Update on the Davis-Woodland Water Supply Project Agency Board June 20, 2013 Discussion Topics • • • • • Recent Activities/Accomplishments Upcoming Activities/Milestones DBO Procurement Project Costs Project Schedule 2 Recent Activities/Accomplishments April - June 2013 PROGRAM MANAGEMENT • Prepared FY 2013-14 Agency Budget • Prepared Amendment to UC Davis Agreement consistent with Amended JPA • Continued pursuit of SRF Loans: – Safe Drinking Water SRF criteria: Lost well capacity due to exceeding MCL’s (nitrate) -Woodland Consolidation of North Davis Meadows -Davis – Submitted initial application for Clean Water SRF $10m in State grant funding for Joint Intake included in legislature-approved State Budget 3 Recent Activities/Accomplishments April - June 2013 (cont’) ENVIRONMENTAL AND PERMITTING • Continued Section 404 Permit efforts - awaiting Biological Opinions from NMFS and USFWS • Commenced Aerosol Study: Four 24-hour sampling events completed CDPH staff site visit on 6/3/13 • Received bids for mitigation banking • Continued work on SEIR for amendment to Water Right Permit for ASR 4 Recent Activities/Accomplishments April - June 2013 (cont’) ENVIRONMENTAL AND PERMITTING • Working with RD 2035 re: WAPA power resource base sharing at Joint Intake • Working with PG&E to define system improvements/costs to serve RWTF and Joint Intake 5 Recent Activities/Accomplishments April - June 2013 (cont’) LAND AND ROW ACQUISITIONS • Continued work on remaining easements: Heidrick/McGinnis and Lillard for easements along Davis Finished Water Transmission Main Sierra Northern Railroad Oates for 3 parcels near Joint Intake site and along Raw Water Pipeline alignment Closing on Intake site & CPG easements • Meeting with Yolo County regarding Encroachment Permit: Road reconstruction/repair following pipeline construction 6 Upcoming Activities/Milestones June - July 2013 PROGRAM MANAGEMENT • Continue to pursue SRF low interest loan and grant funding opportunities • Continue development of ASR Program Preparation for injection testing, modeling, SEIR, water rights amendments • Continue efforts to obtain WAPA power at Joint Intake • Complete Value for Money analysis 7 Upcoming Activities/Milestones June – July 2013 (cont’) ENVIRONMENTAL AND PERMITTING • Outstanding permits/actions: – Biological Opinions from USFWS and NMFS – Section 404 Permit (US Army Corps of Engineers) • Obtain Finding Of No Significant Impact (FONSI) from Bureau of Reclamation • Obtain State 401 Water Quality Certification • Continue Aerosol Study at RWTF Site • Begin negotiations for purchase of environmental mitigation credits 8 Upcoming Activities/Milestones June – July 2013 (cont’) LAND AND ROW ACQUISITIONS • Continue work with Yolo County regarding encroachment permits/road construction • Complete acquisition of Heidrick/McGinnis, Lillard, Turner, and Oates easements • Complete easement agreement with City of Davis • Continue eminent domain actions on 3 parcels PLANNING, DESIGN, AND CONSTRUCTION • Receive priced DBO proposals July 30th 9 DBO Contract Procurement • Received Initial Concept Submittals (ICS) • Reviewed ICS and Proposal Phase Procurement Plans from both DBO teams • DBO teams presented ICS proposals to FPC and in separate meetings to CDPH • Prepared Addendum 2 to DBO RFP – Clarified questions from individual meetings – Modified RFP to respond to common issues raised by both DBO teams 10 Follow Up to ICS Proposals • CH2M Hill – Questions/clarifications noted in ICS letter to team – Satisfactory feedback received – Proposal Phase Procurement Plan approved • CDM Smith – Noted deficiencies in ICS in letter to team – Deficiencies not corrected in team response or through contacts with references – Letter to team noted ICS not in compliance – Team withdrew from competition 11 DBO Procurement Process • 2.5 year, competitive process • 5 initial submittals, 3 shortlisted teams • Process worked as designed – Field narrowed to 1 team from original shortlist – 2 bidders removed themselves from consideration • Impacts of delays in procurement schedule • Inability to correct deficiencies in compliance with RFP provisions • Difficulty meeting Price Ceiling requirements • Allows negotiations to begin ahead of schedule • Savings to Agency of approximately $500,000 12 Competitive Provisions of Procurement Process • Maximum cost ceiling to ensure competitive price – both capital and operation – Maximum capital cost ceiling is 20% less than Engineer’s Estimate • Open book competitive pricing for approximately 70% of work to be completed by subcontract • Open book review of all remaining selfperformed work 13 June 15, 2013 Open House Ad 14 Draft DBO Procurement Schedule ACTIVITY DATE Issue Request for Qualifications January 27, 2011 Receive Statement of Qualifications April 15, 2011 Short list three DBO teams June 2, 2011 Davis and Woodland City Council authorization to proceed with project final engineering and construction March 2013 Issue Request for Proposals December 21, 2012 Receive Initial Concept Submittals & Proposal Phase Procurement Plans May 15, 2013 Priced proposal submittal by Proposer July 30, 2013 Board authorization to proceed with negotiations Board award of service contract August/September 2013 October 17, 2013 Updated: 06/20/13 15 30 mgd Project Costs Presented at April Board Meeting (Apr 2013 million dollars) Construction Costs(a) Capital Costs, 2009-2016 Project Component Cost Cost Category Total Joint Intake (Agency Portion)(b) 14.52 Agency Administration 3.56 Raw Water Pipeline 23.76 Program Management 3.47 Water Supply 1.71 Environmental & Permitting 1.59 Land/ROW Acquisition 4.30 6.18 Regional Water Treatment Facility (RWTF) 96.7 Woodland Treated Water Pipeline 5.70 Davis Treated Water Pipelines 23.35 Pre-Design Permit Fees & Construction Counsel 2.89 Construction TOTAL 166.91 (a) Includes DBO contract design and construction costs, design-bid-build Joint Intake construction costs, and Agency design review, construction quality assurance and contract compliance, engineering services during construction, environmental construction monitoring, environmental mitigation, permitting, and incidental costs. (b) Costs currently under discussions with RD 2035. 166.91 Capital Contingency 7.79 Woodland and Davis Local Facilities 31.74 Costs Expended 2009-2011 7.49 TOTAL CAPITAL COSTS 234.75 16 Updated 30 mgd Project Costs (April 2013 million dollars) Construction Costs(a) Capital Costs, 2009-2016 Component Total Woodland Davis Agency Administration 3.47 1.78 1.69 Program Management 4.19 2.21 2.00 Water Supply 1.69 1.23 0.46 Environmental & Permitting 1.48 0.75 0.72 Land/ROW Acquisition 4.19 2.13 2.06 23.99 Pre-Design 6.78 3.65 3.11 2.89 Construction 169.13 90.01 79.12 Capital Contingency 7.06 3.78 3.29 Woodland and Davis Local Facilities 31.74 16.75 14.99 Costs Expended Since 2009 7.49 4.01 3.48 126.31 110.91 Facility Cost Joint Intake (Agency Portion) 16.82 Raw Water Pipeline 23.66 Regional Water Treatment Facility (RWTF) 96.32 Woodland Treated Water Pipelines 5.46 Davis Treated Water Pipeline Permit Fees & Construction Counsel TOTAL 169.13 (a) Includes DBO contract design and construction costs, design-bid-build construction costs, and Agency design review, construction management, engineering services during construction, environmental construction monitoring, and environmental mitigation, permitting and incidental costs. TOTAL CAPITAL COSTS 237.22 17 Significant Project Cost Changes • Increase in Agency allocation for Joint Intake ($2.3 million) – Allocation to Agency for 20% of “soft costs” (i.e. engineering services during construction, CM, etc.) ($0.9 million) – Increased estimate for pipeline trenchless crossing ($1.4 million) • Pre-design fee for DBO Procurement ($250,000) • Technical Services to Davis and Woodland ($100,000) • Raw Water Intake Agency Facilities Design ($395,000) 18 Intake Bidding Schedule ACTIVITY Receive Formal State/Federal Funding Commitment MWH Completes 100% Design Conduct Contractor Prequalification Process Solicit Bids for Intake Project Bids Received Contract Awarded by RD 2035 DATE July 2013 September 2013 October/November 2013 December 2013 February 2014 March 2014 Updated: 06/19/13 19 Project Schedule Milestones Task Completion By Complete RWTF Site Fill November 2012 Obtain water rights for 10 TAF purchased from CPG November 2012 Issue Final RFP for DBO Contract December 2012 Approval of Project Final Engineering and Construction by Each City March 2013 Obtain USACE 404 Permit July 2013 Secure Joint Intake Construction Funding July 2013 Authorization to Proceed with Bond Financing by Each City Award DBO Contract Advertise Joint Intake Construction Bid Documents Joint Intake Construction Completion DWWSP Acceptance Testing Completion August 2013 October 2013 December 2013 March 2016 September 2016 Updated: 06/20/13 20 Questions 21 Financing Milestone Schedule Task Date Plan of Finance Presentation to City of Woodland City Council Jan 2013 Plan of Finance Presentation to City of Davis City Council Jan 2013 Plan of Finance Presentations to WDCWA (Discussion of Joint vs. Individual Issuance) Feb 2013 City of Davis Special Election, Completion of 218 Process, Approval of Project, and Approval of Water Rates Mar 2013 City of Davis Receives Preliminary Rating Mar 2013 Determination re: Agency Issued Debt Apr 2013 Initial Clean Water SRF Application May 2013 Board Decision Project Rating Agency Review / Selection of Preferred Bidder Jul 2013 Ratings Available for Davis and Woodland Aug 2013 Woodland and Davis City Council Authorization to Proceed with Bond Financing Aug 2013 Information Item for Agency Board re: City Councils’ authorization to proceed with bond financing Aug 2013 Board Award of Service Contract Oct 2013 Bonds Issued OctUpdated: 2013 City Council Decision X X X* X* X 04/17/13 22