Cleanup of Sewage Lakes: Case Studies in Jeddah and Riyadh • Background • Jeddah Sewage Lake – Drivers and project overview – Recommended plan – Clean-up Completion • Al-Nazeem Sewage Lake (Riyadh) – Project overview – Sediment management – Clean-up status • Project’s Benefits • Septage issues in nearly all Cities – ~50 % of population served by central collection systems – Country-wide issue that is independent of city size • No inventory available for sewage lakes • Jeddah – Only 6 percent of municipal planning area is currently sewered – ~140,000 m3/day hauled by tanker trucks • Riyadh – ~50 percent of population on central collection system • Wastewater pumped from cesspits and trucked to sewage lake – Air pollution from trucks – Significant energy investment in trucking • Background • Jeddah Sewage Lake – Drivers and project overview – Recommended plan – Clean-up Completion • Al-Nazeem Sewage Lake (Riyadh) – Project overview – Sediment management – Clean-up status • Project’s Benefits • Received 1500 to 2000 tanker trucks/day • Up to 50,000 m3/day of sewage • Lake grew to 2.8 km2 in surface area • May 2010 – Custodian of the Two Holy Mosques King Abdullah bin Abdulaziz issued a royal decree ordering that the hazardous Sewage Lake be emptied within 1 year – NWC took responsibility for the project July 25, 2010 • June 2010 – NWC hires Lake Contractor • July 2010 – Water evacuation efforts initiated – Planning consultant hired • October 2010 – Lake Evacuation completed • November 2010 to July 2011 – Sediment clean-up October 2, 2010 • Flood Management – Removal of the Sewage Lake Dam • Water Management – Evacuation of the Lake – Water Use and Agricultural Activities • Sediment Management – Characterization – Treatment/Management alternatives • • • • Regulatory Requirements Mitigation Needs Recommended Plan Plan Supervision 9 • Additional sediment depth sampling points – 125 measurements • Sediment depths – Main Lake – <0.5 m – West Lake - <1.2 m • Sediment volume – Main Lake • 300,670 m3 – West Lake • 84,724 m3 Total Volume = 385,000 m3 • 10 Characteristics of silty clay ~ 3-5 cm thick 11 • Main Lake Data – Data indicated meeting KSA criteria for agricultural use of sludge and US EPA “Exceptional Criteria” – A few sites with elevated petroleum hydrocarbons • Secondary Lake – Showed sediments also met KSA and EPA Criteria – Did show general contamination by petroleum hydrocarbons Open Water and Wetlands Ecosystem Planted Forest Upland Ecosystem • Continued drying of sediments – Use mineral material as a drying agent – Sample new areas as can be accessed • Mix thinner sediments in place – When sufficiently dry • Excavate thicker sediments – Spread in upper areas of the Main lake with thin deposits • Mix sediments that have been spread • Conduct “Site Release Sampling Plan” – Verification of site safety • Excavate sediment material littered with trash from former conveyance channel and dispose at a land fill Stratified Sediment Before Mixing Topsoil Condition After Mixing Organic Sediment 20 cm <50% Organic Matter ~0.75 g/cc Mixed Topsoil Tillage <25% Organic Matter ~1.0 g/cc Mineral Soil 10 cm <1% Organic Matter ~1.5 g/cc Subsoil Subsoil 16 30 cm Stratified Sediment Before Mixing Topsoil Condition After Mixing Tillage 17 • October 2010 – Lake Evacuation completed • November - December – Sediment drying and mixing activities – Additional sediment characterization • December-February 2011 – Completion of report documentation – Additional rainfall events partially refilling the lake to ~2m depth • March – August 2011 – Pumping to evaporation ponds – Continued sediment drying and mixing activities – Completed site release sampling 29 March 2011 • Lake evacuation – Delayed because of availability of pumps – Started in March 2011 – Completed in May 2011 • Sampling grid – Final grid included 205 cells – Thick vegetation along margins prevented sampling of infrequently flooded areas • Total Organic Carbon – low levels indicating sediments are stable • Metals – maximum values <12% of criteria • Microbiological – Fecal Coliform – Maximum value of 24 MPN/g versus standard of 1000 MPN/g – Parasite eggs – None detected • Petroleum Hydrocarbons – Only 3 sites showed some values exceeding levels of 2000 mg/kg for Total Petroleum Hydrocarbons – Additional mixing and re-sampling significantly reduced levels Cleanup plan was executed and site release sampling demonstrated site was safe for turnover back to the municipality • Background • Jeddah Sewage Lake – Drivers and project overview – Recommended plan – Clean-up Completion • Al-Nazeem Sewage Lake (Riyadh) – Project overview – Sediment management – Clean-up status • Project’s Benefits 23 • Lake has been used for approximately 20 years • Received – 1000 to 1500 trucks per day – ~20,000 to 30,000 m3/day • Mixture of Domestic and Industrial Waste – Domestic waste eliminated in January 2011 – Industrial waste eliminated in Mid-May 2011 24 • Lake area is ~3.5 km2 • When cleanup began in June/July 2011 – very little water remained • Cleanup focus – Sludge characterization – Sludge drying – Sludge treatment • Lake are divided into 4 zone with 39 separate lakes • Characterization focus – Metals – Microbiological indicators – Petroleum hydrocarbon fractions – Volatile and Semi-volatile compounds • Results – Zones 3 & 4 – no results exceed criteria – Zones 1 & 2 • Metals and hydrocarbon issues at several locations • Clean-up has involved excavation, mixing and combining with clean sand • Lake contractor is conducting verification sampling • Upon completion – site release sampling will be conducted by an independent laboratory • Background • Jeddah Sewage Lake – Drivers and project overview – Recommended plan – Clean-up Completion • Al-Nazeem Sewage Lake (Riyadh) – Project overview – Sediment management – Clean-up status • Project’s Benefits 30 • NWC Efforts have eliminated two long standing health hazards • Detailed investigations have led to environmentally sensitive solutions • Jeddah Lake project recognized with GLOBAL WATER INTELLIGENCE Reuse Project of the Year (reuse of sludge to enhance soils) Cleanup of Sewage Lakes: Case Studies in Jeddah and Riyadh