Delay Attribution Guide April 2011 Changes

advertisement
Delay Attribution Guide
April 2013
Changes
Ana Maria Sanchez
Delay Attribution Board Secretariat support
New Codes
•2 new codes have been introduced to the April 2013 Delay Attribution Guide (DAG)
•JB – this is a replacement for the old QL code. A new incident is required for any
reactionary delays caused by a late running train as a result of a ‘P’ coded TSR.
•YQ - Where an operator’s service suffers delay as a result of overcrowding or station
overtime due to that train being of short-formation, and all reasonable attempts to
mitigate have been made, the delay should be attributed to the prime cause incident that
resulted in the train being of short-formation for that service.
CODE
CAUSE
JB
Reactionary Delay to ‘P’ coded TSR
YQ
Passenger overcrowding caused by a train being of shortformation
1st April 2013
ABBREVIATION
PLND TSR
SHRT FRMD
2
New JB code example
• JB Example
Train “A” runs 5 late, with a P-coded Temporary Speed Restriction being the largest cause of
delay. Train “B” is then regulated for “A” and is itself delayed.
The delay to Train “B” is explained as “YB” to Train A, but this cannot be allocated to the
original P-coded incident. A separate incident coded “JB” must therefore be created, to
account for the fact that the TSR has caused reactionary delay, and the delay to Train “B”
allocated there.
1st April 2013
3
New code YQ example
• YQ Definition – As per current but with the additional comment: “The delay should
be explained as a reaction to whichever train is initially responsible for the short
formation”.
• YQ Example
The diesel unit scheduled to form Train “A” encounters a brake defect and has to be taken
out of service.
To avoid cancelling the service, the operator detaches a unit from Train “B” (which is
booked to run with two attached units) and runs that in place of the failure.
This means that Train “B” (and possibly later workings) has to run with half its planned
passenger capacity. Delays caused by overcrowding on the short-formed Train “B” should
be allocated to an incident coded “MN” (to account for the original failure) and described
as “YQ” to Train “A”.
This principle would equally apply where, for example, Train “A” encountered an external
object on the line which damaged the train and the incident was established as
vandalism, the responsibility of Network Rail.
Delays subsequently caused by overcrowding on the short-formed Train “B” (and possibly
later workings) should be allocated to an incident coded XB and described as “YQ” to
Train “A”.
1st April 2013
4
4.25 Guidance where NFF
4.25 Guidance where no fault found (technical equipment) has been updated to
indicate that:
• If there is NO agreement that all reasonable efforts have been undertaken to investigate
the delay, then the NFF section is not to be used.
Where parties have agreed that all reasonable efforts to investigate have been done
then NFF is applied.
4.25.3.2 has been updated to include the words in the below paragraph in italics
• Where a train fails to read a piece of infrastructure based equipment but then reads
subsequent equipment and it cannot be determined if the fault is train based or
infrastructure based, it should be deemed unless otherwise proven, that the fault is with
the train based equipment. Where two or more separate trains fail to read the same
equipment in similar circumstance, it should be deemed that the fault is with the
infrastructure based equipment. This principle of two or more separate trains should
also be applied in the same way to two separate train-based radios.
1st April 2013
5
4.25.4
Delays caused by RETB system failure where no fault is found following
investigation, are considered to be the responsibility of the Operator.
The table in 4.25 has been amended also.
1st April 2013
6
Any Questions?
• We encourage you all to visit the DAB website at: www.delayattributionboard.co.uk
• There you will find the latest copies of the DAG, Freight user documents and competency
standards.
• The web site is updated regularly with up and coming events and activities that the DAB are
undertaking.
• You can use the website to obtain forms to make proposals for change to the DAG and PDAC as
well as to make requests for guidance.
• You can use the website to make suggestions on how to improve delay attribution on the whole.
• You can email the website, however, please do not use this facility to request specific attribution
guidance – the request for guidance process is to be followed in these cases.
• Feel free to email the DAB Secretariat on: admin@delayattributionboard.co.uk for clarification on
process in regard to delay attribution/disputes.
1st April 2013
7
Download