PPT - Telugunadu CMA Convention

advertisement

Infrastructure, Petroleum and Gas

: Key Enabler for successor states

A.P. Gas Distribution Corporation

(A Joint Venture of APGIC and GAIL Gas Limited)

Vizag

20 September

2014

Objectives of the session

2

Opportunities for establishing infrastructure facilities

Developing petroleum and gas corridors

Infrastructure as pre-requisite for industrial growth and economic activities

PPP model: Pros & cons

3

Disclaimer

The following presentation and views are for information purpose only and are express personal opinion of the speaker. These are not endorsed by GAIL

, APGDC or GoAP. Audience may independently verify before taking action and speaker does not held any responsibility for accuracy of information contained therein.

Presentation Outline

4

Successor States: Value unlocking in Oil & Gas Sector

Introduction of APGDC

Transmission & Distribution Infrastructure

Oil and Gas production infrastructure

LNG Import facilities

Refineries & Product / LPG Pipelines

Oil & Gas Infrastructure : Key enabler of growth

Key drivers and Challenges

5

Value unlocking in Oil & Gas Sector

To Bhilwara

To Ankot (Gujarat)

ENPL

Gangavaram

Kakinada

Offshore Gas fields

(RIL, ONGC, Cairn, GSPL)

GAIL KG Basin Network

Legends:

GAIL KG Network:

Krishnapatnam

EWPL (RGTIL) :

MVPL (under const):

Ennore

P/l under bidding :

LNG Terminals planned:

Gas Fields :

Successor States

Specific priorities in individual states

Focussed development

Industrial

Decentralization – towards inclusive growth

Deeper focus in Oil & Gas in

A.P.

: production, import,

Distribution & export to other states

Telengana : Acts as consumption centre as well as transit corridor

Paradigm change & New

Synergy with other states :

New product pipeline (from

Paradip), power transmission from Gujarat, Gas pipeline from Bangalore /Ennore

6

Value Unlocking : Andhra Pradesh

Population : 4.94 crores

Coastline : 972 km , Second longest in India, next to Gujarat

Gross State Domestic Product

(GSDP) : Rs.

2,35,930 Cr

(US$39 billion) in 2012-13

Industries : IT, Boitech, Pharma, Oil & gas, Power, Banking & Financial,

Tourism, Textiles, Retail, Leather

Oil & Gas : Oil & Gas reserves (KG

Basin) Refinery, Petroleum Import, pipelines, Gas Based IPPS

7

Value Unlocking : Telengana

Population : 3.52 crores

Mineral-rich state, with coal reserves

Collieries at Singaerni

Gross State Domestic Product

(GSDP) : Rs. 3,35,018 Cr in

2012-13

Industries : IT, Boitech, Tourism

Power : Coal, Hydel based

8

Introduction of APGDC

APGDC – An Introduction

9

APGDC Limited incorporated on 10.01.2011 by APGIC

Equity Structure: APGIC :50% ; GAIL Gas : 50% with each to offload 25% to Private/Public Investors

APGIC : Joint Venture of APIIC with 51% and APGENCO with 49%

GAIL Gas : Wholly owned subsidiary of GAIL (I) Ltd.

Authorized capital is Rs. 100 Crores and paid up as on date is Rs. 20 Crores. APGIC and GAIL Gas paid Rs. 10 Crores each.

Objectives and Business Plan, as developed through KPMG:

Development of Natural Gas regional pipeline grid across the state of AP; City Gas Distribution to cover various Major cities of AP.; and creation of LNG infrastructure in the East Coast for import of Gas, etc.

APGDC – An Introduction

10

Objective :

To Design , Develop and construct Gas pipeline and gas distribution systems, Gas processing, Liquefaction, Regasification plants and to import, store, process, distribute natural gas transport,

To develop gas distribution networks in the state of Andhra

Pradesh

Vision

To be the leader in sourcing, transporting and distributing natural gas in Andhra Pradesh , and beyond by maximizing value creation for all stakeholders in an environmentally sustainable manner.

To Source natural Gas : through import or domestic

Mission

Making Andhra Pradesh a Natural Gas driven economy

MOU with Govt of A.P.

11

MOU signed between APGDC and GOAP during

Partnership Summit, 14 Jan, 2012

To lay Dedicated natural gas pipeline from Kakinada to

Vishakhapatnam

To lay regional pipeline grid

GOAP would facilitate permissions and clearances

MOU Signed between GAIL Gas / APGDC and GOAP during Partnership Summit, 14 Jan, 2012

To set up of FSRU and On land terminal through APGDC.

GOAP would facilitate permissions and clearances

12

Division of A.P. State : Value unlocking in Oil & Gas

Sector

Introduction of APGDC

Transmission & Distribution Infrastructure :

Existing Pipelines

Transmission & Distribution Infrastructure

Unified AP Gas grid

Oil and Gas production infrastructure

LNG Import facilities

Refineries & LPG Pipelines

Oil & Gas Infrastructure : Key enabler of growth

Key drivers and Challenges

India : NG Vs Total Energy trend

13

700

600 52,9

46,3

55,3

56,7

500

46,7

37,2

36,1

400

33,5

32,1

28,7

26,6

300

200

320,8

345,1

366,8

100

390

420,1

446,5

483,8

510,2

534,6

573,3

595

Share of Natural gas in the Energy

Basket : 24 %

There is marginal decline in 2013

0

2003 2004 2005 2006

Natural Gas (in Mtoe)

Total Energy (Mtoe)

2007 2008 2009 2010 2011 2012 2013

Share of Natural

Gas is in increasing trend in longer term

Data Source : B P Statistical Review 2014

Natural Gas Consumption

14

Share of Natural gas consumption as part of total primary energy :

Slow but steady growth

12,00

10,00

8,00

Gas as % of Total Energy

8,29 8,32

8,75

8,59 8,59

8,33

9,65

11,11

10,34

9,23

7,78

Natural consumption sizable and significant role in longer term

Gas is

6,00

4,00

2,00

0,00

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Data Source : B P Statistical Review 2014

A.P. natural gas demand: salient features

Market Study and Business Plan completed by M/s KPMG:

Existing shortfall:13.6 MMSCMD

Additional prospective demand (in existing plants): 12.4 MMSCMD

Due to drastic reduction in domestic gas production, huge

Investments made by power plants threatened to become stranded assets

Power is the first customer base in

AP:

Affordability of RLNG is a key issue,

Pipeline connectivity required to mitigate the risk of power shortage.

Existing Demand (in MMSCMD)

Sector

Fertilizer

Power

CGD

Ceramics, Glass,

Steel, and Others

Total

Contract ed qty.

3.3

14.0

0.10

0.9

18.3

Supply

Future Demand (in MMSCMD)

Sector Require ment

Fertilizer (RLNG ) 5.4

Power

CGD

Others

Total

10.0

2.0

2.0

19.4

2.6

2.8

0.11

0.2

5.7

GAP

5.4

3.0 *

2.0

2.0

12.4

15

GAP

0.7

12.2

-

0.7

13.6

16

Gas Distribution Infrastructure

To Bhilwara

To Ankot (Gujarat)

ENPL

Gangavaram

Kakinada

Offshore Gas fields

(RIL, ONGC, Cairn, GSPL)

GAIL KG Basin Network

Krishnapatnam

Ennore

Legends:

GAIL KG Network:

EWPL (RGTIL) :

MVPL (under const):

P/l under bidding :

LNG Terminals planned:

Gas Fields :

Gas Pipelines

17

S no. Name of the P/L

1 GAIL KG Basin

Network

2 East West Pipeline

(EWPL)

3 Mallavaram Bhilwara pipeline (MBVPL)

From – To

Kakinada- Rajahmundry

– Vijayawada

Kakinada – Gujarat

Kakinada – Bhilwara

Capacity

(MMSCMD)

15

80-120

57

4

5

Kakinada Srikakulam pipeline and Ennore-

Nellore pipeline

Ennore Nellore

Kakinada to Srikakulam further to Haldia &

Ennore to Nellore further to vijayawada

Ennore - Nellore

20

36

Status

Existing

Existing

Under

Implementatio n

Under

Implementatio n

Awarded

6 Vijaywada - Nellore Viajywada – Nellore 10-15 Proposed

18

Andhra Pradesh Gas Grid

19

Objective : to transform economy of

A.P. To gas based economy

APGDC has made demand assessment and feasibility studies across the state through M/s KPMG

Expression of interest (EOI) to PNGRB, on behalf of the GoAP , for following sections :

Kakinada Srikakulam

Ennore Nellore Pipeline

Nellore Vijaywada pipeline

APGDC has emerged as successful bidder and has been authorized by

PNGRB to lay pipeline from Kakinada to Srikakulam

DBPL

Nellor e

Renigunta

Srikakulam

V’nagaram

Anakapalli

R’mundry

V’wada

Tuni

Kakinada

Vizag

Guntur

Ongole

GAIL P/L

EWPL (RGTIL)

APGDC Authorized P/L

P/L under biding

EOI Proposed

Existing CNG locations

Proposed CNG Locations

Salient Details of KSPL

20

From Kakinada to Srikakulam

Total length : 301 km ( Main Line )

Sources :

Kakinada LNG

Gangavaram LNG

KG Basin ONGC/ RIL KG D-6 /

Ravva fields.

Demand Centres:

KG Basin, Kakinada SEZ, MBBVPL,

EWPL

Visakhapatnam, PCPIR

Vizyanagram, Bobbilee Ind. Area

Srikakulam

AUTHORIZATION BY PNGRB

21

Bid invited by PNGRB:

Letter of Intent issued :

20 th June, 2013

05 th June, 2014

Performance Bank Guarantee: Rs. 10.13 crore

16 th July, 2014

Letter of Authorization Issued :

Now Open for booking of capacity by Consumers/ Customers

22

S no.

1

Project Implementation schedule

Activity

Critical Path :

Sep-14 Dec-14 Mar-

15

3 6 9

Jun-15 Sep-15 Dec 15 Mar-16 Jun-16 Sep-16 Dec 16 Mar-17 Jun-17

12 15 18 21 24 27 30 33 36

Authorization by PNGRB

2 Detail Route Survey

3 ROU, Land & Permissions

4

5

6

7

8

9

Process Design & Proj.

Engg.

Ordering

Manufacturing &

Delivery

Contracting

Construction

Testing & Commissioning

Andhra Pradesh Gas Grid: An early Imperative

23

Karnool

Srikakulam

V’nagaram

Anakapalli

V’wada

R’mundry Tuni

Vizag

Kakinada

Guntur

Ongole

Anantpur Nellore

DBPL

Renigunta

Chitoor

GAIL P/L

EWPL (RGTIL)

APGDC Authorized P/L

P/L under biding

EOI Proposed

Gas Sources/ Inputs:

Gas Sources/ Inputs:

Existing: KG Basin

Proposed : Kakinada,

Gangavaram,

Krishnapatnam,

Ennore, DBPL

Gas Grid to Cover all 13 districts of A.P.

Approx. Length :

1600 km

Approx. Investment :

4200 Cr.

24

A. P. Gas Grid

4

5

S no.

1

2

3

6

Sector Approx.

Length (km)

Approx

Investment

(Rs. Cr)

800

Design Gas flow

(MMSCMD)

65-90

Gas

Transportati on Tariff

(Rs./

MMBTU)

4.5- 6 Kakinada -

Srikakulam

Kakinada –

Vijaywada

Vijaywada –

Nellore

Nellore - Ennore

Hindupur – Anantpur

– Karnool

Hindulpur -

Renigunta

300

250

(existing)

300

300

400

300

Existing

800

730

1000

800

10-15

15

36

10

10

5.6

7-10

8-11

10-12

8-10

25

Infrastructure Investment & Financial viability

Investment in Order of magnitude Cost : Rs. 4200 crore

Schedule :

Immediate : Kakinada – Srikakulam , Vijaywada –

Nellore , Ennore – Nellore

Next 3-5 years : Anantpur – Karnool- Renigunta

Linked with Gas availability, Landed cost

Transportation Cost : 5- 15 Rs./ MMBTU , Nominal compared to gas cost

Gas Distribution : CGD and CNG

26

Existing CGD :

Kakinada

Rajahmundry

Vijaywada

:

Proposed CGD and CNGS

Vizag

Viajayanagaram

Srikakulam

Guntur

Ongole

Nellore

Renigunta

DBPL

Nellor e

Renigunta

Srikakulam

V’nagaram

Anakapalli

R’mundry

V’wada

Tuni

Kakinada

Vizag

Guntur

Ongole

GAIL P/L

EWPL (RGTIL)

APGDC Authorized P/L

P/L under biding

EOI Proposed

Existing CNG locations

Proposed CNG Locations

27

Telengana: Gas Infrastructure

EWPL

MBVBPL

VSPL (LPG)

2 Major Gas grids passing through the state:

EWPL(RIL) , MBVBPL

(GSPL)

Ramgundam : Gas based

Fertlizer

City Gas Distribution and CNG stations

Currently at Hyderabad

Notified for bidding :

Nalgonda, Khamam,

Medak Rangareddy

28

Division of A.P. State : Value unlocking in Oil & Gas

Sector

Introduction of APGDC

Transmission & Distribution Infrastructure

Oil and Gas production infrastructure

LNG Import facilities

Refineries & LPG Pipelines

Oil & Gas Infrastructure : Key enabler of growth

Supports from State Govts and Central Govt.

Key drivers and Challenges

Proved reserve of Natural Gas: India

29

Production in 2013 :33.7 Billion Cu m equivalent to average of 92.3

MMSCMD

Reserve to production ratio of 40.2, vsa-vis world average of 55.1

Data Source : India Pet & NG statistics 2012-13

Production (BCM)

60

50

40

30

20

10

0

29,5 29,2 29,6 29,3 30,1 30,5

39,2

50,8

46,1

40,3

33,7

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Oil & Gas Production

30

Krishna Godavari Basin in Andhra Pradesh :

Oil and Gas

Discoveries

Onshore and Offshore

Production by Private and Govt Companies

More exploration in progress

DBPL

Srikakulam

V’nagaram

Anakapalli

R’mundry

V’wada

Tuni

Kakinada

Vizag

Guntur

Machlipatnam

Ongole

Nellore

Renigunta

Krishnapatnam

31

KG Basin : Exploration & Discoveries

More than 225 prospects have been probed by drilling of more than 557 exploratory wells.

Hydrocarbon accumulations have been proven in 75 of these prospects

Oil : 22

Gas : 53

Source : DGH

Oil & Gas discovery in KG Basin

32

Onshore

141 prospects have been probed by 375 exploratory wells by

ONGC,

11 oil & gas pools

31 gas pools have been discovered

Most of them are on production.

Offshore:

84 prospects have been probed by 182 exploratory wells .

Hydrocarbon accumulations have been proved in 33 :

11 oil & gas and 22 gas prospects

3 discovery by ONGC in the block KG-DWN-

98/2 within Plio-Pleistocene sandstone of

Godavari formation and

About 19 discoveries have been made by

Pvt./JV companies so far in NELP blocks

15 Dhirubhai discoveries by RIL in blocks KG-

DWN-98/3 and KG-OSN-2001/2,

3 discoveries by Cairn Energy Pty. Ltd. (CEIL) in block KG-DWN-98/2 within Mio-Pliocene,

1discovery by GSPC in block KG-OSN-

2001/3 within Lower Cretaceous).

33

Division of A.P. State : Value unlocking in Oil & Gas

Sector

Introduction of APGDC

Transmission & Distribution Infrastructure

Oil and Gas production infrastructure

LNG Import facilities

Refineries & LPG Pipelines

Oil & Gas Infrastructure : Key enabler of growth

Key drivers and Challenges

34

LNG Projects in East India

Digha

Paradip

Gangavaram

Kakinada

Krishnapatanam

Ennore

Karaikal

FSRU (In progress)

FSRU (Planned)

Land based LNG terminal

LNG Terminals planned in East Coast:

FSRU based :

Kakinada (2 nos.)

Krishnapatanam

Paradip

Digha

Karaikal

Land based terminal:

Gangavaram

Ennore

LNG Import in East Coast : Advantage

10

5

0

20

15

13.41

5.47

1,49

20.36

FOB Price &

Other

Taxes Transportation Total Cost

LNG un loaded on the West Coast & delivered in AP

18

16

14

12

10

4

2

0

8

6

14.00

2,03

0,40

15.68

FOB Price &

Other

Taxes Transportation Total Cost

LNG un loaded in East coast & delivered in AP

LNG Import on the East Coast

 In case the LNG Import facility is located on the East Coast in AP, then the delivered price will be lower at least by 4 US Dollar due to the avoidance of additional taxes and transportation charges

 Therefore, an LNG Import facility on the east coast can meet the demand shortfall economically when compared to the RLNG terminals on the West coast

 Further, towards open access of terminal, power plants can make high sea purchase, where tax component becomes nil, and no customs duty, thereby making more viable

36

Kakinada FSRU : Project Layout

Onshore

Receipt

Facility

Offshore

Pipeline

Fishing harbor

FSRU Basin

Break Water

K

D

W

P

Widening of

Channel

Existing Channel

FSRU : Configuration vis-à-vis Jetty ,

Jetty

FSRU

LNG Carrier

PLL LNG Terminal

38

 land based Liquified Natural Gas (LNG) Terminal at

Gangavaram Port

Petronet LNG Limited (PLL) signed a firm and binding term sheet with Gangavaram Port

Initial capacity of 5.0 MMTPA expandable to 10

MMTPA

MoEF Environmental Clearance ObtainedSchedule : 4-5

Years

PLL LNG Terminal

39

Close to Vizag Market- but no gas based Industry at present

Breakwater : does not exist for Isolated LNG berth

Availability : Dedicated LNG berth, if made outside harbour is operable only for

250 days.

Land availability : Adequate land not available. Area to be re-claimed from sea and hill cutting involved

Pipeline Connectivity : None

40

Division of A.P. State : Value unlocking in Oil & Gas

Sector

Introduction of APGDC

Transmission & Distribution Infrastructure

Oil and Gas production infrastructure

LNG Import facilities

Refineries & Product / LPG Pipelines

Oil & Gas Infrastructure : Key enabler of growth

Key drivers and Challenges

41

Refineries & Product/LPG Pipelines

Machlipatnam

Vizag Refinery (HPCL)

Capacity 8.3 MMTPA

Petrol, HSD, LPG, FO, lubricants

VSPL LPG Pipeline (GAIL : 600

Km, 1.4 MTPA

VVSPL Product P/L (HPCL)

Bottling Plant, POL Terminals

(OMCs) – Vizag, V’wada,

S’bad

Proposed :

Refinery & Petrochem :

Machlipatnam

PCPIR – Viazg - Kakinada

Existing Refinery

Planned Refinery & pet.chem

LPG/ Prduduct P/L Corridor

PCPIR

42

Division of A.P. State : Value unlocking in Oil & Gas

Sector

Introduction of APGDC

Transmission & Distribution Infrastructure

Oil and Gas production infrastructure

LNG Import facilities

Refineries & LPG Pipelines

Oil & Gas Infrastructure : Key enabler of growth

Key drivers and Challenges

43

Oil & Gas Infra : Key enabler to

Industries

Oil & Gas

Infrastruct ure

Fertilizer

Power

Petrochemicals

City Gas Distribution

CNG & Transportation

Ceramics, Glass

Other Industries

44

Oil & Gas Infra : Key enabler to

Industries

Should be efficient and cost effective

Available

Affordable

Environment friendly

Sustainable

To meet Govt Priorities

Oil & Gas

Infrastructu re : Key

Characteris tics

45

Division of A.P. State : Value unlocking in Oil & Gas

Sector

Introduction of APGDC

Transmission & Distribution Infrastructure

Oil and Gas production infrastructure

LNG Import facilities

Refineries & LPG Pipelines

Oil & Gas Infrastructure : Key enabler of growth

Key drivers and Challenges

Key Drivers for Oil & Gas Infrastructure

46

Industry and market Demands

Moderate and sustainable Crude and LNG price regime in

International Market

Private sector participation and FDI

Govt Facilitation:

Approvals

Land availability and acquisition ease

Taxation regime – Equitable to gas sector and long term growth oriented

Allocation / allotment of domestic gas to local / State Govt

Key Challenges

47

Higher prevailing LNG pricing : impediment to import

Power Plants : Power tariff capped- hence gas price has to be competitive

Huge initial Capital Investment

PNGRB Bidding in gas pipelines : Assymatry , unhealthy competition

48

Thank You

Download