Wind Farm 040412 - NWT Chamber of Commerce

advertisement
Diavik Wind Farm
NWT Chamber of Commerce
4th April 2012
Location
Diavik
Diavik
Why Wind Power?
•
Diavik is completely dependent on diesel for all site power needs.
•
Hybrid power options sought to reduce cost and decrease GHG emissions.
5
What will Wind Power deliver?
•
Reduced power generation costs.
•
~ $30 million investment with 8 year
payback.
•
~ 10% reduction in diesel power
generation.
•
> 4 million litres reduction in diesel usage
per year.
•
Equates to around 100 truckloads per
year.
•
12,000 tonnes reduction in CO2
emissions per year.
•
6% overall reduction in GHG emissions.
6
Diavik Wind Farm
•
Four Enercon E70 generators.
•
Tower height
65m
•
9.2 Megawatt installed capacity
•
Blade length
35m
•
•
2.1 to 6 Megawatt online capacity.
•
Total height
100m
•
17 GWh power produced annually.
•
Generator weight
55 tonnes
Designed to operate to -40oC.
7
Timeline
•
2008
Commence wind data collection.
•
2010
Analysis of wind data and project feasibility study.
•
2011
Project approval / contract negotiations.
Generators ordered and commenced construction.
Site geotech. drilling / construction commenced.
Generator components shipped to Canada.
• 2012
Generator components transported to site via the Winter Road.
Complete site construction and erection of wind turbines.
Power generation commences.
8
Timeline
9
Innovation
•
First large scale wind farm installed at a remote operating mine.
•
Largest remote wind-diesel power generation installation.
•
Application of technology designed for arctic conditions.
10
Benefits beyond Diavik…
•
Demonstrate wind power as a viable
component of power generation in the
North.
•
Provide support to future wind power
initiatives and develop northern
capability.
• Weather tower donated to Det’on Cho
Earth Energy Giant Mine study.
11
Questions?
12
Download