52 - ABB Group

advertisement

How to determine the right self healing grid strategy to achieve your budget and reliability goals: A look at three business models

© ABB Group

April 15, 2020 | Slide 1

Self healing grid strategies

Presenter

Cleber Angelo

Outdoor Medium Voltage

Global Product Manager

© ABB Group

April 15, 2020 | Slide 2

Self healing grid strategies

Agenda

 Challenges facing utilities today

 Situational analysis

 Improvement goals for self healing strategies

 Introduction to self-healing grid business models

 device level and /or peer to peer

 substation level

 centralized

 Detailed explanations of each business model including

 The type of investment required

 Expected reliability improvements

 Options to determine the best implementation strategy for your budget

 Summary

© ABB Group

April 15, 2020 | Slide 3

Self healing grid strategies

Challenges facing utilities today

 The industry is moving toward a deregulated, competitive environment requiring accurate information about system performance to ensure maintenance money are spent wisely and customer expectations are met

 CAIDI and SAIDI scores are under close scrutiny from government agencies

System reliability pertains to both sustained interruptions and momentary interruptions

Any interruption of greater than five minutes is generally considered a reliability issue in some countries.

 Limited capital budgets for continued improvements in grid reliability

© ABB Group

April 15, 2020 | Slide 4

Self healing grid strategies

Interruption definitions

 Momentary interruption – A single operation of an interrupting device that results in zero voltage.

 Momentary interruption event - An interruption of duration limited to the period required to restore service by an interrupting device. This must be completed within 5 minutes or any other period determined by regulation agencies.

 Sustained interruption – any interruption not classified as a momentary interruption

© ABB Group

April 15, 2020 | Slide 5

Self healing grid strategies

Improvement goals

 Implementing self healing or fault detection isolation and restoration

(FDIR) can help utilities:

 Improve CAIDI and SAIDI metrics by up to 33%

 Decrease restoration time to less than 30 seconds

 Reduce the cost of restoration

 Prevent lost revenues

Boost the utility’s reputation with customers, stockholders and government regulators

© ABB Group

April 15, 2020 | Slide 6

Self healing grid strategies

1

st

business model: Device level or peer-to-peer

 Device level and/or peer-to-peer

 A group of reclosers, load break switches, and feeder circuit breakers operate together to restore power in the most optimal manner

 Benefits

 Allows utilities to focus investments on feeders that experience the most outages

 Fast implementation

 Initial low capital investment

 Target solution appropriate for problem feeders

 Improves SAIDI and CAIDI scores

© ABB Group

April 15, 2020 | Slide 7

Self healing grid strategies

Requirements for device level (no communications required)

 System topology representation

Feeders with single restoration path, generally open “tie switch”

 Pre-fault system status

 Normal voltage measurements at each node and on both sides of “tie switch”

 Pre-fault system loading (capacity check for the restoration done by protection or planning engineers)

 Fault detection and isolation

 Coordinated protection devices using standard protection curves and predetermined reclosing intervals

 Load restoration

Loss of voltage detected on one side of “tie switch” and on source side of reclosers on faulted circuit

 Timing sequence initiated

 If loss of voltage is sustained for predetermined interval, other reclosers open if necessary to continue isolation and “tie switch” closes restoring power

Device level

Loop automation (no communications)

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

1 VT

1 VT

Sectionalizing

Recloser

52

GridShield

Sectionalizing

Recloser

52

GridShield

Midpoint

Recloser

52

GridShield

3

VT’s

1 VT

Midpoint

Recloser

52

GridShield

Tie Point

Recloser

52

GridShield

3

VT’s

1 VT

Device level

Loop automation (no communications)

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

1 VT

Sectionalizing

Recloser

52

GridShield

Fault

X

Sectionalizing

Recloser

52

GridShield

Midpoint

Recloser

52

GridShield

3

VT’s

1 VT

Midpoint

Recloser

52

GridShield

Tie Point

Recloser

52

GridShield

3

VT’s

1 VT 1 VT

Device level

Loop automation (no communications)

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

1 VT

Sectionalizing

Recloser

52

GridShield

Fault

X

Sectionalizing

Recloser

52

GridShield

Midpoint

Recloser

52

GridShield

3

VT’s

1 VT

Midpoint

Recloser

52

GridShield

Tie Point

Recloser

52

GridShield

3

VT’s

1 VT 1 VT

Device level

Loop automation (no communications)

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

1 VT

Sectionalizing

Recloser

52

GridShield

Fault

X

Sectionalizing

Recloser

52

GridShield

Midpoint

Recloser

52

GridShield

3

VT’s

1 VT

Midpoint

Recloser

52

GridShield

Tie Point

Recloser

52

GridShield

3

VT’s

1 VT 1 VT

Device level

Loop automation (no communications)

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

1 VT

Sectionalizing

Recloser

52

GridShield

Fault

X

Sectionalizing

Recloser

52

GridShield

Midpoint

Recloser

52

GridShield

3

VT’s

1 VT

Midpoint

Recloser

52

GridShield

Tie Point

Recloser

52

GridShield

3

VT’s

1 VT 1 VT

Device level

Loop automation (no communications)

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

1 VT

Sectionalizing

Recloser

52

GridShield

Fault

X

Sectionalizing

Recloser

52

GridShield

Midpoint

Recloser

52

GridShield

3

VT’s

1 VT

Midpoint

Recloser

52

GridShield

Tie Point

Recloser

52

GridShield

3

VT’s

1 VT 1 VT

Self healing grid strategies

Requirements for peer-to-peer (requires communications)

 System topology representation

Feeders with single restoration path, generally open “tie switch”

 Pre-fault system status

 Switch status (upstream and downstream information for devices)

 Pre-fault system loading (capacity check for the restoration)

 Fault detection

 Based on recloser lockout status and reclosing counter value change, or substation breaker trip signal

 Downstream node of the lockout switch is the fault location

 Fault isolation

 Downstream switch(es) of the fault location

 Load restoration

 Start from the downstream node of the isolation switches

Device level

Peer-to-Peer

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

Sectionalizing

Recloser

52

GridShield

Midpoint

Recloser

52

GridShield

IEC 61850 Communications

Sectionalizing

Recloser

Midpoint

Recloser

52

GridShield

52

GridShield

Tie Point

Recloser

52

GridShield

Device level

Peer-to-Peer

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

Sectionalizing

Recloser

52

GridShield

Fault

X

Midpoint

Recloser

52

GridShield

IEC 61850 Communications

Sectionalizing

Recloser

Midpoint

Recloser

52

GridShield

52

GridShield

Tie Point

Recloser

52

GridShield

Device level

Peer-to-Peer

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

Sectionalizing

Recloser

52

GridShield

Fault

X

Midpoint

Recloser

52

GridShield

IEC 61850 Communications

Sectionalizing

Recloser

Midpoint

Recloser

52

GridShield

52

GridShield

Tie Point

Recloser

52

GridShield

Device level

Peer-to-peer

Substation

Circuit

Breaker

Source 1

Substation

Circuit

Breaker

Source 2

Sectionalizing

Recloser

52

GridShield

Fault

X

Midpoint

Recloser

52

GridShield

IEC 61850 Communications

Sectionalizing

Recloser

Midpoint

Recloser

52

GridShield

52

GridShield

Tie Point

Recloser

52

GridShield

Summary device level

 Initial low capital investment

 Target solution appropriate for problem feeders

 Best fit for single restoration path circuits

 Improves SAIDI and CAIDI scores

 Loop schemes requires voltage sensors

 Peer-to-peer requires high speed communications –

IEC61850 is only standards based peer-to-peer solution available with open protocol environment

 Protection/coordination engineers manage logic

© ABB Group

April 15, 2020 | Slide 20

Self healing grid strategies

2nd business model: Substation level

 Substation level

 Coordinated control between groups of reclosers, load break switches, and substation circuit breakers within a substation and possibly with adjacent substations

 Benefits

 Avoids overloading of adjacent substations

 Reduces engineering support and recurring costs

 Target solution appropriate for problem feeders

 Supports future communications investments for applications such as asset health and volt/Var control

 Utilities realize benefits on groups of substations and the feeders they control

 Increases improvement in SAIDI and CAIDI scores

© ABB Group

April 15, 2020 | Slide 21

Self healing grid strategies

Introduction to substation level

 IEDs monitor and control switches

 Substation computer collects data from IEDs

 FDIR active logic resides on substation computer

 Automatic identification and isolation of a fault

 Automatic power restoration

 Generally faster response than control centerbased FDIR

© ABB Group

April 15, 2020 | Slide 22

Substation level

Substation based supervision

Substation

Circuit

Breaker

Source 1

Sectionalizing

Recloser

52

GridShield

Fault

X

Midpoint

Recloser

52

GridShield

Substation

Circuit

Breaker

Source 2

DNP/IEC Communications

Sectionalizing

Recloser

Midpoint

Recloser

52

GridShield

52

GridShield

Tie Point

Recloser

52

GridShield

Substation level

Substation based supervision

Substation level

Substation based supervision

Substation level

Substation computer-based FDIR active logic

Start

Obtain IED Information

Poll IED information

-Sw status (open, close, lockout)

-Sw recloser counter value

Sw Current …

No

Permanent Fault

Occurs ?

Yes

Generate Isolation Logic

Implement isolation control

Generate Restoration Logic

Implement restoration control

- Identify fault location

- Identify isolation switches

- Send isolation control command

- Confirm isolation actions

- Search alternative sources

- Obtain restoration solution

- Send restoration control

command

- Confirm restoration actions

© ABB Group

April 15, 2020 | Slide 26

Substation level

Substation computer-based FDIR requirements

 Dynamic system configuration update

 Represent system topology through system single line

 Automatically generates logic for isolation and restoration via single line model

 System incidence matrix is dynamically generated based on

 System connectivity model

 Real-time system switch status

 Depth-first search strategy (traces all paths available to determine the optimal solution to restore power)

 Fault restoration

 Load current-based capacity check (pre-fault load current)

 Single or multi-path restoration supported

 Multi-path restoration

– unserved loads picked up by multiple feeders

© ABB Group

April 15, 2020 | Slide 27

Summary Substation Level

 Initial low capital investment

 Target solution appropriate for problem feeders

 Can provide multiple paths for restoration, but generally best fit if all sources for restoration are from same substation

 Improves SAIDI and CAIDI scores

 Requires communications (lower baud, i.e., 9600) but possibly already in place

 Protection/coordination engineers must work with SCADA engineers.

 Should reduce customized logic in protection devices

 Utilities realize benefits on groups of substations and the feeders they control

© ABB Group

April 15, 2020 | Slide 28

Self healing grid strategies

3

rd

business model – Centralized control

 Centralized

 Coordinated control between groups of reclosers, load break switches, and high voltage circuit breakers across the distribution grid

 Benefits

 Takes advantage of load profile forecasting

 Allows utilities to take a proactive approach to power management

 Highest level of worker safety

 Supports smart grid initiatives

 Utilities realize benefits across the grid

 Maximum improvement in SAIDI and CAIDI scores

© ABB Group

April 15, 2020 | Slide 29

Self healing grid strategies

Introduction to centralized control

 IEDs monitor and control switches

 Substation computer collects IED data

 Substation computer acts as gateway – serves IED data to control center

SCADA and DMS

 Restoration Switching Analysis (RSA) run on DMS

 Load flow analysis as part of RSA, i.e., full network model used

 Automated or advisory FDIR

 Generally slower response than substation-based FDIR, but more comprehensive solution

© ABB Group

April 15, 2020 | Slide 30

Centralized control

Source 2

52

52

( GridShield

52

Source 1

52 52

GridShield

Fault

X 52

GridShield

52

GridShield

52

GridShield

52

GridShield

52

GridShield

52

GridShield

Source 4

52

52

GridShield

52

GridShield

52

GridShield

Source 3

52

Source 4

52

B

52

GridShield

52

GridShield

Centralized control

Centralized control

Centralized control

Centralized control

Summary centralized control level

© ABB Group

April 15, 2020 | Slide 36

 Requires SCADA applications, generally DMS with load flow and short circuit capability

 Target solution appropriate for all feeders

 Can provide multiple paths for restoration from multiple substations

 Improves SAIDI and CAIDI scores

 Requires communications (lower baud, i.e., 9600) but possibly already in place.

 Protection/coordination engineers must work with SCADA engineers

 Should reduce customized logic in protection devices

 Utilities realize benefits on groups of substations and the feeders they control

Summary

 Electric System performance and reliability are continually being scrutinized by customers and regulators

 Performance indices are becoming more difficult to meet

 Bottom line is that utilities need flexible and adaptable solutions to reduce outage restoration times

No single solution meets every customer’s needs

Device level solutions are generally “low cost”, easy to pilot and can be implemented by protection and control group

 Substation level solutions provide multi-feeder restoration paths, again are easy to pilot and can re-use existing equipment and communications infrastructure

 Centralized solutions offers most flexible and comprehensive restoration options.

© ABB Group

April 15, 2020 | Slide 37

Overview

Outdoor Portfolio

© ABB Group

April 15, 2020 | Slide 38

© ABB Group

April 15, 2020 | Slide 39

Download