where we are going november 20, 2013

advertisement
MARYLAND TRANSPORTATION
BUILDERS AND MATERIALS ASSOCIATION
WHERE WE ARE – WHERE WE ARE GOING
NOVEMBER 20, 2013
PAUL L. SHANK P.E., C.M.
CHIEF ENGINEER
BWI MARSHALL AIRPORT
RSA IMPROVEMENTS, PMP & STANDARDS PROGRAM
PROGRAM YEAR 2013
TASK CONTRACT
1
2
3
4
5
6
7
8
9*
Runway 15R-33L
Standards Compliance
Earthwork Project
Runway 15R Deicing
Pad Pavement Rehab.
And Stnds. Compliance
Low Maintenance
Grassing Test Plots
General Aviation
Pavement Rehabilitation
RSA Program
Environmental Stream
Restoration Project
Runway 15L-33R
Runway Safety Area
Improvements
Runway 15R-33L RSA,
PMP and Standards
Compliance Project
Runway 10-28 and 15R33L Obstruction Clearing
Project
Runway 15R-33L
NAVAIDS Project
*Graphic location same as Task 7
VALUE MBE
$21,800,000
25%
$14,169,000
30%
$133,000
25%
$994,000
20%
$2,079,000
26%
$4,960,000
20%
$83,235,000
20%
$413,000
4%
$5,409,000
13%
15R 33L EARTHWORK
CONTRACT VALUE:
$ 21,756,470
Contract Completes – Summer 2014
MBE: 25%
PROJECT OVERVIEW:
Clearing and grubbing. Storm drain installation. Box culvert
installation. Sanitary sewer and underground fire hydrant
relocation. Mass earthwork, grading and retaining wall.
RUNWAY 15R DEICING
CONTRACT VALUE:
$ 14,168,409
Contract Completes – November 2013
MBE: 30%
PROJECT OVERVIEW:
Removal of existing pavement. Installation of new
glycol drainage infrastructure, lighting, diversion vaults.
New concrete pavement and pavement markings.
ENVIRONMENTAL STREAM RESTORATION
CONTRACT VALUE:
$ 2,078,771
Contract Completes – July 2014
MBE: 26%
PROJECT OVERVIEW:
Grading of stream channels and placement of fill.
Construction of in-stream structures. Removal of
invasive vegetation and plantings.
RUNWAY 15L 33R RSA
CONTRACT VALUE:
$ 4,959,398
Contract Completes – Spring 2014
MBE – 14%
PROJECT OVERVIEW:
New vehicle service road and airfield equipment access
road. Drainage pipe, box culvert and structure installation.
Preparation of site and infrastructure for future relocation of
existing NAVAIDS.
RUNWAY 15R 33L RSA
CONTRACT VALUE:
$ 83,235,000
Proposed Schedule – September 2013 to April 2015
PROJECT OVERVIEW:
Comprehensive Pavement Rehabilitation. Runway Safety
Area Grading and Improvements. NAVAID Relocations and
Infrastructure Improvements. Runway and Taxiway Lighting
Improvements. Taxiway Realignments. Runway Incursion
Prevention Elements.
PROGRAM YEAR 2014-2015
2014-2015 PROGRAM ELEMENTS
6
15A
New T/W “Uniform” & T/W
“Uniform 1” And South Portion
De-ice Pad
15B
Runway 4-22 Conversion To
Taxiway “Papa”
15C
New Taxiway Construction (EB75)
15B
15A
15D
15D
Runway 10-28 Navaids &
Runway 28 Displacement
Old Taxiway “Delta” Demolition
15C
6
PROGRAM VALUE 75-100M
EXISTING TERMINAL - 2012
SECURITY
CHECKPOINTS IN THE
THROAT OF THE
CONCOURSES
RESTRICT EGRESS/
EVACUATION CAPACITY
CORRIDOR WIDTH
IN ORIGINAL
PORTIONS OF
CONCOURSES
INADEQUATE
10
LONG TERM TERMINAL PLAN
UPPER LEVEL PLAN
NEW CHECKPOINTS
BETWEEN
CONCOURSES
BEHIND SECURITY
CONNECTORS ALLOW FOR
LOAD BALANCING AND
CONNECTING FLIGHTS
11
LONG TERM TERMINAL PLAN PHASING PLAN
CONCOURSE D
ORIGINALLY FIRST
BECAUSE DEFICIENCIES
WERE GREATER DUE TO
THE NUMBER OF GATES
SERVED.
E
SWA / AIRTRAN MERGER
AND CONSOLIDATION ON
CONCOURSES A/B/C
SHIFTED PRIORITIES TO BC
CONNECTOR
C
A
B
12
BC CONNECTOR PROGRAM
TWO CONSTRUCTION PROJECTS
B/C CONNECTOR
CONCOURSE C
WIDENING
13
BC CONNECTOR
FINAL UPPER LEVEL PLAN
9 LANE
CHECKPOINT
14
BC CONNECTOR
CONTRACT VALUE:
$ 43,937,000
MBE: 20%
PROJECT OVERVIEW:
Secure passenger corridor connecting Concourse B and C.
Nine (9) Lane Security Checkpoint. Observation Deck
improvements. Concessions and Office Spaces.
BC CONNECTOR
NEW BC SECURITY CHECKPOINT
NEW BC CONNECTOR
CONCOURSE C WIDENING
CONTRACT VALUE:
$ 28,799,512
Completion Date – January 2013
MBE: 31%
PROJECT OVERVIEW:
Renovate Concourse C to include larger passenger hold rooms
and a wider corridor and exit.
New passenger boarding bridges. New baggage handling system.
New public restrooms. Modify mechanical & electrical systems.
DE CONNECTOR
CONTRACT VALUE:
$ 75-100M
Proposed Design Schedule: September 2013- September 2014
Proposed Construction Schedule: January 2015- November 2016
DE CONNECTOR
DE CONNECTOR
ARRIVAL LEVEL PLAN
DE CONNECTOR
DEPATURE LEVEL PLAN
NEW DE SECURITY CHECKPOINT
DE SECURITY CHECKPOINT
VIEW FROM TERMINAL D
DE SECURITY CHECKPOINT
VIEW FROM TERMINAL E
DE CONNECTOR
DE CONNECTOR
VIDEO OF PROJECT OVERVIEW:
BWI CONFORM.wmv
Contract Number & Title
MAA-CO-13-020
Parking Access and Revenue Control System (PARCS)
Proposed Date
Project Value
***May 2013
$8M-$11M
MAA-CO-14-001
2015 Airfield Capacity Enhancement Project
**April 2014
$80M
MAA-CO-14-005
International Building Expansion
**December 2013
$7M
MAA-CO-14-007
Comprehensive Interior/Exterior Modification 2014
**November 2013
$25M
**November 2013
$1.7M
*October 2013
$.5M
**November 2013
$1M
MAA-CO-14-008
Long Term Parking Lot B Pavement Rehabilitation
MAA-CO-14-009
Pedestrian Walkway from CRCF to the East Tenant Lot
MAA-CO-14-010
Public Parking Area Pavement Rehabilitation
MAA-CO-14-011
Central Terminal Third Floor Elevator Upgrades
**November 2013
$.5M
MAA-CO-14-012
Air Cargo Drive Pavement Rehabilitation
*February 2014
$1.7M
*Program
**Advertised
***BidsDue
****Bid Opening