220 kV D/CT/L for In/out of Tarbela

advertisement
NATIONAL TRANSMISSION AND DESPATCH COMPANY (NTDC)
NTDC DEVELOPMENT PROGRAM
PLANNING POWER (NTDC) PEPCO
January 2012
TABLE OF CONTENTS
SR.
NO.
DESCRIPTION
I
List of ongoing Development projects
Table-1
II
List of Future projects where financing has been lined up
Table-2
III
List of Future projects where financing is required
Table-3
IV
Cross Border Inter-connection Projects
Table-4
NTDC ONGOING DEVELOPMENT PROJECT
SR.
NO.
NAME OF SUBSTATIONS
TRANSFORMER
CAPACITY (MVA)
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
1
Ext. at 500 kV Sheikh
Muhammadi
1x450
-
Feb, 2012
2
Ext. at 220 kV Bannu
1x160
-
3
Ext. at 220 kV
Sarfraznagar
1x160
-
Feb, 2012
New 220 kV GIS
Bandala
2x160
220 kV Gatti - K.S.K D/C In/Out
at Bandala. (5+5 km)
April, 2012
Installation of SVCs at
220 kV N.K.L.P.
Lahore.
SVCs
Static Var Compensators of
appropriate capacity.
June, 2012
4
5
6
Looping In/Out of 220
kV G/Barotha-S/Bagh
T/L at Mardan
Looping in & out of one circuit
of Ghazi Barotha – Shahi Bagh
at Mardan (30 km)
Feb, 2012
Feb, 2012
3
NTDC ONGOING DEVELOPMENT PROJECTS
SR.NO.
7
NAME OF
SUBSTATIONS
TRANSFORMER
CAPACITY (MVA)
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
-
March, 2012
220 kV Yousafwala - Sarfaraz
Nagar D/C In/Out at Okara. (5 +
5km)
June, 2012
Extension/Augmenta
tion at existing
substations:
500 kV Dadu
1x450
1x160
220 kV Burhan
8
1x160
220 kV Mardan
1x250
500 kV Sheikh
Muhammadi
1x160
500 kV New Rewat
1x250
220 kV Shikarpur
1x160
220 kV Okara
3x250
9
220 kV Toba Tek
Singh/Gojra
3x250
220 kV Faisalabad-Multan D/C
In&Out at T.T.Singh/Gojra. (1+1
km)
June, 2012
4
NTDC ONGOING DEVELOPMENT PROJECTS
SR.
NO.
10
11
NAME OF NEW
SUBSTATIONS
Installation of
SVC at Quetta
TRANSFORMER
CAPACITY (MVA)
SVC
Ext. at Ghazi
Brotha for
addition of 600
MVA 500/220 kV
T/F.
1x600
12
220 kV Loralai
2x250
13
Augmentation of
220 kV Ravi at
Lahore.
3x250
500kV D.G Khan
Substation.
2x600
2x250
14
ASSOCIATED TRANSMISSION
LINES
Static Var Compensators of
appropriate capacity
EXPECTED
COMMISSIONING
Dec, 2013
Dec, 2012
220 kV D.G Khan – Loralai (250 km)
Nov, 2012
Nov, 2011
500kV Guddu-Multan 2nd cct In/Out
at D.G. Khan substation(20+20) km
Dec, 2013
5
NTDC ONGOING DEVELOPMENT PROJECTS
SR.
NO.
NAME OF NEW
SUBSTATIONS
15
220 kV Rohri New
for interconnection
of IPPs at Engro
Energy PP and
Mari (Dharki) CCPP
TRANSFORMER
CAPACITY
(MVA)
2x250
ASSOCIATED TRANSMISSION
LINES
EXPECTED
COMMISSIONING
220 kV D/C T/L Dharki CCPP– Rohri
New (115 km)
132 kV D/C T/L for In/Out of RohriKhairpur/Gambat D/C T/L at Rohri
New (1+1 km)
220kV D/C Rohri New-Shikarpur T/L
(50 km)
June, 2012
220 kV D/C T/L for In/Out of Dharki Rohri New at Engro CCPP (5+5 km)
132 kV Rohri New-Gambat D/C T/L (53
km)
16
220 kV Gridstation
at Khuzdar,
17
220 kV Grid Station
at Ghazi Road,
Lahore
2x160
220kV D/C Dadu – Khuzdar
Transmission Line (300 km)
3x160
220 kV D/C T/L for In&Out of NKLP –
Sarfraz Nagar at Ghazi Road. (30 km)
Aug, 2012
June, 2012
220 kV D/C T/L for In&Out of Ravi–
KSK at Ghazi Rd. (30 km)
6
NTDC ONGOING DEVELOPMENT PROJECTS
SR.
NO.
NAME OF NEW
SUBSTATIONS
T/F
CAPACITY
(MVA)
ASSOCIATED TRANSMISSION
LINES
220 kV Grid Station at
Kassowal along with
associated 220kV D/C
T/Lines.
2x160
220 kV GIS substation
at Gwadar
2x160
20
500 kV R.Y.Khan
2x600
500 kV Guddu - Multan 3rd Circuit
In/Out at R.Y.K (30+30 km)
21
220 kV GIS Shalamar
(Mehmood Buti)
3x250
220 kV Ravi-KSK D/C In/Out at
Shalamar (9km long overhead
T/L) & (3+3km) cable
18
19
EXPECTED
COMMISSIONING
220 kV D/C Transmission Line for
In&Out of Vehari – Yousafwala at
Kassowal. (45+45 km)
Aug, 2012
220 kV D/C T/L from Pak-Iran
border to Gwadar (100 km)
Jun, 2013
Dec. 2012
May.2012
7
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
Name of
Project
1
220 kV
Gujrat
2
220 kV
Chishtian
3
500 kV New
Lahore
Transformer
Capacity
(MVA)
ASSOCIATED
TRANSMISSION
LINES
3x250
220 kV Mangla-Ghakkar
D/C In/Out at Gujrat
(2+2 km)
2805
33
22.10.2007
JICA
2x250
220 kV Vehari Chishtian D/C T/Line.
( 65 km)
3740
44
22.10.2007
JICA
12665
149
09.12.2010
JICA
2x750
Two 500 kV S/C T/Lines
for In/out of 500 kV
Sahiwal – Lahore S/C at
Lahore New (15+15 km)
Estimated
Expected
Approval
Cost
Eqt. US$
by
Financing commissi(Rs. in
in Million
oning
ECNEC
Million)
June,2013
June,2013
June,2013
Two 500 kV S/C T/Lines
for In/out of 500 kV
Lahore – Gujranwala
S/C at Lahore New
(50+50 km)
220 kV D/C T/Line for In/out
of 220 kV NKLP-Ghazi Road
at Lahore New. (50 km)
220 kV D/C T/Line for In/out
of 220 kV NKLP-Wapda
Town at Lahore New. (54km)
8
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
Name of
Project
Transformer
Capacity
(MVA)
ASSOCIATED
TRANSMISSION
LINES
Expected
Estimated
Eqt. US$
Year of
Cost
Approval
in
Financing
commissi(Rs. in
by ECNEC
Million
oning
Million)
Two 500 kV S/C
T/Lines for In/out of
500 kV Dadu-Guddu
circuit No:1 at
Shikarpur (20+20
km)
500 kV
4- Shikarpur
2x600
Two 500 kV S/C
T/Lines for In/out of
500 kV Dadu-Guddu
circuit No:2 at
Shikarpur. (22+22
km)
220 kV D/C for
In/Out of 500/220 kV
Guddu – Sibbi S/C
at Shikarpur (50 km)
8160
96
09.12.2010
JICA
Dec,2013
9
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
Name of
Project
S.#
Expected
TransforEstimated
ASSOCIATED
Eqt. US$
Year of
mer
Cost
Approval
TRANSMISSION
in
Financing
commissiCapacity
(Rs. in
by ECNEC
LINES
Million
oning
(MVA)
Million)
-
220 kV D/C T/L
for In/out of
MansheraSangjani T/L (40
km)
1105
13
PC-I under
ADB Tr-IV
preparation
2012-13
-
220 kV D/C T/L
from T.M Khan
Road to Hala
Road (30 km)
850
10
PC-I under
ADB Tr-IV
preparation
2012-13
220 kV Chakdara
– Mardan (85
km)
3230
38
PC-I under
ADB Tr-IV
preparation
2013-14
nd
2 source of
supply to
5Islamabad
University
nd
2 Source of
supply to Hala
6Road Grid
Station
220 kV
7Chakdara
2X250
10
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
8-
9-
Name of
Project
220 kV Mirpur
Khas
220 kV Taxila.
Expected
TransforEstimated
ASSOCIATED
Eqt. US$
Year of
mer
Cost
Approval
TRANSMISSION
in
Financing
commissiCapacity
(Rs. in
by ECNEC
LINES
Million
oning
(MVA)
Million)
2x160
220 kV D/C T/L
from Hala Rd. to
.M.Khan . (10 km)
In/Out of one
circuit of above
220 kV proposed
T/L at Mirpur
Khas New (70
km).
2975
35
PC-I under
preparation
ADB Tr-IV
2013-14
2x250
In/Out of 220 kV
Burhan - ISPR S/C
at Taxila. (6 km)
2295
27
PC-I under
preparation
ADB Tr-IV
2013-14
11
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
S.#
Name of
Project
220 kV
10Nowshera
11-
12-
Transformer
Capacity
(MVA)
ASSOCIATED
TRANSMISSI
ON LINES
3x250
220 kV D/C
T/L for In/Out
of G.Brotha
Sh/Bagh T/L
at Nowshera
(5+5 km)
3x250
220 kV Gatti
- Ludewala
D/C In/Out at
Chiniot Ind.
(4+24km)
220 kV Lalian
Dispersal of
Power from
Uch-2
-
220 kV Uch-II
– Sibbi D/C
(125 km)
Expected
Estimated
Eqt. US$
Year of
Cost
Approval
in
Financing
commissi(Rs. in
by ECNEC
Million
oning
Million)
1876
1581
2975
ADB
Tr-IV
31
06.02.2008
2013-14
18
PC-I
approved
on
11.11.2011
ADB
Tr-IV
2013-14
35
PC-I
approved
on
29.07.2011
ADB
Tr-III Ext
2013-14
12
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
Transformer
S.# Name of Project
Capacity
(MVA)
Augmentation
of 500 & 220 kV
existing
substations
ASSOCIATED
TRANSMISSI
ON LINES
Expected
Estimated
Eqt. US$
Year of
Cost
Approval
in
Financing
commissi(Rs. in
by ECNEC
Million
oning
Million)
-
500 kV Rewat
1x750
-
500 kV Sh.
Muhammadi
4x250
-
13- 220 kV Mardan
2x250
-
220 kV Burhan
4x250
-
220 kV Bund Rd
4x250
-
220 kV
Bahawalpur
2x250
-
220 kV Quetta
Industrial
2X250
-
3825
45
PC-I
Approved
on
29.07.2011
ADB Tr-I
(Ext-II)
2013-14
13
NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP
Transfor
-mer
Capacity
(MVA)
ASSOCIATED
TRANSMISSION
LINES
S.#`
Name of
Project
14-
220 kV
Manshera
2x160
In/out of 220 kV Alai
Khawar-Sangjani
T/L at Manshera
(0.5+.0.5 km)
15-
220 kV D.M
Jamali
1x160
1x100
in/out of 220 kV
Uch-Guddu S/C at
D.M. Jamali (5 km)
-
500 kV Jamshoro-R.Y.K (535 km)
500 kV Moro-Dadu
(55 km)
Interconnection
of 1200 MW
AES Imported
16- coal based
Power Plant
near Karachi
(Part-I)
Expected
Estimate
Eqt.
Year of
d Cost
Approval
US$ in
Financing
commissi
(Rs. in
by ECNEC
Million
-oning
Million)
1105
850
25694
13
Approved
Tranche-III
2013-14
10
Approved
Own
resource/
PSDP
2013-14
285
PC-I cleared
by CDWP
on
18.03.2010
ADB Tr-III
2015-16
14
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
1-
2-
3-
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
2x160
In/out of 220 kV ManglaRewat S/C at Chakwal
(65 km)
220 kV Chakwal
220 kV GIS Jhang
Rd. Faisalabad
2x250
220 kV D.I Khan
2x250
4-
220 kV Gharo
5-
220 kV Jhimpir
2x250
2x250
6-
220 kV Mastung
2x250
220 kV Samundri Rd. –
Jhang Rd. D/C T/L (40 km)
220 kV D/C T/Line for
In/out of 220 kV Chashma
Nuclear – Ludewala S/C
at D.I Khan (100 km)
220 kV Gharo – T.M Khan
Road ((130)
In/Out of 220 kV Gharo –
T.M Khan Road at Jhimpir
(65 km)
220 KV Mastung Sibbi
(120 km)
ESTIMATE
D COST*
(Rs.in
Million)
Eqt.
US$ in
Million
EXPECTED
YEAR OF
COMMISSIONING
2890
34
2014-15
2975
35
2014-15
3825
45
2012-13
4590
54
2014-15
3230
38
2014-15
4080
48
2014-15
15
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
7.
220 kV
Shadman
8.
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRD
YEAR OF
COMMISSIO
-NING
220 kV D/C cable from
Shadman to Bund Road (30
km)
4250
50
2013-14
220 kV D/C T/L from
Chashma Nuclear to Bannu
(125km)
3150
35
2013-14
-
220 kV Tarbela – Burhan D/C
T/L on Rail conductor (35 km)
990
10
2013-14
-
Re-conductoring of 220 kV
Tarbela ISPR on Rail
conductor (62.5 km)
1260
14
2013-14
T/F
CAP.
(MVA)
2x250
Interconnection
of Chashma
Nuclear (C-3 &
C-4)
9.
10.
ASSOCIATED
TRANSMISSION LINES
16
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
11.
500 kV
Islamabad New
T/F
CAP.
(MVA)
2x750
2x250
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRD
YEAR OF
COMMISSIO
-NING
500 kV D/C T/L for In/Out of
500 kV Tarbela – Rewat S/C at
Islamabad New (40 km)
500 kV D/C T/L for In/Out of
500 kV G/Barotha–Rewat S/C
at Islamabad New (50 km)
220 kV D/C T/L for In/out of
Tarbela – ISPR 220 kV S/C at
Islamabad New (25 km).
Two 220 kV D/C T/Ls for
In/out of Mansehra – ISPR at
Islamabad New (5+5 km).
220 kV D/C T/L from
Islamabad New to ISPR (15
km)
10560
120
2014-15
17
NTDC FUTURE PROJECTS WHERE FINANCING IS REQUIRED
S.#`
12-
Name of
Project
500 kV
Faisalabad
New
Transfor
Estimated
Eqt. US$ Expected Year
-mer
ASSOCIATED TRANSMISSION
Cost
of commissiin
Capacity
LINES
(Rs. in
oning
Million
(MVA)
Million)
2x750
2x250
500 kV D/C T/L for In/Out of 500
kV M/Garh – Gatti S/C at
Faisalabad West (2 km)
500 kV D/C T/L for In/Out of 500
kV Multan - Gatti S/C at
Faisalabad West (20 km)
11250
125
3570
42
2014-15
220 kV D/C T/L from Faisalabad
West to T.T Singh (70 km).
220 kV D/C T/L from Faisalabad
West to Lalian / (M3) (100
km).
13-
220 kV M-3
Industrial
Estate
Faisalabad
220 kV M3 Industrial Estate –
Faisalabad New (70 km)
2x250
In/Out of 220 kV Faisalabad
New - M3 Industrial Estate at
220 kV Chinot Industrial New
(30 km)
2013-14
18
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
14
220 kV Jamrud`
15
500 kV
Peshawar New
T/F
CAP.
(MVA)
2x250
ASSOCIATED
TRANSMISSION LINES
220 kV Jamrud – Sh.
Muhammadi (10 km)
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRD
YEAR OF
COMMISSIONING
1445
17
2013-14
5440
64
2014-15
5950
70
2014-15
2635
31
2014-15
In/out of Tarbela – Sh.
Muhammadi at Peshawar
New (2+2 km)
2x750
In/Out of 220 kV Sh.
Muhammadi-Shahibagh at
Peshawar New (5 km)
16
220 kV Kohat – Peshawar
New (50 km)
220 kV Kohat
2x250
17
220 kV
Islamabad I-10
2x250
220 kV Kohat – Bannu
(150 km)
In/Out of 220 kV Rewat –
Islamabad University D/C at
Islamabad I-10 (30+30 km)
19
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
T/F
CAP.
(MVA)
18-
Ext. at 220 kV
Gujrat
1x250
19-
Power Dispersal
from 747 MW
CCPP at Guddu
20-
Interconnection
of 1200 MW
AES Imported
coal based
power near
Karachi (Part-II)
ASSOCIATED TRANSMISSION
LINES
-
ESTIMATED
COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRD
YEAR OF
COMMISSIONING
425
5
2014-15
500 kV Guddu New PP – M.
Garh (256 km)
7735
-
In/Out of Guddu – Multan at
New Guddu (10+10 km)
(PC-I
approved
on
29.07.2011)
500 kV
switch
ing
station
at
Matiari
500 kV S/C T/Line from AES
Power Plant to Matiari
switching station (200 km)
In/Out of 500 kV HubJamshoro S/C T/Line at AES
(45+45 km)
13934
(PC-I
cleared by
CDWP on
18.3.10
91
2013-14
155
2015-16
20
NTDC FUTURE PROJECTS WHERE FINANCING IS REQUIRED
S.#`
Name of Project
21-
Dispersal of
Power from
Neelum Jhelum,
Karot & Azad
Pattan HPPs
22-
Interconnection
of Thar Coal
Based 1200 MW
Engro Power
Plant wi
Transformer
Capacity
(MVA)
-
ASSOCIATED
TRANSMISSION LINES
500 kV Neelum
Jhelum – Gujranwala
D/C T/Line (270 km).
In/Out of one circuit
of Neelum JhelumGujranwala T/L at
Karot (5 km).
In/Out of one circuit
of Neelum JhelumGujranwala T/L at
Azad Pattan (5 km).
Estimated
Cost
(Rs. in
Million)
Eqt. US$
in
Million
Expected
Year of
commissioning
22582
(PC-I
submitted
to GoP in
Dec,2011)
251
2015-16
233
2014-15
20053
-
500 kV D/C T/L form
Engro power plant to
Matiari (250 km
(PC-I
submitted
to GoP in
Aug.2011
21
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
23
220 kV
Kamalabad
24
T/F
CAP.
(MVA)
2x250
Ext. at 500 kV
Gujranwala
1x600
25
Ext. at 500 kV
Lahore New
1x750
26
220 kV Kamra
27
220 kV Iqbal
Town
28
220 kV
Gujranwala
New
ASSOCIATED
TRANSMISSION LINES
In/out of Rewat – Islamabad
Peshawar Rd. at Kamalabad
(5+5 km)
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIONING
1445
17
2015-16
1700
20
2015-16
2040
24
2015-16
-
-
2x250
In/out of 220 kV Tarbela –
Taxila at Kamra (5 km)
1275
15
2015-16
2x250
In/Out of 220 kV Lahore –
Wapda Town D/C at Iqbal
Town (20+20 km)
2125
25
2015-16
2890
34
2015-16
2x250
In/Out of 220 kV Mangala –
K.S.K at Gujranwala New
(20 km)
220 kV Nokhar - Gujranwala
New (50 kM)
22
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
29
220 kV Pindi
Bhattian
30
31
32
220 kV Head
Faqirian
T/F
CAP.
(MVA)
2x250
2x250
220 kV
Joharabad
ASSOCIATED
TRANSMISSION LINES
220 kV Pindi Bhattian Ind. –
Gujranwala (50 km)
220 kV Head Faqirian –
Ludewala (60 km)
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIONING
2380
28
2015-16
28
2380
2015-16
2x250
In/out of 220 kV D/C
Ludewala –Chashma at
Jauharabad (5+6 km)
1445
17
2015-16
2x250
220 kV Kohat – Ali zai D/C
(110 km)
3825
45
2015-16
220 kV Alizai
23
NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED
SR
#.
NAME OF NEW
SUBSTATIONS
33
2 Source of
supply to 220
kV Bhawalpur
substation
34
35
36
T/F
CAP.
(MVA)
nd
220 kV Arif
Wala
Interconnection
of 2x1000 MW
Nuclear Power
Plants at
Karachi
Dispersal of
Power from 720
MW Karot HPP
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIONING
3825
45
2015-16
1445
17
2015-16
25500
300
13250
156
220 kV R.Y.K – Bahalawlpur
D/C T/L (150 km)
-
2x250
-
In/Out of 220 kV Yousafwala –
Kassowal D/C at Arifwala
(5+5 km)
Three 500 kV Circuits from
Nuclear Plants to Matiari (200
km each)
2018-19
500 kV Karot – Lahore New
(270 km)
-
In/Out of 500 kV Neelum
Jhelum – Gujranwala at Karot
(10 km)
2018-19
24
CROSS BORDER INTER-CONNECTION PROJECTS
SR
#.
1-
2-
NAME OF NEW
SUBSTATIONS
Import of 1000 MW
Power from Iran
Import of 1000 MW
Power from
Tajikistan (CASA1000)
T/F
CAP.
(MVA)
ASSOCIATED
TRANSMISSION LINES
ESTIMATE
D COST
(Rs.in
Million)
Eqt.
US$ in
Million
REQUIRED
YEAR OF
COMMISSIONING
40120
472
2015-16
16065
189
2015-16
Two 500 kV HVAC S/C
T/Lines from Zahidan to
Quetta with series
compensation (198 km)
Switching station at
Zahidan, Quetta and
midpoint between Zahidan
& Quetta
-
500 kV HVDC T/L from
Pak-Afghan Border to
Peshawar (71 km)
500 kV Converter Station
Peshawar
25
Download