Brazil - ICRARD

advertisement
NATIONAL AGENCY OF PETROLEUM,
NATURAL GAS AND BIOFUELS
ICRARD 2010
RAPHAEL QUEIROZ
Buxton, June 23rd, 2010.
PRESENTATION STRUCTURE
1.
2.
3.
Operational Safety Department:
•
Mechanical Integrity Audits/Inspections (until 2009);
•
Resolution ANP 43/2007.
Support for Research & Development:
•
Legal requirement – investment clauses;
•
Integrity management projects: AURI and Monflex.
Conclusions:
•
Partnership in projects;
•
Challenges.
SAFETY - ANP RESOLUTION Nº 43/2007
Focus on Safety Management Systems
New Regulatory Framework for Offshore Safety
 Performance-Based/Goal Setting Model
 Fewer prescriptive requirements
 Non-restrictive approach to technological innovations
Minimum requirements for: Mechanical Integrity, Risk Assessment, Contractors
Selection, Internal Audits, Incident Investigations, Management of Change, Safe
Working Practices, Simultaneous Operations etc.
CONCESSIONAIRE RESPONSIBILITIES
 Ascertain that the installation operator has a management system that meets
the practices of the Management System for Operational Safety (SGSO)
established by the ANP in the Technical Regulation;
 Ascertain that the installation operator will provide the verification of the
critical elements for operational safety and will audit the Operational Safety
Management System as prescribed in the Technical Regulation; and
 Submit to the ANP the Operational Safety Documentation.
ANP DUTIES
 Carry out the analysis of the Operational Safety Documentation –
beginning of operation is allowed if ANP approves it;
 Carry out audits at the installation to verify the performance of the
Operational Safety Management System – 8 audits/month with Bureau Veritas
(BV);
 Carry out inspections of the critical elements for operational safety –
Practice 11 (essencial);
 Put into effect injunction actions when found non-conformities regarding the
Technical Regulation .
OPERATIONAL SAFETY DOCUMENTATION
Management, Leadership and Personnel
Facilities and Technology
MP 1: Culture of Safety, Commitment and
Managerial Responsibility
MP 2: Involvement of Personnel
MP 3: Personnel Qualification, Training
and Performance
MP 4: Work Environment and Human
Factors
MP 5: Selection, Control and Management
of Contracted
MP 6: Monitoring and Continuous
Improvement of Performance
MP 7: Audits
MP 8: Information and Documentation
Management
MP 9: Incident Investigation
MP 10: Design, Construction, Installation
and Decommissioning
MP 11: Critical Operational Safety
Elements
MP 12: Risk Identification and Analysis
MP 13: Mechanical Integrity
MP 14: Planning and Management of Major
Emergencies
Operational Practices
MP 15: Operational Procedures
MP 16: Management of Change (MOC)
MP 17: Safe Working Practices and Control
Procedures in Special Activities
SUPPORT FOR R&D
Objectives of supporting for R & D:
Legal Requirement;
Development of New Technologies: AURI and Monflex Projects;
Centers of excellence: CENPES (Petrobras Research Center)
Qualification of the Oil and Natural Gas professionals: Human
Resource Program;
Development of Geological Knowledge of the sedimentary basins:
ANP is drilling in order to bid better blocks for exploration and
production of oil and natural gas.
R&D INVESTMENT CLAUSE
In the case of Special
Participation Fee be owed by a
field in any quarter of a year, the
Concessionaire must realize
expenses in Research and
Development in an amount
equal to 1% of the net revenue
of Production for that field.
Year
Total
1998/99
$
30.887.085,15
2000/01
$
221.471.784,08
2002/03
$
586.836.845,00
2004/05
$
912.012.921,41
2006/07
$ 1.232.892.602,46
2008
TOTAL
$
860.858.232,82
$ 3.844.959.470,92
SELECTED PROJECTS
Projects selected are meant to be used mainly in deep water operation on the
management of riser integrity:
1.
A.U.R.I. – Autonomous Underwater Riser Inspection Tool;
2.
Monflex – Monitoring of Flexible Oil Lines.
A.U.R.I. PROJECT
Objective:
1.
Managemente of riser integrity;
2.
Inspect the vertical section of the riser in order to detect Corrosion and
Fatigue with lower price and safer technique.
The A.U.R.I inspection may be set by 4 different parameters (also means
redundances in case of failure):
•
Maximum pressure on depth sensor ;
•
The length of the run;
•
Maximum mission duration;
•
Maximum allowed tilt (inclinometer) < 30º.
A.U.R.I. PROJECT
Most used technique – ROV for visual inspection:
•
Requires experienced operator;
•
High cost – special vessel;
•
Continuous monitoring.
Pipeline with anomalous diameter variation
Polymeric sheath damage and exposed
armour steel layer.
A.U.R.I. PROJECT
A.U.R.I Tool primary concerns:
•
Not getting trapped under the TDP (Touch Down Point) and not
getting crushed by the weight of the riser causing damage to the
pipeline;
•
Severe electrical failure, returns automatically – Positive
buoyancy;
•
Mechanical fuses break without releasing sharp pieces – in case of
rescue with ROV is needed.
A.U.R.I. PROJECT
A.U.R.I Tool
Suspension:
•
Eight rollers – diameters from 190 to
360 mm;
•
Absorb impacts and negotiate variation
preventing AURI from getting stuck.
Propulsion:
•
2 thrusters;
•
Used to do all the inspection (positive
buoyancy only for the safety of the tool.
A.U.R.I. PROJECT
Onboard sensors: four cameras, pressure transducer, odometers, digital
compass, inclinometer and thermometers;
•
Lights on only for a brief period – cameras shooting;
•
Digital compass – exact positioning of the acquired images;
•
Odometers – images each 300 mm.
Embedded computer and Software control the system after AURI starts, can
be upgraded and store the inspection data and logs.
The mission is considered complete when reach the parameters set:
pressure, distance, time and inclination.
A.U.R.I. PROJECT
Three options for launching:
•
From the surface of the platform;
•
Submerged with a diver;
•
Submerged with ROV.
Testing:
The AURI has only been tested in a pool environment with offshore tests.
A.U.R.I. PROJECT
Test Results:
•
Mission logic control worked for different returning criteria;
•
Returned without any human intervention;
•
The illuminating was considered appropriate;
•
Forces produced by the thrusters in agreement with the
manufacturer’s specification;
•
Dynamic friction on the rollers was higher than expected –
problem in suspension design;
•
Inspection of 1,000 m – estimated time is 44 minutes.
A.U.R.I. PROJECT
Prototype
A.U.R.I. PROJECT
Conclusion:
•
Challenges for an autonomous riser inspection tool;
•
Hasn’t been tested in real condition yet, but it seems to be good
alternative with low cost, low time, safer condition;
•
Possible to be used as a platform for new types of inspections
using other techniques, such as radiography.
AURI Video
MONFLEX PROJECT
Introduction:
As the operation water depth for flexible risers increases, the stress
level in these structures also increases. This higher load, associated
with stress concentration close to end fitting, can induce fatigue
damage in tensile armors at riser top section. Progressive rupture of
wires due to fatigue, which may be accelerated by corrosion, is an
important indication of deterioration in riser-end fitting connection, and
has become a typical failure mechanism for flexible riser top section.
MONFLEX PROJECT
Objective:
In order to mitigate the progression of these damages, this techniques
try to come with early detection of failure mechanisms at the riser-end
fitting connection, specially at the tensile armors with a continuous
monitoring.
There are techniques under development:
1. Visual torsion monitoring through video cameras;
2. Monitoring through optical fiber sensor extensometers.
MONFLEX PROJECT
Main damages:
• Usually caused during installation;
• Majority of occurrences from 30m depth to the platform connection,
more concentrated in the close end fitting;
• Torsional instability, external sheath damage and corrosion.
MONFLEX PROJECT
Visual torsion monitoring through video cameras;
•
Small angle deformation and on-line data acquisition in order to
provide immediate identification for non-conformities;
•
Procedure: attaching target on the riser – behavior on the videocamera;
•
Already been installed in 4 platforms and results were considered
efficient. Plan to install another 50 until the end of 2010;
•
PTZ (Pan, Tilt and Zoom) system on the cameras;
•
Multiple targets – 1 camera.
MONFLEX PROJECT
Visual torsion monitoring through video cameras
System:
•
Target picture and target
digitalized image –
comparison between the
images and a graph
showing the torsion
variation;
•
In case of excess of
variation on the
predefined values, sound
an alarm.
MONFLEX PROJECT
Monitoring through optical fiber sensor extensometers.
System:
• Many optical fiber sensors covering 100% of the wires;
• Remote sensing – software;
• Rupture brings tension from the operational tension to zero.
CONCLUSION
Searching for partners:
1.
Brazil, through CENPES (Petrobras Research Center), is open for
partnerships in the projects with universities or technological institutes:
2.
CENPES + Brazilian Universities + International Universities.
3.
AURI Project – new technologies (ultrasound inspection or
radiography inspection), robotic solutions and improvement of the tool.
4.
Other Mechanical Integrity Projects.
CONCLUSION
Searching for partners:
5.
Challenges with ultra deep water – how to maintain the gas pipeline
integrity under 2,000 m water depth and 300 Km distance to the shore
(foreseeing problems in 5/10 years).
6.
Challenges with ultra deep water:
7.
•
How to export the natural gas over the distance of 3oo Km to the
shore;
•
How to maintain the gas pipeline integrity under 2,000 m water
depth.
Production of CO2: injection or exporting?
THANK YOU!
RAPHAEL QUEIROZ
RQUEIROZ@ANP.GOV.BR
Download