Human Services Department CSES Replacement (CSESR) Project PCC Initiation An HSD initiative to replace the Child Support Enforcement System (CSES) December 18, 2013 Andy Vallejos, CSED Director & Executive Business Owner Sean Pearson, HSD CIO & Executive Technology Owner Carol Thomas-Gravel, HSD Deputy CIO Helen Yackel, HSD IT Project Manager CSES Replacement – PCC Initiation 2 Introduction Child Support Enforcement System Replacement (CSESR) Major System Replacement or Enhancement • High cost & large scope project • HSD involvement and vested interest (not only CSED) • Long-term project • Impacts State, Federal and Private Partners (30) • Planning Phase will determine technical solution CSES Replacement – PCC Initiation 3 Background … • CSES maintains more than 59,000 active cases with over $132.1 Million distributed annually in child support payments. • CSED provides assistance to over 100,000 NM and Navajo Nation children based on FY13 numbers. • States are Federally mandated to “have an automated system to operate it’s child support program efficiently, effectively, and economically.” OCSE supports states to improve their systems so that: • Caseworkers have more time to focus on complex cases • States can adhere to mandated timeframes to achieve successful outcomes • Case data is more reliable, secure, and readily available • Data exchange and information sharing is more comprehensive and useful • Reporting can be predictive, analytic and versatile • Customer service is improved and available at multiple points of contact CSES Replacement – PCC Initiation 4 Business Problem … Legacy CSES • 20-year old mainframe technology • Real-time client benefit information not available to staff and clients • Currently has minimal flexibility for changing business needs to support collections and support for NM children Solution must meet State and Federal requirements • National Human Services Interoperability Architecture (NHSIA) standards • OCSE, IRS and Disaster Recovery requirements • Flexibility to comply with changing regulations CSED mainframe hosting, maintenance, operations & storage costs continue to increase CSES Replacement – PCC Initiation 5 Project Objectives / Benefits Objectives: • Evaluate alternatives to select best technology solution for CSED business program needs. • Transition from mainframe to modern web-based technology • Spend state and federal funds wisely Benefits: • Timing allows prime opportunity to leverage current standard technology and architecture across HSD • Leverage resources • Provide one-stop service access for all HSD clients • Provide consistent data reporting across all HSD Divisions. CSES Replacement – PCC Initiation Initiation Activities… • Business Assessment Review (BAR) • Business Process (current and recommended) • Data Cleanup • Project Management Office (PMO) Procurement • RFP release in early-mid December 2013 • PMO start July 2014 • Lessons Learned • Other States and Recent Projects 6 CSES Replacement – PCC Initiation 7 Assumptions… • State and Federal Funding will be available and approved throughout the Project. • HSD staff with subject matter expertise will be available and assigned throughout the Project. • Procurements will identify experienced and qualified contractors for the project. • Cost savings and enhanced control of resources, system architecture, and tools are expected through one shared PMO for both CSES & MMIS Replacements. CSES Replacement – PCC Initiation 8 Project Risks… Risk Mitigation Funding Uncertainties Work closely with OCSE and State throughout project especially during planning phase for thorough & accurate analysis & feasibility of alternatives and cost benefits of options and recommended solution. Competing HSD and State Priorities Provide HSD Executive Steering Committee with necessary facts for governance decisions over HSD projects to confirm objectives are met and project is successful. Contracting Experienced and Qualified Vendors Contract with experienced & qualified vendors with track record of similar successful projects completed in recent past. Staff inexperience with large IT projects Contract experienced PMO qualified in Child Support to prepare and support state business & technical staff through such a project and conduct lessons learned and knowledge transfer sessions with experienced staff. CSES Replacement – PCC Initiation 9 CSES-R Project Governance Executive Sponsor Executive Technology Owner ITD / CIO Executive Steering Committee Executive Business Owner HSD Division Directors Strategic Leadership Team Tactical Technical Project Owner PMO Project Director Contracted PMO Program Project Owner Communication Owner Contractor Leads System Integrator Staff PMO Staff IV&V CSES Replacement – PCC Initiation 10 CSESR Estimated Timeline FY17 Funding Request PCC Planning 1st Half Integrator Starts PCC Implementation 8/11/15 3/11/14 2nd Half Start 11/20/13 1st Half 2nd Half Planning 7/1/14 - 7/1/16 7/1/16 1st Half 2nd Half 1st Half Testing Complete 9/21/18 4/21/17 2nd Half 1st Half 2nd Half Testing Phase 10/9/17 - 9/21/18 6/14/19 1st Half Waved Rollout 11/5/18 4/19/19 PCC Initiation PMO Starts 11/20/13 7/1/14 IAPD Approved IV& V Starts 8/4/15 3/8/16 PCC Close Pilot 11/2/18 Finish 6/14/19 CSES Replacement – PCC Initiation 11 Request… • HSD requesting PCC Approval to Initiate this Project • Funding certification will be requested at Planning PCC (March 2014) CSES Replacement – PCC Initiation Thank you… Questions? 12