LINE CHARGING YES SHUNT CAPACITOR YES SHUNT REACTOR YES SYN CONDENSOR YES YES STATIC VAR COMPENSATOR YES YES THUMB RULES NETWORK ENERGISATION LOAD GENERATION BALANCE • TYPE OF THE LOAD – PEAK OR OFF PEAK – COLD LOAD INRUSH • • • • GENERATOR CAPACITY MINIMUM LOADING OF GENERATOR RESPONSE TO SUDDEN LOAD PICKUP TIME ELAPSED(HOT START) LOAD RESTORATION • DURING RESTORATION EFFECT OF EACH RESTORATION ACTION ON FOLLOWING TO BE CONSIDERED – – – – – – GENERATOR LOADING TRANSMISSION LINE LOADING LOAD ANGLE RATE OF LOADING RESPONSE OF THE GEN TO LOAD CHANGE CHANGE IN SYSTEM FREQ AND OPERATION OF UFR’S – FLUCTUATING LOADS- EX. TRACTION, FURNACE ETC. THUMB RULES RESTORATION STRATEGIES BUILD DOWN OR SEQUENTIAL STRATEGY BUILD UP OR PARALLEL STRATEGY BUILD DOWN OR SEQUENTIAL STRATEGY RE-ENERGIZATION OF BULK POWER NETWORK BALANCED STEP-BY-STEP RESTORATION OF LOADS AND GENERATION SUITABLE FOR SMALL SYSTEMS NOT HAVING LONG EHV LINES OR PREDOMINANTLY HYDRO SYSTEMS WITH HIGH REACTIVE ABSORPTION CAPABILITY OR FOR LARGE SYSTEMS WITH VERY COMPACT SERVICE TERRITORIES USUALLY SELECTED WHEN STRONG NEIGHBOURING INTERCONNECTION ASSISTANCE 1S AVAILABLE INTERCONNECTION STATUS IS TO BE ASSESSED, HENCE TIME CONSUMING AND TASKING. BUILD UP STRATEGY SIMULTANEOUS RESTORATION OF ISLANDS/ SUBSYSTEMS FOLLOWED BY THEIR MUTUAL SYNCHRONIZATION USUALLY SELECTED IN CASE OF A COMPLETE SYSTEM COLLAPSE AND LACK OF INTERCONNECTION ASSISTANCE RELATIVELY QUICK PROCESS REQUIRES SEVERAL OPERATING TEAMS AND ADEQUATE COMMUNICATION FACILITIES FOR MUTUAL COORDINATION BUILD UP EXAMPLE- AP SYSTEM RESTORATION NSR+SSLM VTS+GAS RyTPP+ CUDDAPAH RADIAL ON TN SPECIAL CONSIDERATIONS FIRM TRANSMISSION IN THE INTERCONNECTION BETWEEN SUBSYSTEMS AND FIRM GENERATION CAPACITY IN EACH SUB SYSTEM TO BE ENSURED DURING EARLY STAGES OF RESTORATION DEACTIVATION OF AUTOMATIC LOAD SHEDDING SWITCHED CAPACITORS DURING INITIAL STAGES, AND AUTOMATIC RESTORATION OF SMALLER RADIAL LOADS FOLLOWED BY LOW VOLTAGE AC NETWORK LOADS WHILE MAINTAINING REASONABLY CONSTANT REAL TO REACTIVE POWER RATIO PICKING UP SMALL BLOCKS OF LOADS FOLLOWED BY AS LARGE AS POSSIBLE, WITHOUT RISKING DANGEROUS DECLINE OF FREQUENCY, AS RESTORATION PROCEEDS. KEEPING GENERATOR TERMINAL VOLTAGES RELATIVELY LOW INITIALLY, AND ADJUSTING TRANSFORMER TAPS, SUBSEQUENTLY AS RESTORATION PROCEEDS RESTORATION PLANNING GENERAL GUIDELINES FORMATION OF A PLANNING TEAM • PARTICIPATION OF EXPERIENCED/KNOWLEDGEABLE PERSONNEL FROM RESPECTIVE FIELDS LIKE PROTECTION, COMMUNICATION, OPERATIONS, SYSTEM ANALYSIS ETC. • REVIEW OF SYSTEM CHARACTERISTICS (RELEVANT TO RESTORATION) RESTORATION PLANNING COMMON CONCERNS • TIME CONSUMING NATURE OF SWITCHING OPERATION • START-UP TIMINGS OF THERMAL UNITS • FREQUENCY RESPONSE OF PRIME MOVERS TO SUDDEN LOAD PICK UP • COLD LOAD INRUSH, POWER FACTORS AND COINCIDENT DEMAND FACTORS • AVAILABILITY OF GOVERNOR FACILITIES OF UNITS FORMULATION OF ASSUMPTIONS WORST POSSIBLE SCENARIO TO BE CONSIDERED USING SYSTEM OPERATORS EXPERIENCE AND JUDGEMENT CONSTRAINTS MAY DIFFER WIDELY FOR PEAK AND LEAN CONDITIONS COORDINATION OF LOAD PICKUP WITH GENERATOR RESPONSE AND ARRESTING FALL OF FRFQUFNCY, BEYOND PRIME MOVER RECOVERY CAPABILITY UNDER PEAK CONDITION BLACK-START FACILITIES MAY NOT BE AVAILABLE DURING WEEK END LEAN PERIOD ESTABLISHMENT OF GOALS LOCAL CONDITIONS LIKE GENERATIOR MIX TYPE OF LOAD AND CONTRACTUAL OBLIGATIONS PLAY A DECISIVE ROLE IMMEDIATE OBJECTIVE (SYSTEM SPECIFIC) COULD BE. RE-ENERGIZING THE BULK POWER NETWORK OR ATTAINING A CERTAIN LEVEL OF ACTIVE AND REACTIVE CAPABILITY OR PICKING UP A DOWNTOWN LOAD OR SUPPLYING TIME-CRITICAL INDUSTRIAL LOADS OR ENERGIZING EHV LINE TO A REMOTE, LARGE GENERATING STATION VALIDATION OF ASSUMPTIONS • PROPER MODELLING OF STEADY STATE AND DYNAMIC BEHAVIOUR OF POWER SYSTEM • CONFIRMING THE FEASIBILITY AND SECURITY OF PROPOSED ACTIONS USING A VARIETY OF ANALYSIS AND SIIMULATION TOOLS LIKE STEADYSTATE POWER FLOW, TRANSIENT AND DYNAMIC STABILITY ANALYSIS AND ELECTROMAGNETIC TRANSIENT SIMULATIONS • LOAD DATA, GENERATION DATA ETC. TO BE PREPARED CAREFULLY ITERATION TWO ITERATIONS ARE INVOLVED 1. MODELS HAVE TO BE VALIDATED AGAINST MEASURED AND TELEMETERED DATA 2. THE RESTORATION PLAN (TACTICS) DEVELOPED TO BE CHECKED AGAINST THE INITIAL STRATEGY FOR CONFORMITY AND FEASIBILITY LOGISTICS AND COMMUNICATION CLOSE AND CONTINUAL CO-ORDINATION AMONG POWER SYSTEM POWER PLANT AND FIELD NEIGHBOURING INFORMED OF TO UTILITIES, OPERATORS AUTHORITIES TIME TO TIME ABOUT THE TO BE PROGRESS RESTORATION. DEPEND MORE ON THE UTILITIES’ OWN COMMUNICATION FACILITIES FALL BACK ARRANGEMENT COMMUNICATION FAILURE. IN CASE OF EXPERT / COMMANDO GROUP COMMANDO GROUP TO BE FORMED AS THE SYSTEM COMPLEXITY GROWS. GROUP SHOULD CONSIST OF ENGINEERS FROM DIFFERENT FIELDS AND BELONGING TO DIFFERENT UTIILITIES. PERFECT UNDERSTANDING IN THIS CORE GROUP IT ENCHANCES THE MORAL STRENGTH OF FIELD OFFICERS AS WELL AS REDUCES RESTORATION TIME AUIDITS AND UPDATES A TECHNICAL PERSON OUTSIDE THE RESTORATION TEAM SHOULD AUDIT THE ACTIVITIES. AUDITED RESTORATION PLAN MUST BE UPDATED. DOCUMENTS MUST BE REVISED REGULARLY TO REFLECT THE LATEST CHARACTERISTICS OF THE SYSTEM. CHANGES IN THE SCADA/EMS INSTALLATION OR MAJOR PLANT CONTROL, AVAILABLE TOOLS ALSO TO BE INCORPORATED. TRAINING INSTRUCTION MANUALS OR AUDIO –VISUAL TAPES, FOR INDEPENDENT STUDY CLASSROOM INSTRUCTIONS LEARNING FROM PAST EXPERIENCE DURING RESTORATION. OPERATOR TRAINING SIMULATOR. ROLE PLAY OPERATOR’ S PROBLEM SOLVING CAPABILITY CAN ALSO BE EXPLORED AND DEVELOPED. ALTERNATIVE, SOURCE OF FINDING NEW IDEAS. DETAILED INTERACTION WITH THE PERSONS INVOLVED IN RESTORATION DOCUMENTATION PURPOSE: TRAINING- REFERENCE, IMPROVEMENT OF RESTORATION PROCEDURES. SHOULD BE READILY ACCESSIBLE AND EASILY UNDERSTOOD. SHOULD BE STORED IN A CONVENIENT MEDIA FOR QUICK PROCESSING. SHOULD BE ILLUSTRATED WITH FAMILIAR DIAGRAMS AND CHARTS ACTIONS REJECTED AND INCORPORATED IN THE PLAN MUST BE RECORDED