© ABB Group
April 15, 2020 | Slide 1
Self healing grid strategies
Cleber Angelo
Outdoor Medium Voltage
Global Product Manager
© ABB Group
April 15, 2020 | Slide 2
Self healing grid strategies
Challenges facing utilities today
Situational analysis
Improvement goals for self healing strategies
Introduction to self-healing grid business models
device level and /or peer to peer
substation level
centralized
Detailed explanations of each business model including
The type of investment required
Expected reliability improvements
Options to determine the best implementation strategy for your budget
Summary
© ABB Group
April 15, 2020 | Slide 3
Self healing grid strategies
The industry is moving toward a deregulated, competitive environment requiring accurate information about system performance to ensure maintenance money are spent wisely and customer expectations are met
CAIDI and SAIDI scores are under close scrutiny from government agencies
System reliability pertains to both sustained interruptions and momentary interruptions
Any interruption of greater than five minutes is generally considered a reliability issue in some countries.
Limited capital budgets for continued improvements in grid reliability
© ABB Group
April 15, 2020 | Slide 4
Self healing grid strategies
Momentary interruption – A single operation of an interrupting device that results in zero voltage.
Momentary interruption event - An interruption of duration limited to the period required to restore service by an interrupting device. This must be completed within 5 minutes or any other period determined by regulation agencies.
Sustained interruption – any interruption not classified as a momentary interruption
© ABB Group
April 15, 2020 | Slide 5
Self healing grid strategies
Implementing self healing or fault detection isolation and restoration
(FDIR) can help utilities:
Improve CAIDI and SAIDI metrics by up to 33%
Decrease restoration time to less than 30 seconds
Reduce the cost of restoration
Prevent lost revenues
Boost the utility’s reputation with customers, stockholders and government regulators
© ABB Group
April 15, 2020 | Slide 6
Self healing grid strategies
st
Device level and/or peer-to-peer
A group of reclosers, load break switches, and feeder circuit breakers operate together to restore power in the most optimal manner
Benefits
Allows utilities to focus investments on feeders that experience the most outages
Fast implementation
Initial low capital investment
Target solution appropriate for problem feeders
Improves SAIDI and CAIDI scores
© ABB Group
April 15, 2020 | Slide 7
Self healing grid strategies
Requirements for device level (no communications required)
System topology representation
Feeders with single restoration path, generally open “tie switch”
Pre-fault system status
Normal voltage measurements at each node and on both sides of “tie switch”
Pre-fault system loading (capacity check for the restoration done by protection or planning engineers)
Fault detection and isolation
Coordinated protection devices using standard protection curves and predetermined reclosing intervals
Load restoration
Loss of voltage detected on one side of “tie switch” and on source side of reclosers on faulted circuit
Timing sequence initiated
If loss of voltage is sustained for predetermined interval, other reclosers open if necessary to continue isolation and “tie switch” closes restoring power
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
1 VT
1 VT
Sectionalizing
Recloser
52
GridShield
Sectionalizing
Recloser
52
GridShield
Midpoint
Recloser
52
GridShield
3
VT’s
1 VT
Midpoint
Recloser
52
GridShield
Tie Point
Recloser
52
GridShield
3
VT’s
1 VT
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
1 VT
Sectionalizing
Recloser
52
GridShield
Fault
X
Sectionalizing
Recloser
52
GridShield
Midpoint
Recloser
52
GridShield
3
VT’s
1 VT
Midpoint
Recloser
52
GridShield
Tie Point
Recloser
52
GridShield
3
VT’s
1 VT 1 VT
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
1 VT
Sectionalizing
Recloser
52
GridShield
Fault
X
Sectionalizing
Recloser
52
GridShield
Midpoint
Recloser
52
GridShield
3
VT’s
1 VT
Midpoint
Recloser
52
GridShield
Tie Point
Recloser
52
GridShield
3
VT’s
1 VT 1 VT
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
1 VT
Sectionalizing
Recloser
52
GridShield
Fault
X
Sectionalizing
Recloser
52
GridShield
Midpoint
Recloser
52
GridShield
3
VT’s
1 VT
Midpoint
Recloser
52
GridShield
Tie Point
Recloser
52
GridShield
3
VT’s
1 VT 1 VT
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
1 VT
Sectionalizing
Recloser
52
GridShield
Fault
X
Sectionalizing
Recloser
52
GridShield
Midpoint
Recloser
52
GridShield
3
VT’s
1 VT
Midpoint
Recloser
52
GridShield
Tie Point
Recloser
52
GridShield
3
VT’s
1 VT 1 VT
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
1 VT
Sectionalizing
Recloser
52
GridShield
Fault
X
Sectionalizing
Recloser
52
GridShield
Midpoint
Recloser
52
GridShield
3
VT’s
1 VT
Midpoint
Recloser
52
GridShield
Tie Point
Recloser
52
GridShield
3
VT’s
1 VT 1 VT
Self healing grid strategies
Requirements for peer-to-peer (requires communications)
System topology representation
Feeders with single restoration path, generally open “tie switch”
Pre-fault system status
Switch status (upstream and downstream information for devices)
Pre-fault system loading (capacity check for the restoration)
Fault detection
Based on recloser lockout status and reclosing counter value change, or substation breaker trip signal
Downstream node of the lockout switch is the fault location
Fault isolation
Downstream switch(es) of the fault location
Load restoration
Start from the downstream node of the isolation switches
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
Sectionalizing
Recloser
52
GridShield
Midpoint
Recloser
52
GridShield
IEC 61850 Communications
Sectionalizing
Recloser
Midpoint
Recloser
52
GridShield
52
GridShield
Tie Point
Recloser
52
GridShield
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
Sectionalizing
Recloser
52
GridShield
Fault
X
Midpoint
Recloser
52
GridShield
IEC 61850 Communications
Sectionalizing
Recloser
Midpoint
Recloser
52
GridShield
52
GridShield
Tie Point
Recloser
52
GridShield
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
Sectionalizing
Recloser
52
GridShield
Fault
X
Midpoint
Recloser
52
GridShield
IEC 61850 Communications
Sectionalizing
Recloser
Midpoint
Recloser
52
GridShield
52
GridShield
Tie Point
Recloser
52
GridShield
Device level
Substation
Circuit
Breaker
Source 1
Substation
Circuit
Breaker
Source 2
Sectionalizing
Recloser
52
GridShield
Fault
X
Midpoint
Recloser
52
GridShield
IEC 61850 Communications
Sectionalizing
Recloser
Midpoint
Recloser
52
GridShield
52
GridShield
Tie Point
Recloser
52
GridShield
Summary device level
Initial low capital investment
Target solution appropriate for problem feeders
Best fit for single restoration path circuits
Improves SAIDI and CAIDI scores
Loop schemes requires voltage sensors
Peer-to-peer requires high speed communications –
IEC61850 is only standards based peer-to-peer solution available with open protocol environment
Protection/coordination engineers manage logic
© ABB Group
April 15, 2020 | Slide 20
Self healing grid strategies
Substation level
Coordinated control between groups of reclosers, load break switches, and substation circuit breakers within a substation and possibly with adjacent substations
Benefits
Avoids overloading of adjacent substations
Reduces engineering support and recurring costs
Target solution appropriate for problem feeders
Supports future communications investments for applications such as asset health and volt/Var control
Utilities realize benefits on groups of substations and the feeders they control
Increases improvement in SAIDI and CAIDI scores
© ABB Group
April 15, 2020 | Slide 21
Self healing grid strategies
IEDs monitor and control switches
Substation computer collects data from IEDs
FDIR active logic resides on substation computer
Automatic identification and isolation of a fault
Automatic power restoration
Generally faster response than control centerbased FDIR
© ABB Group
April 15, 2020 | Slide 22
Substation level
Substation
Circuit
Breaker
Source 1
Sectionalizing
Recloser
52
GridShield
Fault
X
Midpoint
Recloser
52
GridShield
Substation
Circuit
Breaker
Source 2
DNP/IEC Communications
Sectionalizing
Recloser
Midpoint
Recloser
52
GridShield
52
GridShield
Tie Point
Recloser
52
GridShield
Substation level
Substation level
Substation level
Start
Obtain IED Information
Poll IED information
-Sw status (open, close, lockout)
-Sw recloser counter value
Sw Current …
No
Permanent Fault
Occurs ?
Yes
Generate Isolation Logic
Implement isolation control
Generate Restoration Logic
Implement restoration control
- Identify fault location
- Identify isolation switches
- Send isolation control command
- Confirm isolation actions
- Search alternative sources
- Obtain restoration solution
- Send restoration control
command
- Confirm restoration actions
© ABB Group
April 15, 2020 | Slide 26
Substation level
Dynamic system configuration update
Represent system topology through system single line
Automatically generates logic for isolation and restoration via single line model
System incidence matrix is dynamically generated based on
System connectivity model
Real-time system switch status
Depth-first search strategy (traces all paths available to determine the optimal solution to restore power)
Fault restoration
Load current-based capacity check (pre-fault load current)
Single or multi-path restoration supported
Multi-path restoration
– unserved loads picked up by multiple feeders
© ABB Group
April 15, 2020 | Slide 27
Summary Substation Level
Initial low capital investment
Target solution appropriate for problem feeders
Can provide multiple paths for restoration, but generally best fit if all sources for restoration are from same substation
Improves SAIDI and CAIDI scores
Requires communications (lower baud, i.e., 9600) but possibly already in place
Protection/coordination engineers must work with SCADA engineers.
Should reduce customized logic in protection devices
Utilities realize benefits on groups of substations and the feeders they control
© ABB Group
April 15, 2020 | Slide 28
Self healing grid strategies
rd
Centralized
Coordinated control between groups of reclosers, load break switches, and high voltage circuit breakers across the distribution grid
Benefits
Takes advantage of load profile forecasting
Allows utilities to take a proactive approach to power management
Highest level of worker safety
Supports smart grid initiatives
Utilities realize benefits across the grid
Maximum improvement in SAIDI and CAIDI scores
© ABB Group
April 15, 2020 | Slide 29
Self healing grid strategies
IEDs monitor and control switches
Substation computer collects IED data
Substation computer acts as gateway – serves IED data to control center
SCADA and DMS
Restoration Switching Analysis (RSA) run on DMS
Load flow analysis as part of RSA, i.e., full network model used
Automated or advisory FDIR
Generally slower response than substation-based FDIR, but more comprehensive solution
© ABB Group
April 15, 2020 | Slide 30
Centralized control
Source 2
52
52
( GridShield
52
Source 1
52 52
GridShield
Fault
X 52
GridShield
52
GridShield
52
GridShield
52
GridShield
52
GridShield
52
GridShield
Source 4
52
52
GridShield
52
GridShield
52
GridShield
Source 3
52
Source 4
52
B
52
GridShield
52
GridShield
Centralized control
Centralized control
Centralized control
Centralized control
Summary centralized control level
© ABB Group
April 15, 2020 | Slide 36
Requires SCADA applications, generally DMS with load flow and short circuit capability
Target solution appropriate for all feeders
Can provide multiple paths for restoration from multiple substations
Improves SAIDI and CAIDI scores
Requires communications (lower baud, i.e., 9600) but possibly already in place.
Protection/coordination engineers must work with SCADA engineers
Should reduce customized logic in protection devices
Utilities realize benefits on groups of substations and the feeders they control
Summary
Electric System performance and reliability are continually being scrutinized by customers and regulators
Performance indices are becoming more difficult to meet
Bottom line is that utilities need flexible and adaptable solutions to reduce outage restoration times
No single solution meets every customer’s needs
Device level solutions are generally “low cost”, easy to pilot and can be implemented by protection and control group
Substation level solutions provide multi-feeder restoration paths, again are easy to pilot and can re-use existing equipment and communications infrastructure
Centralized solutions offers most flexible and comprehensive restoration options.
© ABB Group
April 15, 2020 | Slide 37
© ABB Group
April 15, 2020 | Slide 38
© ABB Group
April 15, 2020 | Slide 39