K-RIDE In September 2000, the Government of Karnataka (GoK) and Ministry of Railways (MoR) signed an MoU to set up a Joint Venture Company called “ Rail Infrastructure Development Company ( Karnataka) Limited – K-RIDE”. Objective : To expedite development and implementation of 4 identified Railway Projects in Karnataka viz: 1) Hubli – Ankola New Line 2) Hospet – Guntakal Doubling 3) Sholapur – Gadag Gauge Conversion 4) Hassan – Mangalore Gauge Conversion Nov’ 20, 2000 : Registered as a Public Limited Company under Companies Act,1956. Oct’ 22, 2001 : Government Order issued vide IDD Letter No. 10 NSW 2001. This SPV with financial participation by the MoR, GoK, FIs/Banks, etc. was set up to meet the objective of funding certain identified projects in Karnataka, particularly those with potential for attracting private investment. Nov’2002 : Shareholders’ Agreement Signed. Authorized Capital Rs. 5.00 Crores Share Capital Issued Rs. 5.00 Lakhs Share Application Money Held Rs. 4.95 Crores Pattern of Contribution GoK 26% Rs. 1.3 Crores MoR 26% Rs. 1.3 Crores iDeCK 48% Rs. 2.4 Crores Investment Done : Rs. 2.00 Crore in HMRDC Board of Directors Sl. No . Name Designation 1. Dr. Rajkumar Khatri, IAS Secretary to GoK, IDD & Chairman/K-RIDE 2. Mr. Niraj Kumar Executive Director/ Perspective Planning, Railway Board/MoR 3. Mr. B.N. Mohapatra Executive Director/ Finance – Expenditure - 1, Railway Board, MoR 4. Mr. Vinay Singh, IRSE Executive Director/ Works, Railway Board, MoR 5. Mr. Randeep D Deputy Secretary to GoK, FD (B & R) 6. Mr. Anil B. Shenoy CFO/CS, iDeCK Functional characteristics As per MOU, K-RIDE was to fund all the projects under its own name, mobilize equity from strategic investors and debt funds from financial institutions As per Government Order role of K-RIDE was changed from an implementing agency of the projects to that of a project Development Company. Each project to be developed separately as an independent SPV. Each project SPV would mobilize finances by a mix of equity/subordinate debt contributions from K-RIDE and strategic partners/ investors and debt from banks, financial institutions and the capital market. MoR and GoK might also participate directly in the equity. SPVs would enter into contractual agreements with MoR for construction, operations and maintenance. MoR and GoK might decide to give construction or maintenance or operations to another agency or to the SPV itself if it would result in improved performance or substantial savings. Mandate Given and Status of Projects: As per the Shareholders’ Agreement four on-going sanctioned projects of the Indian Railways were identified for implementation by K-RIDE. The present status is as under: Hubli – Ankola new line The line could not be taken up for development as approval from MoEF is still awaited. Sholapur – Gadag Gauge Conversion No SPV was formed to take up this project as it was not found viable enough. Instead GoK and MoR agreed to share the balance cost as on 01.04.2002. Project Commissioned in Dec’ 2008. Hassan – Mangalore Gauge Conversion A separate SPV was set up after CCEA clearance to complete this project. Project commissioned on 02.05.2006. Guntakal – Hospet Doubling Funding of this project was taken over by RVNL a PSU of Indian Railways. New Projects The Company has brought before BoD various possible projects that could be implemented under PPP mode/as a part of Business Plan. Kottur – Harihar New A traffic study was conducted and report submitted by M/s. A.F. Line Ferguson & Company suggesting high potential for development through alternate financing. However, the project could not be brought under the ambit of K-RIDE because Indian Railway did not agree to change the mode of financing from cost sharing to PPP. Mechanized Iron Ore The draft pre-feasibility report submitted by the Consultant M/s. loading terminal at BARSYL was incomplete and additional reports were solicited. Hospet The firm did not turn up. However, in the changed scenario, this was not required. Talaguppa - Honnavar GoK has funded a study by M/s. KRCL on the traffic Potential in the catchment area of the line. The final report is received and sent to IDD/ GoK for study of traffic potential and environmental impact of the line. iDeCK submitted Bankability report Sent to Railway Board Single Window Agency on 11.06.10 for clearance. Railway Board vide letter No. 2000/PL/88/12 dt. 28.06.10 advised GoK that this project has been entrusted to RVNL for examining implementation through PPP and suggested for association with RVNL for project development and participation. RVNL was approached in July 2010 on this issue and a meeting was held on 30.07.10. RVNL in their letter dt. 10.01.11 stated that fresh bankability report need to be made on behalf of GoK on commercial terms. No further development. Bagalkot – Kudachi New Line This is one of the sanctioned project of Railways. This is a greenfield project. Railways have advised that the Company can take up traffic validation and bankability studies to assess the feasibility to develop under PPP at its own cost. The Company has sought funds from the Shareholders (GoK & MoR) to meet the expenditure on these studies. iDeCK submitted Bankability report Sent to Railway Board Single Window Agency on 11.06.10 for clearance. Further Railway Board stated that this line has already been sanctioned and included in the Railway Budget 2010-11 for execution on 50:50 cost sharing basis with GoK with the approval of MoR. Hence, it would be appropriate to continue implementation on cost sharing basis. Bijapur – Shahabad New Line RVNL has entrusted traffic survey & bankability report to Deloitte Touche Tohamatsu India Pvt. Ltd, Gurgaon. Work is in progress. Future Role of K-RIDE Viewpoint Government of Karnataka GoK through G.O No. IDD 59 NSW 2009 dated 17.08.2009 empowered the Company to act as a Nodal Agency for development of Rail Infrastructure within the State which covers entire gamut of railway activities viz. Identification of new viable Railway Projects for execution through PPP/SPV Ministry of Railways As per the approval obtained from CCEA, KRIDE is mandated to develop, structure and Finance four identified projects on SPV route. This is also reiterated in S.H.A / MoA Specific approval of CCEA would be required for any new ventures through SPV route. Monitoring the progress of RoB’s / No mention in any of documents of a coRuB’s (55 in progress) duly coordinate role to be performed by the ordinating with RITES / BBMP/ BDA Company. and other State Agencies Liaisoning with DCs & SLAOs for land acquistition of ongoing Railway projects Act as a facilitator for drawal of funds Matter to be referred to MoR for released by GoK towards its share to concurrence for effecting modifications various Railway Projects and interact as per G.O. in the SHA. closely with SWR, SCR, SR & CR. MoR to be approached