8-Poynter-P2P Exchange

advertisement
BRIDGES ON THE MOVE
Sean Poynter, LEED-AP
Senior ABC Estimator
nothing too heavy, nothing too high
A LITTLE ABOUT SARENS…
nothing too heavy, nothing too high
BRIDGES ON THE MOVE…
•
•
•
•
FIRST BRIDGE MOVE
COMPLETED IN 1980
SINCE THEN WE
COMPLETE ON AVERAGE
70 BRIDGES EVERY YEAR
BRIDGE MOVES VARY
FROM CONCRETE DECK
ON STEEL, CONCRETE
DECK ON CONCRETE
GIRDERS, STEEL TRUSS
BRIDGES, ETC.
HEAVIEST BRIDGE
MOVED IN U.S.- SAM
WHITE BRIDGE IN LEHI,
UT 354 FEEL LONG AND
WEIGHING 4,200 KIPS
nothing too heavy, nothing too high
SELF-PROPELLED MODULAR
TRANSPORTERS (SPMT’s)
• USUALLY SEE 4 KINDS OF
SPMT’S USED IN THE US.
–
–
–
–
KAMAG (SARENS CHOICE)
GOLDHOFER
SCHEURLE
NICOLAS
nothing too heavy, nothing too high
nothing too heavy, nothing too high
WHAT THE DESIGNER
SHOULD KEEP IN MIND
• SPMTS (KAMAG) COME IN CONFIGURATIONS OF 4 AND 6
AXLES.
• EACH AXLE HAS A MAXIMUM CAPACITY OF ROUGHLY 79 KIPS
• MUST CONSIDER SUPPORT STRUCTURE WHEN DETERMINING
SPMT QUANTITY (WEIGHT).
• SPACE CONFINEMENTS…..DO THE SPMT’S WORK WITH THE
SPACE PROVIDED.
• GROUND BEARING CONCERNS.
nothing too heavy, nothing too high
SPMT
BENFITS INCLUDE:
• COUPLING SIDE BY
SIDE OR END ON END.
• FLEXIBLE STEERING.
• ACCURATE
ALIGNMENT.
• CENTRAL CONTROL
UNIT.
• DIAGONAL/CRAB
DRIVE FROM 0°TO
110°
• CIRCLE DRIVE
“CAROUSEL” AROUND
THE CENTER OF THE
CONFIGURATION.
nothing too heavy, nothing too high
WHY SPMT’s OR ABC
•
•
•
•
•
•
REDUCE USER COST
ALLOW BRIDGE ERECTOR
TO BUILD OFF SITE AND
OUT OF TRAFFIC.
MINIMIZE TRAFFIC
IMPACT.
FASTER COMPLETION
TIME.
INCLEMENT WEATHER
HAS LESS IMPACT ON
CONSTRUCTION
SCHEDULE.
GOOD INVESTMENT
• EVERY $1 SPENT ON
ABC THER IS A $5
SAVINGS ON USER
COSTS.
nothing too heavy, nothing too high
HOW SARENS MOVES BRIDGES
SUPPORT BEAMS
CROSS-BRACING
FOR LATERAL
SUPPORT
610mm SUPPORT SPOOLS
12-AXLE LINES
nothing too heavy, nothing too high
EXAMPLE PROJECTS:
• ABERDEEN AVENUE –
HAMILTON, ONTARIO
• SAM WHITE – LEHI, UT
• WELLESLEY –
WELLESLEY, MA
• TORRENCE AVENUE –
CHICAGO, IL
nothing too heavy, nothing too high
EXAMPLE PROJECTS
ABERDEEN AVENUE
•
•
•
•
•
•
LOCATION: HAMILTON,
ON
MAJOR THOROUGHFARE:
HIGHWAY 403.
JOB: REMOVE TWO (2)
EXISITING SIMPLE SPANS
AND REPLACE WITH TWO
(2) NEW SPANS.
WEIGHT: ~1,200 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 12 HOURS
nothing too heavy, nothing too high
EXAMPLE PROJECTS
SAM WHITE
•
•
•
•
•
•
•
LOCATION: LEHI, MA
MAJOR THOROUGHFARE:
I-15.
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~4,200 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 12 HOURS
EQUIPMENT: 96-AXLE
LINES KAMAG SPMT’s
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
ABUTMENT PREPARATION
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
ROLLING OUR FROM TEMPORARY
CONSTRUCTION ABUTMENTS
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
ROLLING OUT
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
USE OF CS250 FOR ADDITIONAL
JACKING CAPABILITIES
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
OPERATION OF THE SPMT’s
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
AXLES ROTATED TO CRAB
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
KEEPING THE DECK LEVEL ON
UN-LEVEL TERRAIN
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
PROJECT ENGINNER MONITORING
DEFLECTION
nothing too heavy, nothing too high
EXAMPLE PROJECTS
WELLESLY
•
•
•
•
•
•
•
LOCATION: WELLESLEY,
MA
MAJOR THOROUGHFARE:
STATE HIGHWAY 9
JOB: SET ONE (1) TWOSPAN BRIDGE SECTION.
WEIGHT: ~1,000 KIP
CONSTRUCTION: STEEL
GIRDER WITH CONCRETE
DECK.
TIMELINE: 6 HOURS
EQUIPMENT: 24-AXLE
LINES KAMAG SPMT’s
SETTING THE BRIDGE!
nothing too heavy, nothing too high
EXAMPLE PROJECTS
TORRENCE AVE.
•
•
•
•
•
•
•
LOCATION: CHICAGO,
IL
MAJOR
THOROUGHFARE:
CHICAGO COMMUTER
TRANSIT
JOB: SET ONE STEEL
TRUSS BRIDGE
WEIGHT: ~4,400 KIP
CONSTRUCTION:
STEEL.
TIMELINE: 6 HOURS
EQUIPMENT: 96-AXLE
LINES KAMAG SPMT’s
nothing too heavy, nothing too high
THE END
THANK YOU
nothing too heavy, nothing too high