AWMA – Georgia Chapter Air Permitting Update April 16, 2013 Eric Cornwell Stationary Source Permitting Program SSPP Structure • 4 Units - 28 permit engineers, 2 admin – Chem Unit – Glass, engineered wood – NOx Unit – Landfills, engines – VOC Unit – Wood pellets, lumber kilns – Min Unit – Military, rendering, asphalt Permit Application Timeliness: • Pending Application Count (April 2013): – 202 permit applications – 12 (non TV-renewal) apps older than six months – 500 permit apps processed in past 12 months • Processing time – Title V significant modifications……161 days – 502(b)10…………………………….…...66 days – Synthetic Minor…………………..……62 days Expedited Permits • In response to Senate Bill 427 O.C.G.A 22-2(c)(1)(A). • Implemented no later than July 1, 2013 • Two stakeholder meetings (Oct and Dec) • http://www.georgiaair.org/airpermit/html/sspp /expeditedssppmeeting.htm Expedited Permits, Cont. • No rulemaking – Director to implement procedures. • Fee-based and optional for applicants • Reviews done by EPD – no third party review • TV-I, TV-R, MAWO not eligible PSD Resources • PSD Guidance for Industry – now available • Pre-processed met data – now available • Background ambient concentrations – now available • Statewide NAAQS and PSD Increment inventory (aka Off-site Emissions inventory) – Not yet…EPD intends to do this if funding is available PSD Guidance for Industry • Provides up-front expectations for a complete PSD application – BACT, Modeling, Submittals – Emphasizes early resolution of issues. • http://www.georgiaair.org/airpermit/html/sspp /psd_guidance_document.htm Meteorological Data • GA EPD has developed 5-years of meteorological data for each ASOS surface and upper air pairing – Pairing based on distance, climatological zone, and data completeness criteria – Last updated on April 4, 2013 • All data sets are available on-line – http://www.georgiaair.org/airpermit/html/sspp/modeling/aerme tdata.htm 8 Surface/Upper Station Pairings KCHA/KFFC KGVL/KFFC KRMG/KFFC KVPC/KFFC KFFC/KFFC KATL/KFFC KAHN/KFFC KDNL/KFFC KMCN/KFFC KCSG/KFFC KABY/KTLH KAMG/KJAX KSAV/KCHS KSSI/KJAX KVLD/KTLH 9 KTLH/KTLH Surface Roughness Update • Previously, EPD provided data sets with three different surface roughness values (0.05, 0.5, 1.0) and the applicant ran AERSURFACE at the project site to find the most representative value. • Now, meteorological data is processed using the surface roughness at the airport – 12 different sectors • Applicant will provide a justification for representativeness in modeling protocol 10 Background Concentrations • GA EPD has develop background concentrations for each county based on the 2009-2011 design values – PM10, PM2.5, SO2, NO2, CO, Pb • Will update to 2010-2012 design values by the end of April • All data sets are available on-line – http://www.georgiaair.org/airpermit/html/sspp/modeling.htm 11 Permit Modeling Guidance • Guideline for Modeling PM10 Ambient Concentration in Areas Impacted by Quarry Operation Producing Crushed Stone - August 7, 2012 – http://www.georgiaair.org/airpermit/downloads/sspp/ modeling/quarryguideline_august2012.pdf 12 GHG Permitting • July 20, 2014 – Biomass deferral set to end. – GHG-major sources with non-PSD permits must “begin actual construction” prior to this date; otherwise permit invalid. • US EPA has recently proposed revised “Global Warming Potential (GWP) for Part 98. 78 FR 19809, Table 2 Boiler MACT and GACT • Final standards published in FR Feb 2013 • SSPP slowly rolling details into permits – – – – Adding to already pending applications Companies can request revisions Conditions as specific as practical No mass “open for cause” Wood Pellet Emission Factors • Process – Log chipper, dryer (usually directcontact), hammermill, pelletizer, and pellet cooler. • Downstream testing showed VOC previously unaccounted for. – Plants over ~120,000 tpy production may be PSD major without downstream controls. • Manny Patel developed default wood pellet emission factors from AP-42 and testing EPD switching email systems – Novell to Outlook – Air Branch transition this week – Email addys to remain the same • First.last@dnr.state.ga.us • First.last@gaepd.org • First.last@gadnr.org – 10 Megabyte attachment limit