Vogtle 3 & 4 Commercial Facility Turnover and Information Handover Lessons Learned Elizabeth J. Johnson SNC CM Project Lead Introduction • Education • Professional • Personal Objectives • To provide Operating Experience of Facility Turnover and how it relates to Plant Turnover. • Discuss current Information Handover challenges at Vogtle 3&4. About the Project • Received COL February 2012 • Expected COD – Unit 3 in 2016 – Unit 4 in 2017 • Interesting Fun Facts Commercial Facility Turnover • • • • • • • Vogtle 3 &4 Training Center Fire Training Facility Executive Office Building Engineering and Administrative Building Maintenance and Support Building Communications Building Warehouses Vogtle 3&4 Training Center • Constructed by a local A&E firm • Early occupancy needed – Included partial turnover of the facility • Fire Protection System (FPS) issues • No Formal Turnover process developed Fire Training Facility • • • • Constructed by Primary Construction Contractor Early occupancy needed No Formal Turnover process developed Documentation discrepancies and issues Mitigation Strategy • • • • Development of Facility Turnover Procedures Turnover Strategy Meetings Point of Contact identified Development of Document Receipt Procedures Similarities to Plant Turnover • MUST HAVE a process and plan • Roles and Responsibilities identified • Communication between SNC and the Consortium • Process and plan for receipt of documents and records Information Handover/Turnover WEC Vendor Documents Design/Licensing Documents Shaw Design Documents WEC Procedures WEC Shaw Vendor Documents Shaw Data PDMS (ECF) Information Handover / Turnover Process Into Permanent Storage Available for Ops Readiness & Startup Team Process Into Interim Storage PDF Files CM Software Meta Data Data Maximo Documents & Records w/ Metadata Vogtle Documentum Information Handover Challenges • Contract • Resources • Planning – – – – Pre-operational Program Information Handover Plan CIMS Commercial Facility Turnover Configuration Management Program Activities Jan Feb March April May Policy Statement Procedure Development June July Aug Sep Oct Nov Dec ND-EN-008 Approved 5/9/12 Program Document Procedure Development 3rd Quarter Handover Plan Development 3rd Quarter Handover Specification Development 2nd Qtr Recieve Handover Information From Consortium Until Turnover CM Software RFP 3rd Quarter CERT Approval 3rd Quarter CM Software Implementation 4th Qtr Lessons Learned Recap • Commercial Facility Turnover – Develop and Implement a Plan • Information Handover – Plan early including the EPC contract Questions