MOPANI DISTRICT MUNICIPALITY (LIMPOPO) 1 Project description • Lepelle Northern Water appointed as implementing agent for the following: – Accelerate the completion of the Giyani water treatment works (WTW) upgrade and refurbishment – Repair of non functional boreholes (inclusive of Nkhensani Hospital) and – Refurbishment of Giyani Waste water treatment works. 2 3 Progress to date • 32 villages receive bulk water supply • 22 villages receive water from boreholes • One (1) village (Siyandani) receive tankering service as a temporary measure , while permanent solution to provide water is in progress. • Though there is water supply in these villages, there are various challenges on the bulk and reticulation that affect the total coverage 4 List of 32 villages supplied from bulk pipeline 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Makosha Mapayeni Mapuve Maswanganyi Mavalani Mbatlo Mhlava Mningisi Block 3 Ndidani Nghalalume Ngove Nkomo A Nwadzekudzeku Bode Dzingidzingi Bon’wane 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Gaula Giyani CBD Hlomela Homu A Homu B Khakhala Krematart Mahlathi Makhuva Shawela Thomo Vuhehli Vuhehli North Xibulane Xikhumba Xikukwani 5 List of 22 villages supplied by boreholes 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Mbhetle Mninginisi Block 2 Mphagani Munghonghoma Mushiane Mzilela Nkomo B Xitlakati Phalaubeni Muyexe Thomson 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Bambeni Daniel Dzumeri Guwela Khaxani Kheyi Loloka Mageva Maphata Matsotsosela Mayephu 6 Challenges in Siyandani Supply Challenges Remedial action Responsibility Completion Date Giyani Water The Kanyisa Booster is out of LNW April 2015 pumps LNW June 2015 Illegal connections and other Once the water Implementation of LNW June 2015 internal reticulation challenges Water Conservation and demand LNW February 2015 LNW June 2015 Treatment Works operation due to the cavitation of pumps Planned shutdown for the surveillance of the line from the Low Lift reservoir to the Kanyisa Booster station Siyandani pump station Refurbishment of the station. management Mapuve Scheme The Mapuve bulk supply to Support the MDM in resolving the Siyandanhi project is not challenges on the Phase 1 of the commissioned due to the project. blockages on the line blockages on the line ,etc. ) Groundwater Boreholes are vandalized and Refurbishment of boreholes and Augmentation transformers were stolen application of transformers. (i.e. attending to 7 Challenges affecting supply Challenges Remedial Action • Vandalism of Infrastructure • Water Conservation and Demand Management • LNW is providing Security Service to safeguard the Infrastructure • Unauthorised connection • Aging Infrastructure • Replacement of asbestos cement pipelines and associated infrastructure • Lack of operation and Maintenance of Infrastructure • LNW has deployed personnel to assist with the Operations and Maintenance of the Infrastructure. • Continuous support is required • Lack of Reticulation • Installation of reticulation network 8 Giyani water treatment works The intervention had the following impacts: • The 6Ml/day expansion project is functionally complete – snagging in progress • The refurbishment project is complete • Total daily yield is now on average greater than 34Ml/day, a capacity which is sufficient to supply the Giyani town and all its 55 villages that are within the scheme’s footprint 9 Giyani water reticulation • Main booster pump station completed and commissioned • Material for replacement of asbestos cement pipelines A, B, D, E has been procured and delivered • Boreholes to 16 priority villages have been refurbished and commissioned • Village reticulation designs in progress • Leaks and emergency are attended to timeously and promptly • More villages now have water supply and consistent supply is maintained. 10 Nkhensani hospital • The hospital now has a secure water supply • The 6 boreholes have been refurbished and re- commissioned • Installation of water purification plant is in progress and at an Water purification plant on site advanced state. Water softener 11 Giyani wastewater treatment works The intervention had the following 1.5Ml/day expansion project complete and functional – test and commissioning underway impacts: • 1.5Ml/day expansion project complete and functional – test and commissioning underway • 1.5Ml/day package plant – fabrication complete, construction under way. • Morogholo Pump station refurbishment complete 12 Giyani water reticulation • Main booster pump station completed and commissioned • Material for replacement of asbestos cement pipelines A, B, D, E has been procured and delivered. • These pipelines are within the diameter distance of not less than 700 km 13 Action plan Project Brief Scope Time frame Amount R,000 Giyani Groundwater Augmentation- Boreholes at Khensani Hospital And Prioritised villages and scheme assessment March 2015 R65 000 Giyani Water Treatment Works Refurbishment Refurbishment of electromechanical equipment and 16 sand filters 30 R10 000 Giyani Water Treatment Works upgrade Expansion of existing Water Treatment works by 6.7 ML/day 30 Giyani waste Water Treatment works revitalization Refurbish and install package plant and construct 20ML/day March 2017 R333 000 Middle LetabaNsami canal repairs 60km engineering assessment and repairs March 2015 R50 000 Nandoni – Nsami raw water bulk pipeline 52 km pipeline planning and redesigning March 2017 R450 000 Bambanana Pipeline New 600mm pipeline, planning, approval and design March 2017 R308 000 Planning, finalised design and permits March 2017 14 R80 000 New Nwamitwa dam Septemb er 2014 R10 000 Septemb er 2014 Action plan Project Brief Scope Time frame Amount R,000 Mametja Sekororo New Water treatment works, raw and clear water pipelines and reservoirs March 2017 R249 000 Water Conservation and demand management District wide demand and supply measures March 2019 R340 000 Nandoni- Mhinga water supply Feasibility, planning , finalised designs and permits March 2016 R40 000 Namakgale Waste water treatment works upgrade Refurbish existing and upgrade March 2016 R249 000 TOTAL PROGRAMME VALUE R1, 992 000 15 NGAKA MODIRI MOLEMA DISTRICT MUNICIPALITY (NORTH WEST) 16 Mahikeng bulk water supply (BWS) action plan • Phase 1 (Refurbishment of the Mmabatho Water Treatment Works (WTW): – Complete by 30 November 2014, with the last few adjustments to maximize output to be completed in February 2015. – This intervention has increased the output of the WTW from an average of 9.5Mℓ/d to 17.5Mℓ/d currently due to reach 20Mℓ/d once fully operational. • Phase 2 (Upgrading of the Mmabatho WTW from 20Mℓ/d to 30Mℓ/d): – Work is underway and the expected completion date is October 2016 • Phase 2 (Construction of the Lokaleng reservoir and related bulk pipelines): – Design work has been completed – Envisaged to start with construction from April 2016 and completion by July 2017 17 Mahikeng BWS financial implications Funding allocation Total project cost RBIG funding Counter funding Shortfall on MTEF * Cumulative shortfall Expenditure / Allocation x R1000 14/15 Expenditure projected 16/17 12/13-13/14 expenditure 15/16 Total 286 648 22 785 186 869 22 785 17/18 33 039 55 716 87 554 87 554 33 039 45 000 50 000 36 045 0 0 0 0 0 99 779 0 10 716 37 554 51 509 0 10 716 48 270 99 779 * In October 2014 the NMMDM indicated their inability to counter fund the project with an amount of R186 869 million. It is expected that counter funding by the NMMDM will not be possible, resulting in the Department having to fund the complete project. The additional funding is expected to be obtained from the RBIG programme in 2018/19 amounting to R99 779 million for project completion in the same year. 18 Ratlou BWS action plan • Phase 1A (Provision of water to Setlagole): site establishment is underway, together with earthworks at the reservoir and procuring of the necessary materials, i.e. reinforcement steel, shuttering and the like. The expected completion date of the works is June 2016. • Phase 1B(Provision of water to Madibogo) and Phase 2 (Provision of water to the balance of Ratlou): Implementation Readiness Studies are to be completed by July 2015, followed by the approval process and implementation. 19 Ratlou BWS financial implications Funding allocation Total project cost RBIG funding * Counter funding Shortfall on MTEF ** Cumulative shortfall Expenditure / Allocation x R1000 14/15 Expenditure projected 16/17 12/13-13/14 expenditure 15/16 Total 78 690 8 557 51 501 18 632 203 180 8 557 45 000 51 000 98 622 0 0 0 0 0 -124 490 0 6 501 -32 368 -98 622 0 6 501 -25 867 -124 490 17/18 Total project cost RBIG funding * Counter funding Shortfall on MTEF ** Cumulative shortfall ** Although counter funding is reflected as zero, the amount of R7.079 million to be provided by NMMDM as counter funding will be included in the counter funding requirement for the balance of the project 20 Part C WATER CONSERVATION THROUGH WAR ON LEAKS PROGRAMME Background • • All Municipalities in the country experience high water losses. The majority are above the National Average of 36.8% and are therefore vulnerable. Examples of some Vulnerable Municipalities per province in terms of non-revenue water (in excess of the National Average): No. Municipality Province 1 Makana Local Municipality Eastern Cape 2 Ndwedwe Local Municipality KwaZulu-Natal 3 Letsemeng Local Municipality Free State 4 Knysna Local Municipality Western Cape 5 Nama Khoi Local Municipality Northern Cape 6 Moses Kotane Local Municipality North West 7 Polokwane Local Municipality Limpopo 8 Emfuleni Local Municipality Gauteng 9 Emalahleni Local Municipality Mpumalanga 22 Background (cont...) 23 Background (cont...) • Losses categorized as: • Water leaks • Non-revenue water • Unauthorized consumption • Technical inaccuracies • Administrative inaccuracies Physical leakage (Real losses) Unbilled authorized consumption Commercial losses (Apparent losses) • High water loss areas: • “Rural municipalities have a non-revenue water rate of 72.5%, while metropolitan municipalities are averaging around 34.3% water loss. Rural municipalities have such a high water loss, despite servicing less citizens, due to poorer infrastructure.” – Source: http://www.sablog.kpmg.co.za/2014/04/sa-needs-curb-water-wastage – Non_revenue water levels: • Metro Municipalities - 34,3% (on average) • Mid-sized Municipalities - 30,5% - 41,3% (on average). • Small Municipalities – 72.5% (on average) – Source: http://www.wrp.co.za/sites/default/files/event_attachments/WaterWheel_2013_1_Jan. pdf 24 Proposal on War on Leaks STEP 1 STEP 2 (Recruitment and project Infrastructure setup). (Initiate various initiatives national) 15000 UNEMPLOYED YOUTH STEP 3 (Rollout and deploy national) South Africa Area of Supply EVALUATION PLUMBERS RECRUITMENT TRAINING PLACEMENTS WAR ON LEAKS INITIATIVES SCIENTISTS LEAKAGE WATER CONTROL BALANCE INTERVENTION UNLAWFUL MAINTENANCE CONNECTIONS IDENTIFICATION 25 Proposal on War on Leaks (cont...) Real Losses (Training Programmes) Plumbers, Graduate engineers, Asset management, Water Quality, Water Conservation and demand Management Real Losses (Infrastructure assessment) Specialized Services: Infrastructure Conditional assessment for infrastructure priorities Unbilled authorized consumption and Commercial losses Training: Administrative on accounting- Water Balance Apprenticeship This will then input into Municipal IDP processes for MIG allocation 26 Proposal on War on Leaks (cont...) Resource Categories Target Area Objective Value Proposition Numbers 1. Water Agents Communities Water Wise Knowledge Water Conservation Pollution Reduction Water Wise Gardening School learning 7000 2. Plumbers Communities / Municipalities Water Loss reduction Installation of water-efficient devices Water Leakage Repairs water audits; identify and repair water leaks; retrofit water fixtures, fittings and devices and undertake water conservation advocacy. Water losses reduction Savings from reduction of physical losses 3000 3. Technicians Municipalities / Industry Water system management ,Retrofitting, Pressure management Water system management 1000 4. Process Controllers Municipalities / WATSAN Sector Water treatment and waste management Water and waste water treatment management 500 5. Scientists Municipalities / WATSAN Sector Water / Waste management Water and waste water controls and verifications 500 6. Engineers Municipalities / WATSAN Sector Water / waste Water Systems Design and maintenance Water and waste water system design and maintenance, Assets Management 500 7. Post Graduates MSc Municipalities / WATSAN Sector Water / waste research and development Research and development in water risks 250 8. Post Graduates PhD Municipalities / WATSAN Sector Water / waste research and development Research and development in water risk management and solutions 250 9. Water Managers Municipalities Develop and promote WC/WDM strategies and BPs Management of water balance more accurately Improved management through sectorisation, water balance calculations and response time 2000 27 Implementation plan 28 Budget: real losses (training programme) DESCRIPTIO N Total YR-1 Contract Staff R94,500,000.00 R15,750,000.00 YR-2 R15,750,000.00 YR-3 R15,750,000.00 YR-4 YR-6 YR-6 R15,750,000.00 R15,750,000.00 R15,750,000.00 Graduate Learner R16,011,811,11 R5,993,572,222.2 R3,403,572,222.2 R3,403,572,222.2 R1,570,322,222.2 R1,570,322,222. Requirement R70,450,000.00 1.11 2 2 2 2 22 (including stipend) Overheads / R424,305,300.0 R168,479,300.00 Capex - RWA 0 R50,815,200.00 R50,815,200.00 R52,565,200.00 R50,815,200.00 R50,815,200.00 Total (Excluding project fees, R16,530,616,41 R6,177,801,522.2 R3,470,137,422.2 R3,470,137,422.2 R1,638,637,422.2 R1,636,887,422. R137,015,200.0 contingences 1.11 2 2 2 2 22 0 and CPI adjustment) Project management R1,405,102,394 R491,785,838.23 fees - 8.5% of .94 Total R281,020,478.99 R210,765,359.24 R140,510,239.49 R140,510,239.4 R140,510,239.4 9 9 Contingencie R896,785,940.3 s - 5% of R149,464,323.38 0 Total R149,464,323.38 R149,464,323.38 R149,464,323.38 R149,464,323.3 R149,464,323.3 8 8 Overall cost (excluding CPI) R18,832,504,74 R6,819,051,683.8 R3,900,622,224.5 R3,830,367,104.8 R1,928,611,985.1 R1,926,861,985. R426,989,762.8 6.36 4 9 5 0 10 8 29 Budget: real losses (infrastructure) • Real Losses (Infrastructure) – This Budget should be a revolving loan, there is a positive business plan in fixing all the leaks • Example: Emfuleni has an estimated 37% nonrevenue water – Roughly 15% of this is infrastructure losses – If they buy R500,000,000 worth of water they loose R75,000,000 on Municipal leaking infrastructure 30 Funding / investment required • Real Losses (Training Programme) – Budget rolled over 5 - 8 years is approximately (R18 Billion) – Bulk of budget (Stipends, Training Costs) • Real Losses (Infrastructure) – Revolving loan that all municipalities will pay back with water savings revenues (R5 Billion) – The 1% fund can contribute to the revolving loan fund 31 Decisions under consideration • National roll out approach • Stakeholder identification • Budget provisions 32