ERTMS deployment experience in Turkey: Mersin - Toprakkale and Gebze - Köseköy lines Leone Fenzi Istanbul, April 2nd 2014 1 Presentation Agenda Ansaldo STS: About Us ERTMS/ETCS: the System Ansaldo STS: ERTMS/ETCS Experiences in Greenfield Projects Ansaldo STS: ERTMS/ETCS Experiences in Brownfield Projects Ansaldo STS Answers to Signalling Projects Challenges 2 Page 2 About us: Ansaldo STS History Ansaldo STS: Over a century of innovation around the World, and continuing Gio. Ansaldo e C. Founded 1853 in Genoa, Italy By Giovanni Ansaldo Transferred to Finmeccanica In 1948 Ansaldo Transporti (ATR) Created in 1966 Page 3 Union Switch and Signals (US&S) Founded 1881 In USA By George Westinghouse Company des Signaux (CSEE) Founded 1902 In France By Fernand Cumont and Baron d’Empain Acquired by ATR In 1988 Acquired by ATR 49% in 1989 100% in 1996 Ansaldo STS Established 2006 Ansaldo Signal NV Established 1996 3 About us: Ansaldo STS Business Lines Ansaldo STS delivers a full range of Railway and Mass Transit Transportation Solutions and Signalling Systems: High Speed Lines Freight Lines Main and Suburban Lines Driverless Metros Page 4 Tramways and Light Rails Conventional Metros Security Systems 4 Presentation Agenda Ansaldo STS: About Us ERTMS/ETCS: the System Ansaldo STS: ERTMS/ETCS Experiences in Greenfield Projects Ansaldo STS: ERTMS/ETCS Experiences in Brownfield Projects Ansaldo STS Answers to Signalling Projects Challenges 5 Page 5 The ERTMS/ETCS What, Why & How ERTMS/ETCS enforced by the Law in Europe …but enforced by the Market all around the World: 6 Page 6 ERTMS in Turkey: TCDD’s <<Vision 2023>> Thanks to the economical and technical benefits granted by the Interoperability and because of its flexibility, robustness and proven-in-use results, ERTMS/ETCS has been chosen by TCDD as the signalling system to implement its growth plan Source: TCDD Website 7 Page 7 Presentation Agenda Ansaldo STS: About Us ERTMS/ETCS: the System Ansaldo STS: ERTMS/ETCS Experiences in Greenfield Projects Ansaldo STS: ERTMS/ETCS Experiences in Brownfield Projects Ansaldo STS Answers to Signalling Projects Challenges 8 Page 8 Ansaldo STS “Greenfield” ERTMS References L1 and/or L2 Greenfield projects (brand new lines) – new Interlocking + ATP (incl. ERTMS) Turkey: Gebze-Köseköy Line (ERTMS L1) 9 Page 9 Turkish Greenfield Lines – ERTMS/ETCS L1 Gebze-Köseköy Line – Length 56 km Max Speed (with Level 1) 160 km/h Signalling Scope of Work Interlocking “Multistation” Page 10 Traffic Control System (1 CTC) ERTMS Level 1 Automatic Block Audio Frequency Track Circuits Point machines Power supply (On Line double conversion UPS) 10 Turkish Greenfield Lines – ERTMS/ETCS L1 Gebze-Köseköy Line – Project Status Interlocking/ETCS Engineering/Basic Design: completed Hardware Design: completed Materials / Installation: ≈ 25% done Commissioning: April/May 2014 RAMS / Verification activities: April/May 2014 11 Page 11 Presentation Agenda Ansaldo STS: About Us ERTMS/ETCS: the System Ansaldo STS: ERTMS/ETCS Experiences in Greenfield Projects Ansaldo STS: ERTMS/ETCS Experiences in Brownfield Projects Ansaldo STS Answers to Signalling Projects Challenges 12 Page 12 Ansaldo STS “Brownfield” ERTMS References L1 Brownfield projects (existing lines) – Interlocking revamping and ETCS to be added Turkey: Mersin-Toprakkale & Boğazköprü-Yenice Lines 13 Page 13 Turkish “Brownfield” ERTMS/ETCS Lines Boğazköprü-Yenice and Mersin-Toprakkale – length 430 km Single track: Bogazkopru-Yenice & Section Adana-Toprakkale = 352 km Double track: Mersin-Adana = 78 km Total number of stations = 33 Signalling Scope of Work Twelve Interlocking “Multistation” (each one controlling up to three stations) Traffic Control System (Two Central Posts: Kayseri & Adana) ERTMS Level 1 Automatic Block Level Crossings Line track circuit audio frequency Point machines Power supply with two Uninterrupted Power Supply (UPS) 14 Page 14 Turkish “Brownfield” ERTMS/ETCS Lines Boğazköprü-Yenice and Mersin-Toprakkale – Project Status Loop extension works completed at 97% “Precommissioning and Commissioning” activities performed for the Interlocking 09 (Mersin, Tirmil and Taskent) “Precommissioning activities” almost completed on Interlocking 08 (Durak; Belemedic; Hacikiri) Design delivered to Customer; Installation ongoing Page 15 SIGNALLING and TELECOMMUNICATION BOĞAZKÖPRÜ - YENİCE & MERSİN - TOPRAKKALE Project Name Work Item Description Total Quantity Unit Current Quantity Remaining Quantity Physical Progress Detail Design 12,00 Interlocking 12 0 100,00% Technical Buildings 25,00 Nr 19,00 6,00 76,00% Cables 6.252,60 km 5.088,00 1.164,60 81,37% Cable Ducts 511,99 km 424,48 87,51 82,91% Signals 685,00 set 462,00 223,00 67,45% Installation of Track-circuit 1.859,00 set 806,00 1.053,00 43,36% Installation of Indoor equipment in the technical building 33,00 set 15,00 18,00 45,45% Installation of point machines 337,00 nr 325,00 12,00 96,44% Level crossings 124,00 nr 51,00 73,00 41,13% CTC 2,00 nr 0,50 1,50 25,00% Interlocking 12,00 set 1,00 11,00 8,33% Balises 3.502,00 nr 0,00 3.502,00 0,00% Onboard Equipment 23,00 nr 10,00 13,00 43,48% Telephone System 33,00 set 0,00 33,00 0,00% 15 Presentation Agenda Ansaldo STS: About Us ERTMS/ETCS: the System Ansaldo STS: ERTMS/ETCS Experiences in Greenfield Projects Ansaldo STS: ERTMS/ETCS Experiences in Brownfield Projects Ansaldo STS Answers to Signalling Projects Challenges 16 Page 16 Product Upgrade “WSP” Platform “WSP”: Wayside Standard Platform – ASTS new Platform for Infrastructure Applications: Interlocking ERTMS CBTC Features: New WSP Platform SIL 4 is derived from already existing 2x2oo2 vital platform already in revenue service in the biggest Italian Electronic Interlocking (Pisa Central Station) WSP satisfies high performances functional and availability requirements: Better Performances Higher Connectivity Higher Reliability Higher Maintainability WSP allows high Flexibility in signalling application (Interlocking centralized/distributed / Gateway / Radio Block Centre / Zone Controller) WSP embeds New Field Device Controllers: flexible, less space/power consuming, cheaper 17 Page 17 ASTS Scalable Approach to Testing Completely Target Test of IXL Fieldconnected complete simulated Device realconnections System to environment simulated environment 18 Page 18 Ansaldo STS: ready for TCDD’s <<Vision 2023>> Source: TCDD Website 19 Page 19 Thank You for your kind attention www.ansaldo-sts.com