Managerial Design Review Presentation (SD II)

advertisement
P09454: Design & Testing of
Centrifugal Pump Components
MSD II –Managerial Presentation
Spring 2009
Design Team:
 Rishitha Dias - ISE – Project Manager
 Kevin Klucher - ME – Lead Engineer
 John Hayles - ME
 Reme Meck - ME
 Ammar Jangbarwala - ME
Project Background:
 Project Family: Sustainable Technologies for the Global
Marketplace
 Project Track: Flow Visualization
 Sponsor: Dresser-Rand Corp.
 Faculty Guide: Dr. S. Day
Project Deliverable:
The goal of the project is to design, build, test and
deliver to KGCOE, a centrifugal pump system
for particle imaging velocimetry (PIV) studies,
which can be used both as a teaching tool for
undergraduate students as well as a research tool
for graduate and faculty researchers.
Customer Needs:
Primary Customers:
 Faculty & Graduate Researchers
 Undergraduate Instructors
Customer Needs / Target Specifications:

Generate Multiple Flows
~ 3 Unique Impeller Designs
~ 2 Unique Diffuser Designs

PIV Compatibility
>85% Transmissivity of Pump Components

Lab Teaching Tool
< 5 min Component Swap Time
> 0.45” Tool Clearance
Measureable Flow, Pressure & Power.
Parts must withstand a drop from 42”
Inherited Pump System:
Sensors &
Actuators
GUI
Close-up view of
Pump Housing &
Impeller
Tank
System Architecture:
Design Concept Summary
Impeller
&
Diffuser
Riser
Deliverable Status:
Impeller Designs
Previous Impeller Design:
New Impeller Designs:
P09454-102
P09454-103 P09454-104
P09454-105
P09454-106
Impeller Designs
Old
Impeller
Design:
Diffuser Designs
P09454-203
P09454-201
Pump Housing:
Project Status:
Budget:
 > 40% of the $6,500
budget remaining
Materials
Parts Manufacture
Shipping
Sensors
 Component Manufacture
& Materials costs are
dominant.
Misc
Remainder
Schedule: Product development Phase
Phase 1
Planning
Phase 2
Current Stage
of Design
Concept Development
Phase 3
System Level Design
Phase 4
MSD I
MSD II
Testing &
Refinement
Schedule:
Project is on Schedule
 Component Manufacture Complete
 Pump Assembly Complete
 Flow Testing Complete
 Documentation Complete
Performance:
 Characterize Various Flows
 5 Impellers & 2 Diffusers
available to generate curves
 Interchangeable
Components
 Measure Pressure, RPM &
Flow
 Built into GUI functionality
 Control Flow, RPM,
Pressure
 GUI Controls & Valves
 Assembly/Disassembly
averages 3.5 minutes
 PIV Compatible
 Clear Acrylic Components
Results:
Test Results
 As head rises, the flow
decreases, demonstrating basic
pump curve relationships.
 With the addition of a vaned
diffuser, the head generated is
increased versus flat ring
diffusers.
P09454-102
Pressure
(psi)
Vaned
Flow
(gpm)
P09454-102 Flat Plate
Pressure
Flow
(psi)
(gpm) Head (ft)
Head (ft)
3.5
8.4
8.077
2.6
7.5
6.000
3.6
8
8.308
2.7
7.2
6.231
4
7.8
9.231
2.8
7
6.462
5
7.2
11.538
3.6
6.3
8.308
6.8
5.4
15.692
4.2
5.5
9.692
8
4
18.462
4.7
4.6
10.846
8.8
2
20.308
5.8
2.5
13.385
9
1.5
20.769
6.2
1.2
14.308
9.1
1.25
21.000
6.2
1
14.308
9.25
0.75
21.346
6.4
0
14.769
P09454-103
Pressure
(psi)
Vaned
Flow
(gpm)
Head (ft)
3.5
8.5
8.077
2.5
7.4
5.769
3.5
8.1
8.077
2.8
7
6.462
4
7.9
9.231
3.1
6.7
7.154
4.8
7.25
11.077
4.2
5.3
9.692
5.65
6.7
13.038
4.9
4.5
11.308
6.6
5.4
15.231
5.3
3.7
12.231
7.75
3.6
17.885
5.8
2.7
13.385
9
2.1
20.769
6.2
1.7
14.308
9.2
1.4
21.231
6.4
1.2
14.769
9.75
0.75
22.500
6.5
0.7
15.000
P09454-103 Flat Plate
Pressure
Flow
(psi)
(gpm) Head (ft)
Discussion
 Pump provides 10x the options (impeller and diffuser) with




65% faster component switch time
Head generated is up to 60% greater than previous system
benchmarks
Flow rate is not up to maximum theoretical value of 22.3
gpm. However, ~ 25% increase over previous iteration
Diffuser made a large difference in the amount of head
generated, up to a 27% increase for the basic 102 impeller
New designs can be rapid prototyped and tested in the test
loop within several days based on standard dimensions used
for the components
Questions?
Download