Update on East West Interconnector

advertisement

East West Interconnector Background

• Security Of Supply

• Promote Competition in The Electricity Sector

• Accommodate Growth Of Renewable Energy

• Reduce Dependence on Imported Fuels

• Downward Pressure on Price

• Achievement of National and European

Objectives

East West Interconnector Background

Key Strategic Project

• Priority Interconnector Project - DG TREN January 2007

‘Critical National Strategic Importance..’ – NDP 2007-2013

CER to arrange for design of competition for construction of a

500MW interconnector at earliest possible date ( 2012 or earlier)

Upon completion, I/C to be owned and operated by EirGrid

Work on selection of sub sea route and sites and associated grid reinforcement to proceed in parallel with selection of developer process

•Irish Land Cable Route – Approx 45km

•Connects To UK Grid At Deeside 400kv Substation

•Welsh Land Cable Route – Approx 30km

Marine Survey

Recent Milestones

Government Approval / Contract Award

Planning Permission in Britain

Planning Approval Granted in Ireland

European Investment Bank funding secured

Granted Foreshore Licence in Britain

Commencement of Works in Wales

EU Grant secured

Full Notice to Proceed

March 2009

Sep 2009

Sep 2009

Sep 2009

Oct 2009

Nov 2009

March 2010

March 2010

North Ocean 102 Cable Laying Vessel

ABB HVC Karlskrona

High level timeline of activities

RA’s SEM

Regional

Integration

Consultation

Review of EU and UK legal requirements (including telecoms)

Customer workshop

Auction Platform workshop

Explicit auction system tender

Mods Approval from

RAs

Start Customer

Registration

Customer workshop

AS Contract Agreed

Registration in BETTA/SEM

EWIC commercially operational

Q4

2009

Q1

2010

Q2

2010

Final Notice to

Proceed

Q3

2010

Q4

2010

Q1

2011

Mods submitted to Mods panel

Q2

2011

Q3

2011

Q4

2011

RA Approval access rules

Go-live explicit

System

Customer Training

Q1

2012

Q2

2012

April 2012

Release

Q3

2012

Regulatory interface

Q4

2012

Auction Process

An auction platform will be procured over the next few months

Coordination underway with Moyle so as to offer 1 platform but 2 separate auctions

Explicit Auctions will be held on annual, monthly, weekly and daily basis

Implicit auctions being considered for within day auctions

Secondary trading will be facilitated

The auctions and the rules of the interconnector will be compliant with the Congestion Management

Guidelines

• UIOLI and UIOSI will be operated

Facts & Figures

500MW Continuous Rated Power

Overload Capacity Up To 550MW

DC Cable Voltage

±

200kV

Reactive Power Capability

Total Estimated Losses At Rated Power –

30MW

Completion Date Q3 2012

End of Presentation

Questions?

EirGrid website: www.eirgrid.com

Project website: www.interconnector.ie

Planning websit www.eirgrideastwestinterconnector.ie

ABB HVDC: www.abb.com/hvdc