CEZ-Mereni_Muller_Mamula_EN

How Smart metering pilot project
lost illusions and ideas
or
nothing is just
18. 4. 2012 Špindlerův Mlýn
BLACK WHITE!
and
composed and performed by members of the project
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
Reasons for massive roll out in Czech republic
 2009/72/EC directive
 development in field of energy metering
 expected introduction of smart grids
 specific (different) position of Czech republic
 cca 5 millions of customers
 RIPPLE CONTROL, under which is managed approx 1/3 of retail
points of consumption (represents approx ½ of energy supplied in
low tariff, retail)
 yearly billing of retail customers
 continuously / remote red are all customers connected to extra high
voltage, high voltage and some connected to low voltage (over 63
amps)
 deployment of smart metering is a big challenge for CEZ, for our
customers and also for our suppliers > that is why we run a pilot project
prior to decision about massive roll-out
Therefore we escaped from basic scenario ( 80% till 2020 )
Reasons for massive roll out in Italy
 What we thought about their reasons
 30% of losses
 black-out
 limited DMS
 cash flow not fully controlled
time for Illario
AMM Drivers in Italy or “Why to become smart”
Ilario Tito & Laura Panella
Europe and Americas Business Development
Infrastructure and Network Division
Spindleruv Mlyn, 18th April 2012
Uso:
Outline
 Enel Group Smart Metering Experience
 Main Drivers of Enel Cost / Benefit Analysis
 Unpredicted Benefits
6
pubblico
Uso:
pubblico
Enel Network Management and Innovation
Heading towards efficiency, the Enel experience as DSO
world reference
2.000 HV/MV substations
remotely controlled (100%)
> 100.000 MV/LV substations
remotely controlled (more than
25%)
Improved Neutral Grounding
System
Automatic fault clearing
procedures on 65% of
MV Lines
 Satellite
>
37
mln meters in Italy
13 mln new generation
meters being deployed in
Spain
340 Mln/ year remote readings
15 mln/ year remote operations
97,4% operations correctly
performed (2010)
Smart Grid/
Network
Automation
Asset
Management
mapping of
network assets
 Database of network events
(power outage notification,
fault detection)
 Optimization of network
investments based on a
risk analysis
 Optimization of network
maintenance
Process
reengineering
Automatic
Meter
Solutions
Work Force
Management
 5.200
Enel teams connected
via GPRS with GPS localization
 ENEL cartographic on board
 Mobile applications for all
Field Operations
State-of-the-art technologies and process optimization to
deliver value to our stakeholders and partners
6
Uso:
pubblico
Enel Operational Excellence: the Italian case
A 10 year path towards becoming the European benchmark
Opex
(€/customer)
• Network remote
control and
automation
• Automated Metering
Management
• Automated Work
Force Management
• Asset Management
• Process reengineering
2011 (42 min, 48
€/Customer)
Quality of service
(minutes interruption/year
Opex reduction: - 40 %
Quality of service: +68 %
4
Uso:
Outline
 Enel Group Smart Metering Experience
 Main Drivers of Enel Cost / Benefit Analysis
 Unpredicted Benefits
9
pubblico
Smart Metering Deployment
Uso:
pubblico
Key success factors
Massive roll out
• all Enel’s LV customers in parallel/ uniform
lots in order to anticipate savings
Value creation
Speed of
• 20% yearly substitution
implementation
International
procurement
• global OEM manufacturing + Enel onsite teams
for production planning&control to ensure high
volumes of production / high quality
International
standards
• open technologies and solutions
Crossover
technologies
•
Customer
engagement
• Strong communication effort
Continuous
innovation
•
Mesh for SM + mobile communication for
concentrators
implementation of the most up to date
solutions
Uso:
pubblico
Smart Meter Project Cost Benefit Analysis
Project’s key indicators
• Number of Meters installed
33 Mln units
» Monophase
90%
» Poliphase
10%
100% advanced new-generation meters
• Roll-out
5 Years
• Cumulated CAPEX*
• Yearly Running Costs **
• Yearly Savings **
2,1 Bln €
67,3 Mln €
450 Mln €
• Meter Average Life
PBP
*
**
15 years
5 years
Capex for 31 Mln meters by 2006; Concentrator/ meter @ 1/80
at the end of roll-out period
11
Uso:
pubblico
Costs - Investment
Breakdown per point of delivery
73%
Smart Meters and Data
Concentrators
20%
Installation
7%
System
Technology (field + system)  approx. 80% of S.Metering CAPEX
12
Uso:
Smart Meter Project Cost Benefit
Analysis Costs and Investment Estimate
Drivers
Smart
meter
Concentrator/
TLC
• Capex
assume:
single
phasepolyphase
Smart
Meter
+
installation;
• Opex
include:
metering, account
admin., invoicing,
personnel
for
metering superv.*
• Investment costs
assume:
concentrator +
installation.
• Operation costs
include data
transfer of data
through PLC,
communication to
the concentrator
pubblico
Average non-discounted data
PM/HW/
SW
Total
costs
• Capex include: AMM
customizing,
interfaces with
legacy,servers +
Project Management
costs;
• Variable costs
include
hardware+software
maintenance
Investment
(€/SM)
~ 68
Yearly
operation
costs
(€/SM)
~ 2,2
*Operation costs due to remote reading failure and meter failure taken into account as
reduction of savings
13
Uso:
Impact on Business
Yearly savings and quality of service
pubblico
Low savings
High savings
Field Operations and Logistics:
•
Manual Meter replacement due to failure reduced by 70% with respect to
dynamic meters
•
Contract parameter modification reduced by 95%*, Quality parameter
Deadline greatly improved, reaching 99,7% by end of deployment
•
Manual activation and deactivation reduced by 99%
•
On-field readings reduced by 99%
•
Logistic costs reduced by 80% due to standardization of models (only three)
Energy Losses:
•
Energy balance for each transformer and antitamper signals allow for a more
accurate fraud contrast, increasing success rate by up to 70%
Credit Control and Management:
•
Remote deactivation of bad payers prohibits customers from continuing illicit
consumption and increasing their own debt
•
Monthly readings improve correctness of energy balance and optimize cash
flows
*Only modification for single-poly phase switching and system failure (less than 2%)
Strong operating benefit delivering
Savings approx.15 € per point of delivery and 2€ yearly
opex per p.o.d.
14
Included
in model
pubblico
Not included in model
Uso:
Smart Meter Project Cost Benefit Analysis
Yearly savings (end-of-installation)
Decrease of
Operation costs*
• Meter reading
• Remote connection/
disconnection
• Avoided
Drivers
•
•
•
•
Estimated
yearly
Savings
(€/SM/year)
meter
replacement
(no
meter change for
contractual
changes,
lower
meter failure)
Lower
switching
costs
Avoided dispatch to
false failure
Lower
metering
maintenance
+
recalibration costs
Lower
fraud
verification costs
~10
Purchasing &
Logistics
• Lower
purchasing cost,
warehousing
cost,
meter
overhauling
logistic..
Lower Energy
Losses
• Revenue
Protection/ lower
commercial
losses:
lower
losses
for
tampering/ fraud,
thefts and reading
errors
• Lower
meter
energy
consumption
(technical losses)
Customer
Service, Billing
• New
•
•
•
•
~2
tariffs/better
pricing
methodology
Improved
customer
profiling and load
administration
Receivables
optimization
More
precise
billing and lower
customer
service-related
costs
Lower back-office
activities
for
errors/ litigations
~2
~1
*
Do not include smart grid benefit (i.e.: faster outage identification, lower network
losses, because it may require network technology upgrade)
15
Uso:
pubblico
Smart Meter Project Cost Benefit Analysis
NPV of a Central Europe 2 Mln customers utility
21%
100%
40%
53%
26%
10%
3%
17%
14%
34%
36%
14%
Savings Logistic/ Energy Cust. Savings Meter/
Install.
HW/
Total
from
purchas. Losses Service
concentr. costs SW/ PM capex
operations gains
&
costs
Billing
NPV
Total
NPV
opex @100% of @80% of
savings
savings
IRR
16%
IRR
11%
… enough to become Smart?
16
Uso:
Outline
 Enel Group Smart Metering Experience
 Main Drivers of Enel Cost / Benefit Analysis
 Unpredicted Benefits
17
pubblico
Uso:
Effective Billing & Trader Switching
pubblico
Heading towards greater operational efficiency
Automated Billing
Readings
Free Market
Billing
7 mil. clients handled
System capacity of >1
mil customers/day
Regulated Market
Billing
Readings
 95% of bills
dispatched within the
first 8 days of each
month
 Strong improvement of
credit indicators
 Billing is not
estimated, making
invoices reliable and
true to authentic levels
of consumption
25 mil. clients handled
Trader Switching
 ~270k Monthly
operations
 99,9 % Carried out in the
first week of
following month
 Regulatory framework allows customers to
freely chose retailer, while real time Trader
switching allows for a greater perception of
benefits.
In an increasingly open market, the number of operations is
bound to grow. Becoming Smart is vital to stay in business
18
Uso:
ilario.tito@enel.com
laura.panella@enel.com
International Business Development
Infrastructures and Networks Division
Enel Distribuzione Spa
Via Ombrone,2
00198 ROMA
THANK YOU FOR YOUR ATTENTION
19
pubblico
Reasons for massive roll out in Sweden
 What we thought about their reasons
 market liberalization
 monthly readings
 easier switching
 easier life for field workforce – remote readings and management
time for Baard
Sweden, 100% Rolled-out by 2009
• Regulation stipulated: Every household should be invoiced based
on actual consumption, every Month, instead of a predicted
consumption.
• The above meant that 5,4 Million meters (Less than 64 Amps)
where to be replaced by “smart meters” that remotely could be
read for meter values once a Month.
• The responsible part of exchanging the meters where the Grid
company (Cost/Benefit analysis positive as a result of charging
the consumer over a period of years)
• Approx. 175 Grid companies changed their meters during a 6 year
period
Swedish conditions for Smart Meters
• Three major Utilities represented more than 52% of all meters
• Different ways of managing roll-outs
• Vattenfall; Did two projects with approx. 500K meters in each
• Fortum; Did one large project with all meters (the supplier ran into
financial difficulties and went bankrupt during the latter part of the
project)
• E.ON; Spread the total amount of meters in 7 different projects with
various amount of meters in each
• Several “small utilities” cooperated in purchasing groups to get
volumes
• Several “municipality owned” grid companies did it them selves
• Difficulties in national
Swedish effect
• All Swedish meters are “smart” from September 2009
• Consumption of energy has risen with 25% in the last 10 years
• At the same time the yearly average price of a kWh has gone up
with 229%
• Smart Metering has increased the easiness of switching
• Smart Metering has improved the knowledge of consumers and
have increased the awareness
• Smart Meters have, however, not created efficiency as expected
Maingate role in the Swedish market?
• I have myself been a project director of two major roll-out projects
in Sweden (Total of 500K meters)
• Maingate have been involved in more than 50 Projects where
54% of the total amount of meters are involved
• Maingate is currently working with more than 300 Utilities to plan
roll outs, execute roll outs, after market approach and in the
demand side management side of Smart Meters and Smart Grid
technology
Key learning points
• Smart metering roll out is a logistic project!
• Planning is key to success!
• Leave it to experts, but stay in control
• Source and purchase not only components but functions/services
• Make your solution future proof
• Make sure that supplier contracts are back to back (when
feasible)
• Choose your partners, not out of price but out of experience
• Be prepared for surprises, there will be at least one every week!
ČR with HDO
SMART METERING
SMART GRID
Enhanced grid
management
Higher quality and
broaden offer of services
More information
for customers
Active customer’s
participation, savings
Starting position for countries where are not implemented
„load controll“ and/or „demand side management“ systems
What makes Czech republic different ? Ripple control
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
Pre-project tasks in a wood age time of paper boxes
 ČEZ Distribuce distribution grid in ČR


3,5 mil. retail customer metering points
55 000 DTS (distribution transformer station 35 kV/400V)


33 000 MPs in 3 main different areas
800 DTS with some different device setup and technologies
 AMM project MP and DTS – 3x transformer station 110/35kV areas
 Pre-project tasks






Location selection
Area size definition
Topology analyzes
MP lists
Sub-areas def.
Data source mgmt.
Zdroj obrázku: www.gpsvizualizer.com
Pre-project tasks in a wood age time of paper boxes
 DTS technology condition check
 DTS split to groups by level of necessary DTS modification for AMM
 Design and drawings for necessary changes on DTS
 Electro installations companies got design set for each DTS (DTS check docs,
maps,lists)
 Selected MP condition check
 MP technical condition check
 Ripple control wiring check (HDO, clocks)
 MP group ripple control setups
 Specification of each DTS AMM box
 Complex DTS switch ON/OFF plan
Pre-project tasks in an ancient time of paper boxes
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
The role of Schrack Technik Ltd
in AMM project
Cast: Mgr. Martin SVOBODA
Schrack - producer of DTS cases
Schrack – producer of DTS cases
Plán Integrovaného Odpojování
PIO (Integrated Plan of switching Off)
genesis of the file
file size initialy 1,5MB, finally 15,5MB
Production of cases
size selected automaticaly
Production of cases
list of equipment in the case, so called „black
list“ (just because of color)
Production of cases
time line (production, assembly, deployment)
- planned time for assembly was 5 weeks
- production itself took 2 days
- some of the cases were produced within 3 days !!
Production of cases
goal was to produce unified cases
Production of cases
options of cases – 46 variations
- 494 pcs of AMM case MAXIPOL
- 50 pcs of BPL repeater in MINIPOL case
- 26 pcs of E GPRS cases MINIPOL
... again cases ...
... another cases ...
Documentation
Scheme of AIL0 equipped case
Surprise – a case
Unlimited support of Schrack
Modifications of infrastructure for Smart Grids
„Wake up from dreams to tough reality“
18. 4. 2012 Špindlerův Mlýn
Milan Kloubec, AZ Elektrostav
Overall information
Within the WPP AMM project the AMM technology was installed in almost
1000 distribution substations
Furthermore was installed:
•
over 100 couplers of the PLC MV technology;
•
tens of repeaters of the BPL technology;
•
and many others.
3-membered team → installation of AMM technology into one substation/day
Installation of the AMM technology includes:
•
creation of interface in substation
•
installation and start up of the AMM technology
Necessary power outage for installation → limitation of consumers
Power outage is necessary to plan at least 2 months in advance!!
Precise coordination → alpha and omega of AMM technology installations…
Coordination: what is connected with installation of
AMM technology?
„Decalogue of AMM“
Coordination of several outages and teams during one day:
1. Logistics of power outages…
2. Preparation for the day „D“ (material, possible complications etc.)
3. Verification of the right phase rotation before power outage
4. Acceptance of worksite by AZ Elektrostav before installation
5. Drawing of circuit diagram in Microstation in field
6. Creation of detailed photo documentation before and after installation
7. Functionality verification of the installed technology with the control
8. Acceptance of worksite by ČEZ Distribuční služby after installation
9. Issuance of works inspector‘s report
10. Preparation and signing of completion certificates and complete
documentation with ČEZ Měření and ČEZ Distribuce
Electrical distributor with a Smart Grids Module
Dimensions of Smart
Grids Module [mm]:
•
750x500
•
750x750
•
1000x500
•
1000x750
Out of 800 modules
only 7 modules were
greater than 1000x750
→ less than 1%
Distribution substation
with a Smart Grids Module
Dimensions of Smart
Grids Module [mm]:
•
750x500
•
750x750
•
1000x500
•
1000x750
In the picture is AMM
technology for
double distribution
substation
Lack of space in double
distribution substation
Distribution substation
with a Smart Grids Module:
KO_1174
KO_1174 became
best measured
distribution
substation in
Central Europe:
Smart Meter PLC MV
Quality Meter E-GPRS
MEG
2 sets of convertors
Inside temp. sensor
Outside temp. sensor
Distribution substation
with a Smart Grids Module:
advantages
All-concrete
compact
substations are a
phenomenon of
these days:
• minimum visual
interference
External boxes:
• on the edge of the
Construction Law
• complications
with other laws
Repeaters installation of the BPL technology
High-speed transmission→ high frequency → shorter range
Smart Region Vrchlabí:
•
task to install about 30 repeaters in a plastic box
•
indicated as routine installations → each box „4 screws and a
cord“ 
•
drawn ambicious plan „2-membered team will install in 3 days“
i.e. 10 boxes a day…
Repeaters installation Ad hoc:
1. do we have project documentation ???
2. is settlement of property rights carried out ???
3. is power outage for installation planned???
•
I will rather stop asking…
Repeaters installation of the BPL technology
1) Installation of box
with repeater
2) Repeater installation
on the door (outside)
3) Repeater installation
inside the stand
4) Repeater installation
on the cover
5) Repeater installation
on the door (inside)
Installations carried
out without outages!!
i.e. without consumer limitations
Installation of smart meters at the CEZ Headquarters
„Able to measure – able to economize“:
•
Installation of the AMM technology for power
circuits of each individual floor
•
Measured data transmission and its display in
foyer → on-line consumption monitoring
Black-out simulation at the CEZ Headquarters:
outcomes
CEZ News: CEZ Headquarters in Prague became best measured
office building in Central Europe…
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
What we have shown you in previous years
Meter
Statistics are boring, but it has something (sometimes) 
More then 31
600 AMM meters (12 500 1p; 19 100 3p)
More then 800 DTS installation
3 and 2 half areas with AMM meters installations
 (Pardubice, Jeřmanice, Vrchlabí, Hradec Králové a Chrudim)
51 cities and 125 city districts with AMM technologies
72 kg archived printed documents about DTS installation (inspection reports, diagrams)
38 GB archived electronics documents from DTS (photos, protocols, logs)
3 man days just for scanning and archiving documents above
32 version of project plan from 2009 to 2010 and additional 17 versions to summer 2011
Usage statistics of our LABoratory for AMM project by companies
Company
ČME
HP
ADD
Ness
Landis+Gyr
Schrack
ZPA
ICOM
Corinex
Powel
Transtech
Goerlitz
ModemTec
Enel
Teco
ČEZ ICT
Applied meters
ČEZ, a.s.
Kvados
Tectra
ČVUT inova centrum
Elektroprivreda Serbia
ZERA
T-Systems
Endeza
Circutor
Microelectronica
EMH
Amount
2714:06
1052:25
895:15
830:08
491:30
485:45
474:10
202:00
145:25
130:00
67:25
55:15
48:30
21:00
13:30
13:20
12:00
8:30
8:00
7:20
6:00
3:00
2:30
2:20
2:00
2:00
1:00
1:00
63
Usage statistics of our LAB for AMM project by companies
Live LAB operation from 22.9.2010
253 operation days and 7695 hours, ie. 30 men-hours per one operation day
117 persons in LAB
 and our LAB record holders 
Name
26Společnost
firem
Time spent
Šmída Oldřich
ČME
1022:54
Dostálek Martin
ČME
616:30
Horáček David
Hájek Karel
Bayerle Petr
Ness
ČME
HP
373:38
363:59
343:35
Poubová Marta
Ness
303:00
Novák Tomáš
ADD
257:15
Salbot Michal
Schrack
231:15
ADD
225:30
Kapala Adam
HP
216:00
Moraru Andrei
ADD
211:00
HP
205:30
Skříčil Jan
Vašák Petr
64
As we have become famous beyond the borders (project + Czech) OR Foreign visitors in the Lab
82 visitors
from 26 companies
from 13 states
Country
City
Company
Bosna a Hercegovina
Banja Luka
Mikroelektronika
Italy
Canada
Moldova
Germany
Germany
Germany
Norway
Austria
Slovakia
Slovakia
Serbia
Spain
Spain
Sweden
USA, California
Milano, Rome
Vancouver
Kišiněv
Frankfurt n.M.
Königswinter
Wittenburg
Trondheim
Vídeň
Bratislava
Prešov
Bělehrad
Barcelona
Madrid
Ostersund
Palo Alto
Enel
Corinex
ADD
T-Systems
ZERA
EMH
Powel
Goerlitz
Schrack
Applied meters
EPS
Circutor
Endeza
Powel
HP
65
Planed vs. installed ratio of AMM meters
7000
6549
6125
6385
6000
5658
6039
5658
5000
4448
4273
4000
3632
3370
3161
3000
2791
2000
1620
1302
únor 12
leden 12
prosinec 11
listopad 11
říjen 11
září 11
červenec 11
červen 11
květen 11
srpen 11
Skutečně instalováno v měsíci
157
0
103
0
15
0
duben 12
178
0
0
březen 12
1140
1052
1000
Plánovaný HMG instalací IEM
66
Project schedules versions (monthly)
Project schedule versions was established 49! just in 1,5 year.
Because project was hit by:


economic recession in 2009, cutting
production and lack of components in 2011
Tsunami 2011 in Japan and chip production
interruption


Detected component defects and SW bugs
Good managers improvements ideas and
cost cutting requests
67
GOOD TIME FOR BRAZILIAN COFFEE
or
No, it is a
cafe ?
break
Geological layers of Giant (Krkonose) mountians
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
Readout structure
Histogram DTS readouts
DTS – installation and clean up



Case installation on DTS (5 technology) optional devices included

Wiring check, base functional check

Data connectivity check
DTS two level monitoring

SiteScope monitor DCU/Router and SIM card

Readout monitoring DTS summary meter

DTS trouble solving based by supplied MP volume
In field DTS check in case of DTS system troubles

Device check and wiring
 -> HW replacement
 -> Device re-setup

GPRS signal strength measurement
 -> Basic antenna replacement with higher gain version

PLC transmission power check
Communication effectivity



Data center readout job

Readout data set definition

Communication spec. setup, timeouts tuning

Readout priority based by different data sets, repetition tuning
DCU setup

Tasks queue management

Timeouts tuning

Crosstalk's special DCU setup in high level crosstalk's areas
PLC tuning

Low voltage networks grouping
 By density of MP, by type of topology
-> Spread flatten network with high MP density
-> long straight lines with low MP density

Tuning of PLC routing

Overhead on PLC communication level – optimalization
Field clean up

Diagnostic

Measurement of PLC signal level by each phase (all DTS are 3p)

LV nodes identification with high level crosstalks

GIS support for field place identification and LV grid topology

Technology specific analyzing tools
 DCU <-> meter sniffers
 Signal, SNR, etc. PLC analyzers


Functional device infield check
Field tasks

LV phase signal

Device replacement (meters, PLC modules, etc.)

Repeaters

GPRS meters

Filters against noise in PLC Cenelec A band
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
A co to zkusit rychleji, milý Bobe?
Communication technology IS bottleneck, especially for SG solution
Smart metering
BANDWIDTH & RELIABILITY
 Overnight reading of register (daily consumption)
 Overnight reading of load profile
PLC
1-4 kbps
noise sensitive
 Collisions zones – many DTSs in the same area (crosstalks)
 Limited numbers of MPs behind DTS
 On-line readings and data processing
 On-line execution of commands
BPL
5-40 Mbps
much more
noise sensitive
Smart grid
77
Agenda
BPL in SMARTGRID and AMI = Working Reality
of one communication platform
Basic parameters and features
BPL AMI Architecture in CEZ
Field Test Results
Risks and future possibilities
www.corinex.com
78
G.Hn Markets Focus
Purpose
Promote G.hn Technology and Ensure
Interoperability of Products Based on the G.hn Spec
Board of Directors
Board of Directors
Contributions
Certification &
Interoperability
Smart Grid
Utilities
Home Grid is the commercial companion group for G.hn
Worldwide industry representation
Corinex is Chair of the AMI Working Group for this impressive
new standard with mandate to:
1.
Develop Clean Tech product standards for devices with
G.hn technology. These standards will be used to access
Clean Tech properties of the technology;
2.
Lab testing and certification process to verify those
properties;
3.
Establish methods of calculation of the carbon offsets for
devices having Clean Tech properties
©2009 All Rights Reserved
Promoters
Contributors
UNH
7
9
79
Features: Full Corinex BPL Architecture Benefits
Corinex BPL Solution Supports All Needs of AMI and SmartGrid
Applications
■
■
■
■
■
■
■
■
■
■
■
■
■
Simple meter interoperability
Integrated ripple control system – broadcasting in all cluster within a
minute
Proven communication performance (AMI, SmartGrid, EV)
The industry lowest cost/performance ratio compared to all communication
technologies
Unmatched performance (up to 40Mbps) and reliability
Self adapt and auto-healing mechanism
Interoperable solution for multi-meter vendor support
Real-time event reporting and meter profile reading
Leadership in open standard (G.hn) solution
Security encryption support
Advanced data integrity and validation (in meter and HES)
Real-time demand load management (within seconds)
Remote firmware upgrade (open for future needs)
80
www.corinex.com
Meter Interoperability
Corinex Technology is Meter Agnostic and has four components.
Solution Components
Net
Perform
L&G meter
Grid
Apps
ZPA meter
Smart
Grid
Connect
Grid
Intel
Net
Admin
Mikroelektronik
a meter
www.corinex.com
Corinex Metering software in
Smart Communication Module
Corinex Wide Band PLC Gateway
81
Integrated Ripple Control System
Corinex- BPL specific features
■
■
■
■
■
■
The module has a broadcast address
The module is able to accept a broadcast
(e.g. a telegram for everybody- only right
ones react)
Reaction for telegram if address part is OK
is: change of tariff/output, change of virtual
output change of limiter, change of
disconnector, etc.
Similar actions as above enabled in TOU
Above actions are enabled by unicast and
single address command
A possibility to operate so called “virtual
relay- e.g. home automation” (nice to have)
82
BPL Network Architecture in CEZ deployment
The BPL network on low voltage is connected to the CEZ 3G WAN for
backhaul to central servers
Collection
Engine
234 Meters In TU_0848
DB
Access Router
WAN
Corinex + Landis BPL Meter in
MDU Buildings
Transformer
Station Via
3G Router
Corinex + Landis BPL Meter in
Residential Houses
Transformer
Station Via
3G Router
Corinex AMI LV Network In TU_0848
Reading Conditions:
• Time Out 20s per read
• Max 5 Retry per Read
CEZ has measured the performance of meter reading to ensure it meets/exceeds
the requirements for their smart grid applications
www.corinex.com
83
Broadband Implementation available for MDM
The deployment in Vrchlabí was chosen to trial the broadband
technology for smart grid applications
Example -Trafo TU 848
AMM Topology
CEZ is piloting new broadband over powerline technology to the meter, which
achieved high bandwidth and reliability for smart grid applications
84
www.corinex.com
84
Pardubice Deployment
Pardubice 2012
PA_0619
Deployment without Repeaters – Q1 2012
Average meter reading success rate of 99.705%
without repeaters
Deployment Approach in 3 steps:
PA_0637
PA_0087
 1108 single phase meters
 112 three phase meters
 1220 total meters
1. Planning and Hardware Installation - Completed
by CEZ without assistance from Corinex.
2. Network Optimization - Accomplished by
Corinex in less than 2 days:
• Only 1.6% meters not reporting
• Consider this step closed and will return
after the CEZ 60% test
3. Clean up and 100% connectivity – Connected
the remaining 1-2% in February
BPL has superior connectivity and performance to any other PLC
85
deployments
www.corinex.com
85
Deployment without repeaters Pardubice Substations
Red_Substation
3 Corinex Gateways at the
Substation
● 0 Repeater Gateways in the field
● 352 meters
● The most remote meter:
390 m
●
Yellow_Substation
3 Corinex Gateways at the
Substation
● 0 Repeater Gateways in the field
● 451 meters
● The most remote meter:
470 m
●
Blue_Substation
3 Corinex Gateways at the
Substation
● 0 Repeater Gateways in the field
● 348 meters
● The most remote meter:
310 m
●
Approx. 500 m
All 1151 meters have connectivity with the
NOC!
BPL to the meter: known and unknown
PROVEN
■ BPL technology has an unparalleled reading performance in areas where tested
■ Easy to deploy
■ Cost comparable with narrow band solution in absolute terms, and hundreds
times lower in price per Mb
■ Technology is supported by strongest silicon vendors (TI, Marvell, Intel).
■ In various market segments: EV, SmartGrid, to the meter.
OPEN
■ It is a new technology. One needs to better understand what it cannot do.
■ Solution can be further enhanced, benefiting from the speed and reliability of the
technology – it is not fully exploited yet.
■ To lower the risk it would be beneficial to expand number of meter vendors
adopting the technology (currently five in Europe)
■ To be able to scale up to 1 million meters + it would be good to have a
concentrator – it is on the roadmap and will be introduced in September 2012. It
will enable solution for up to 30 mil meters.
■ Vulnerable to the limited knowledge about its actual cost and performance
88
www.corinex.com
Thank You
Corinex Communications Corp.
#1200 – 570 Granville Street
Vancouver BC, Canada
V6C 3P1
Tel: 604 - 692 - 0520
Fax: 604 - 694 - 0061
E-mail: saleslead@corinex.com
www.corinex.com
Corinex Communications a.s.
Ambrova 6821 01 Bratislava 37
Slovak Republic,
Europe
Tel.: +421 - 2 - 59 - 212 - 000
Fax: +421 - 2 - 59 - 212 - 222
E-mail: allglobal@corinex.com
Corinex Communications Corp.
B-2910, Jiahe Huaqiang Building,
3006 Shennan RD,
Futian District, Shenzhen,
China
Postal Code: 518031
Tel: +86-755-8367 7675
89
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
Customers complain about prices, but are not interested
in 
Smart technology is not necessary for initial survey of our payments. All you need are your bills. Smart
meter shows consumption progress over time. You need additional technology to gain detailed info
about structure of your consumption
Hot water
Natural gas
Electricity
Natural gas
PRAHA
VRCHLABÍ
Cold water
District heating
Cold water
Hot water
What we can offer and what is customer able to utilise ?
Customer’s engagement (behavior of an average flat / house)
flat fee 5 € / month
Electric owen
0,14 € / kWh off peak
120 kWh / yr
0,25 € / kWh peak
0,80
Microwave owen
50 kWh
0,70
Freezer
300 kWh
0,60
Dishwasher
250 kWh
Washing machine
Ironing
120 kWh
70 kWh
Lights
Real consumption
Type diagram
0,50
0,40
250 kWh
0,30
TV, audio
500 kWh
0,20
PC
400 kWh
0,10
0,00
Σ ~ 2.000 kWh
Σ ~ 10.000 Kč = 400 € per year
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
38
Celkem (N=1300)
What „random“ customers say ?
(N=499)
49
47
41
46
49
41
muž (N=702)
39
(N=270)
žena (N=598)
38
(N=229)
52
44
41
35
(N=137)
42
52
 22% of customers
already monitor
their
consumption.
18-35 let (N=391)
51
from them
let (N=479)
36-5083%
use43manually red data
to calculate
real consumption,
rest
(N=207)
56
40
31
to have rough idea about expected yearly consumption.
36
(N=155)
45 through smart
50 meter
51 (if
 38% declares interest
in detail consumption
data
it is for free). Only 5%
from them would check their consumption more
40
bez maturity (N=455)
(N=181)
50
45
41
often than monthly.
38%
changes to 14%
if detailed (N=199)
data are offered
as a paid
36
(N=550)
SŠ s maturitou
44
49 service
51
(avg. willingness to pay is approx 1,50 EUR)
nad 50 let (N=430)
40
VŠ nebo VOŠ (N=295)
Celkem (N=1300)
0
muž (N=702)
žena (N=598)
25
(N=119)
38
(N=499)
50 % 75 100
0
za čtvrtletí
(tzn. 4 údaje za(N=270)
rok)
39
za dny (tzn. 365 údajů za rok)
38
(N=229)
55
44
49
47
41
25
50 % 75
100
za měsíce
46 (tzn. 12 údajů
49za rok) 41
za hodiny (tzn. 8760 údajů za rok)
52
44
41
18-35
70%
and yearly
let prefers
(N=391) flat pre-payments
35
(N=137)bill /clearing).
42
Only 24% would prefer payment based on real consumption.
36-50 let (N=479)
43
(N=207)
20
52
56
51
40
31
 36% of respondents guess they would be able to save approx 12% of the
just
because of available
detailed(N=155)
data about 45
their consumption
nad bill
50 let
(N=430)
36
50
51
 When two-tariff offered, 46% respondents would adopt and move some
40
(N=181) but requires
50
45
41
consumption form peak
to off-peak hours,
16% incentives
bez maturity (N=455)
SŠ s maturitou (N=550)
36
(N=199)
44
49
51
What customers with AMM tarif say different ?
 Customers have adopted AMM tariff because of prospective
 savings (89%) or
 to be able to on-line monitor their consumption (74%).
 23% of those who accepted guess they will save 16% of their bills.
 Customer’s willingness to decrease their living comfort is very limited –
see next slide
 Final saving was minor – customers were able to move only 1,5% of their
consumption for peak to off-peak
60% wanted to monitor their consumption on web portal,
in reality only 39% monitored, avg. once per 10 days.
Co What customers say ?
PŘESOUVÁ AKTIVITY**
NEPŘESOUVÁ AKTIVITY*
vaření, pečení
51
praní prádla v pračce
žehlení
44
mytí nádobí v automatické myčce
sledování TV, DVD,HiFi 82
59
využívání PC, notebooku
ohřev / filtrace bazénu, sauna
klimatizace
zalévání zahrady čerpadlem
sušení prádla v sušičce
svícení 78
mrazení a chlazení
75
přitápění přímotopy
ohřev vody v průtokovém ohřívači
ohřev vody na kávu, čaj
60
100
0
75
37
23
68
47
46
14
13
28
10
6
14
50
25 % 25
8
6
16
3
11
19
17
1
3
8
5
31
50
0
25
50
75% 75
100
100
Smart office building
Average consumption of one floor in CEZ headquarters (working day [kW] )
 There are 6 floors, there are approx 100 – 150 employees on each
 We do read „office consumption“ – lights, PCs, cafe machines, freezers, ...)
 We will read heating and aircon consumption as well
 There have been a competition in March (energy savings against January)
35,00
30,00
25,00
20,00
XI
XII
15,00
I
10,00
II
5,00
1/2 III
0,00
0
1
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
více než 100
5 NP
95 - 100
90 - 95
4 NP
85 - 90
80 - 85
3 NP
75 - 80
70 - 75
2 NP
65 - 70
60 - 65
20
55 - 60
25
50 - 55
AVG
19,87%
Median 17,50%
45 - 50
40 - 45
35 - 40
30 - 35
25 - 30
20 - 25
30
15 - 20
10 - 15
5 - 10
méně než 5
Competition (bets)
25,00
20,00
15,00
15
10,00
5,00
10
0,00
6 NP
5
0
1 300
6NP
5NP
1 200
4NP
3NP
1 100
2NP
Celá budova
1 000
900
 An „office consumption“
represents less then 8% of
overall building consumption
 10% savings in „office
consumption“ represents yearly
financial savings approx
200.000 Kč
 Each floor’s ability to save
electricity strictly depends on
layout and available daylight
800
700
600
500
400
300
 Higher potential is expected
in heating and air condition
200
100
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
9:00
8:00
7:00
6:00
5:00
4:00
3:00
2:00
1:00
0
0:00
Spotřeba pater [kW]
Smart office – real potential of savings
”Without a human perspective on M2M technology we will never
experience the full potential of M2M.”
“When the infrastructure is in place there are no boundaries of how
it can be utilized. Both at home and at work.”
“We now talk about M2H, machines servicing human and not at
least machines servicing society in large.”
Baard Eilertsen, CEO at Maingate
What do these have in common?
Obsolete apps replaced by digital one´s and
then turned into services
And the electrical meter have gone from
products to Value added services online
E.ON give its customers 100KOLL
Through innovative technology the
customers of the energy company E.ON
are able to control their energy
consumption via smart phones. It is only
when you are both aware and have
access to real knowledge about your
energy consumption that you can make
active decisions and lower both your cost
and impact on the environment, says
Anders Olsson, Deputy CEO at E.ON.
Bright future from financial perpsective:
Business case is negative under current conditions
OPTIONS OF IMPLEMENTATION
FLAT
5 yrs of preparation
FUNCTIONALITY
n yrs of
implementation
INVESTMENT
UNIFICATION
2009/72/ES
SELECTION
BASE CASE
UPGRADE
-
+
-
+
-
+
-
+
-
-
+
-
+
-
+
-
+
-
+
-
+
-
+
-
+
-
+
-
+










+
5
6.
8.
3.
5.
7.
2.
4.
-52,8 6.
1.
+
7
+
10
RIZIKO NEKOMPATIBILITY
POSSIBLE UPGRADE
WRIT OFF OLD TECHNOLOGY
CAPACITY INTENSIVE
-
BENEFITs
SCENARIOS FO IMPLEMENTATION
12 yrs of operation
REDUCED
CURENTLY THE BEST CASE
6.
Bright future from financial perpsective:
Why the case is negative




High investment into AMM technology
High investment into ICT support
Change of customers behavior is limited
High risks (e.g. communication)
 Whole costs will be transfered on the customer in tariff
Bright future from financial perpsective:
We need to change conditions
Black & white content
Intro
1
Reasons for massive roll-out:
2
•
in Czech Republic
•
in sunny Italy
•
in cold Sweden
Project preparation – „one man show“ (in clogs)
3
What have we installed, what pain have we enjoyed
4
How much, how many ... ?
5
Of course, complications !
6
What medicaments are available ?
7
How bright future can we expect ?
8
Conclusions
9
Our recomendation – do not roll out AMM now





smart metergin technology is curently too expensive
many of functions required by EU is supported by ripple control
current market conditions do not stipulate for savings
customers are not interested in savings
customers do not want to change
How many companies were (is) involved ?
How many people were (is) involved ?
Petr Bayerle, Eva Beková, Otto Berger, Pavel Berka, Jiří Bittman, Tomáš Bláha, Aleš Boubelík, Dalibor Bradáč,
Tomáš Burdan, Erika Caithamlová, Michal Cerina, Lubor Čáslavka, Kamil Čermák, Vladimíra Černá, Matouš
Červenka, Jiří Čírtek, Martin Dostálek, Enno Dreier, Jiří Surý, Jiří Dvořák, Luděk Fajgara, Václav Fencl,
František Fiala, Miloš Fojt, Jan Hájek, Karel Hájek, Jan Hájek, Jaroslav Hanyš, Josef Havel, Jan Hejčl, Tomáš
Hejl, Jaroslav Hendrych, Leoš Holanec, Jiří Holub, Ivan Holub, David Horáček, František Horváth, Lukáš
Hořký, Jan Hovorka, Vladimír Hrabě, Gabriela Pátková, Stanislav Hutňan, Rostislav Charvát, Jaroslav
Chlumský, Igor Chrapčiak, Luboš Jelínek, Jaroslav Jirman,
František Kácl, Jan Kanta, Adam Kapala, Petr Karel, Petr Kašpárek, Milan Kloubec, Roman Kloubec, Peter
Kollarčík, Jitka Kortánová, Karel Kotrba, Petr Kozák, Jiří Krajčovič, Zdeněk, Krčmář, Tomáš Krejča, Václav
Krejčí, Marek Kubenka, Michal Kučera, Jiří Kudrnáč, Milan Kuchařík, Radomír Labuť, Radek Lamich, Petr Lisý,
Jiří Luňáček, Jana Luňáčková, Pavel Mahdal, Ferdinand Maneth, Jiří Masorsič, František Mátl, Martina
Matoušková, Jiří Mentlík, Petr Mervart, Martin Michek, Bohuslav Mikeska, Aleš Mikula, Miroslav Mohelsky,
Roman Musil, Hana Něničková, Milan Neubert, Tomáš Nevídal, Lubomír Novák, Jindřich Oupický, Libor
Palivec, Martin Pavlas, Petr Pokorný, Michael Polák, Marta Poubová, Milan Prokop, Radko Purm, Kamil Rajs,
Roman Rezek, Pavlína Rezková, Fredrik Rossen, Michal Salbot, Filip Secký, Radim Sedláček, Petr
Schneeberger, Jiří Schoř, Jan Skříčil, Jiří Smékal, Karel Sobotka, Jakub Souček, Josef Stavárek, Jiří Stich,
Martin Svoboda, Robert Szabo, Kamil Šebesta, Jindřich Šenbauer, Pert Šigut, Oldřich Šmída, Martin Špalek,
Milan Špatenka, Jiří Štefan, Petr Štulc, Pavel Švajner, Lukáš Tančouz. Aleš Tomáš, Petr Tuček, Miloš Tůma,
Karel Urválek, Vladimír Vajnar, Přemysl Vániš, Jan Vanžura ,Petr Vašák ,Aleš Vážný ,Richard Vidlička, Petr
Vikler, Tomáš Viták, Michaela Vlastníková, Miloš Vodička. František Voldán, Bohuslava Volná, Ludmila Vrbová,
Martin Wiener, Marek Zacios, Petr Zachoval, Pavel Zamouřil, Petr Zápařka, Jiří Zázvorka, Milan Železný
And František Muller and Ondřej Mamula
One more memory from the ŠPINDL 2011 conference
What the project gave us and what it took away ?
 Took away:
 illusions and ideas
 a lot of quiet nights
 summer holiday and 2 skiing seasons
 Gave:







real experience
new knowledge
better testing procedures
2x heart attacks
new brothers in arms
annual beach volleyball tournaments
3 babies
Thanks for you attention
František, Ondřej, Illario, Baard, Radek, Martin, Milan, Vlado, Raduz
and many others