Singapore – Infrastructure

Projects

KARMJIT SINGH

CHAIRMAN CILT SINGAPORE

4 JULY 2014

Agenda

1.

2.

Changi Airport East Industrial / Logistics Project

Project Jewel at Changi Airport

3.

Relocation of PSA Container Port to Pasir Panjang (Phase 1) and Tuas (Phase 2)

4.

5.

Development and Expansion of Seletar Airport & Aerospace

Park

New International Cruise Terminal

Agenda

6.

E-Freight and IoT (Internet of Things)

7.

High Speed Rail between SIN-KUL

8.

Expansion of MRT Rail Network

9.

New Generation of Logistics / Warehouses

10.

Development of Modern Industrial Parks in Iskandar (South

Johore)

11.

Development of Industrial Parks in Bintan and Batam

Project description:

New airfreight terminals, cargo centre for forwarders, logistics park and mail control

Expected completion date: 2020 – 2022

Budget: SGD 1

Billion

Project Owner:

Changi Airport

Group

Capacity: 4.5 – 5.5 million tonnes

1. Changi Airport East Industrial

/ Logistics Project

Project description:

World-class lifestyle destination for global travelers. The complex will offer aviation facilities, retail offerings and unique leisure attractions.

Expected completion date: 2018

Budget: SGD 1.47

Billion

Project Owner:

Changi Airport

Group

Capacity: 24 million passengers per annum

2. Project Jewel at Changi Airport

Project description:

PSA port to be relocated in two phases: (1) Pasir

Panjang Port and

(2) Tuas Port

Expected completion date:

2020

Budget: SGD 4.5

Billion

Operated by: PSA

Capacity:

Additional 15 new berths

3. Relocation of PSA to

Pasir Panjang (Phase 1) & Tuas

(Phase 2)

Project description:

Development of

Seletar Airport designed to support industrial and business aviation activities.

Expected completion date: End of 2014

Budget: SGD 60

Million

Project Owner: JTC

& EDB

Capacity: 30 aerospace companies & an

1,800 m runway

4. Development & Expansion of

Seletar Airport & Aerospace Park

Project description:

Development of the

Marina Bay Cruise

Terminal Singapore for international passenger traffic.

Completion date:

2012

Budget: SGD 450

Million

Operated by: SATS

Capacity: Able to berth two 3,000 pax cruise ships

5. New International Cruise

Terminal

Project description:

Using RFID to improve land/sea/freight information flow and productivity

Expected completion date:

2017

Project Owner:

CAAS & IDA

6. E-Freight & IoT (Internet of

Things)

Project description:

Using RFID to improve land/sea/freight information flow and productivity

Expected completion date:

2017

Project Owner:

CAAS & IDA

6. E-Freight & IoT (Internet of

Things)

Project description:

High Speed Rail

(HSR) between

Singapore and

Malaysia to improve SIN-KUL intercity connectivity

Expected completion date:

2024

Budget: SGD 15

Billion

Operated by: ?

7. High Speed Rail between SIN-

KUL

Project description:

Expansion and development of MRT rail network to serve extended areas and a greater number of commuters.

Expected completion date: 2025

Budget: SGD 60

Billion

Operated by: LTA

Capacity: Increase from 160 to 320 km of track

8. Expansion of MRT Rail Network

Project description:

Expansion and development of MRT rail network to serve extended areas and a greater number of commuters.

Expected completion date: 2025

Budget: SGD 60

Billion

Operated by: LTA

Capacity: Increase from 160 to 320 km of track

8. Expansion of MRT Rail Network

Project description:

Improve productivity and develop green buildings, green transport, green ports and green freight and logistics.

By 2020, the commitment is to have 16% reduction in emissions, 30% energy usage reduction, 20% green buildings and

11% increase in public transport usage.

Expected completion date: On-going

9. New Generation of Logistics /

Warehouses (Green Logistics)

Project description:

Improve productivity and develop green buildings, green transport, green ports and green freight and logistics.

By 2020, the commitment is to have 16% reduction in emissions, 30% energy usage reduction, 20% green buildings and

11% increase in public transport usage.

Expected completion date: On-going

9. New Generation of Logistics /

Warehouses (Green Logistics)

Project description:

Joint Malaysian and Singapore government collaboration

Expected completion date:

On-going

10. Development of Modern

Industrial Parks in Iskandar (South

Johore)

Project description:

Joint Malaysian and Singapore government collaboration

Expected completion date:

On-going

10. Development of Modern

Industrial Parks in Iskandar (South

Johore)

Project description:

Joint Malaysian and Singapore government collaboration

Expected completion date:

On-going

10. Development of Modern

Industrial Parks in Iskandar (South

Johore)

Project description:

Development of

Bintan Industrial

Estate and

Batamindo

Industrial Park for manufacturing companies.

Expected completion date:

On-going

11. Development of Industrial Parks in Bintan and Batam