Trust Programme Board 15 July 2013 Transforming Services 1 2 Summary status Comments Programme structure updated to better align care pathways and workforce with transformation 3 Transforming Augmenting Services Benefit / Measure Quality improvement measures Sustainability measures TBC £0 TBC Target TBC £11.8M TBC Being scoped Care Pathways & Packages Workforce Not yet started Transforming Corporate 4 Key Risks and Issues Risk/Issue Baseline Comment 1 month delay Augmenting Service programme initiated 8 July Safety Programme; Leadership and CISK Status PCP Transforming Specialist Care Key Benefits & Measures Cost reduction measures 13/14 Key programme / project PCP reporting 1 month delay Transforming Corporate programme yet to be agreed and initiated Linked programmes Key Programme Status Mitigating Actions Progress TBC TSP13: PCP does not reduce demand on inpatient services to deliver a ‘425 bed model’ Develop target bed model for Oct BoD – work started £5.8M TSC02/09: Financial delivery of TSC this and subsequent years Monitor in year Develop 5 year strategy by Sep 13 WKF09: Timescale and capacity to develop PCP workforce needs Early feed of partinformation from PCP TBC Status Transforming Services – PCP Programme 1 2 Summary status Comments Requests for support to Certified Leaders - only one workshop not covered Partners invited to all workshops. SU+C covering all workshops, still some gaps with partners Key Milestone Status Milestone Status Target Forecast Clinical processes design complete start 22nd July End End Aug 13 Sept 13 Non-clinical design complete Oct 13 Nov 13 End of design stage – Tranche 1 Oct 13 Nov 13 Mitigating Actions Status Medic attendance being progressed First 2 workshops (22nd / 29th July sorted) Plan for Non – clinical design to be developed by Friday 19th July Linked projects 3 CPP; Workforce; Leadership; CIS; Augmenting Baseline Target Key Risks and Issues Risk/Issue Key Benefits & Measures Benefit / Measure 4 Progress Benefits plan to be complete and baseline measures established by August 2013 PCP10: Failure to develop sustainable ‘425’ bed model takes resources out of PCP Develop outline model by Jul 13 (Augmenting Services) PCP03: Not getting stakeholders engaged in available timescales Engagement plan Transforming Specialist Care – Programme Update 1 Comments Linked projects 3 2 Summary status • Neuro Services - largest transformation project that we have on-going. Parts of delivery are on track. Occupancy plans on track for neuro-rehab but challenges remain regarding neuro-psychiatry pathways • Forensics –no financial delivery attached to this project for 13/14. Tyne and Hebron occupancy levels are the focus for 2013/14. Financial delivery expected in 14/15. • Changing commissioners have increased risk of establishing ADHD service. Transforming Community Services Principal Community Pathways Baseline Target Neuro Bed occupancy 90% W3&4 89% for 12/13 90% Tyne Occupancy Levels 95% 47% for 12/13 65% July 13 95% Oct 13 Milestone Status Neuro-Services – medical & AHP staffing stabilised. Neuro Services – review of Heppell House – options appraisal complete Autism Assessment and Treatment Unit – Business Case consideration by Board Forensics - Tyne occupancy levels achieved (95% of 22 beds) 4 Progress Ytd 91% at July 13 51% June 13 More benefits and measures to be determined Target Forecast Nov 13 Nov 13 June 13 July 13 Transforming Specialist Care – 5 year strategy produced. Key Benefits & Measures Benefit / Measure Key Milestone Status May 13 July 13 Oct 13 Oct 13 Sept 13 Sept 13 Key Risks and Issues Risk/Issue TSC.02 – transformation work does not release financial delivery in 13/14 TSC.08 – Transforming Community Services capacity of mobile solution rollout TSC.01 – Large changes in commissioning across SCG Mitigating Actions Financial delivery meetings (monthly) Seek to appoint to roll asap. Seek to understand changes asap. TSC.09 – Ability to deliver financial Financial delivery delivery plans for 2014/15 onwards meetings (monthly) Status Transforming Services – Care Pathways Programme 1 2 Summary status Comments Milestone Progress mostly on track Some concern around timescales for PbR and internal capacity to do financial modelling. Recognised need to improve data quality and sharing / embedding information at team level. Action plan with Operational Groups being taken forward to address MHCT under-scoring. LD Cluster report has been delivered – working up implementation plan. Linked projects 3 Principal Community Pathways; Workforce Augmenting Services Base line Target Progress Status Delivery of Q1 CQUIN 7 Delivery of e-pathways functionality on Rio Draft specification for augmenting packages Delivery of Q&O Implementation plan 4 Key Benefits & Measures Benefit / Measure Key Milestone Status Target Forecast 30 Jun 30 Jun 1 Apr 14 NK 1 Aug 1 Aug 30 Sept 30 Sept Key Risks and Issues Risk/Issue Mitigating Actions Consistent way of describing type and level of demand for services. CPP01 – Lack of capacity for financial modelling impacts on delivery against national timeframe Information to support financial modelling for move towards PbR CPP15 – Poor data quality impacts Weekly monitoring on PCP demand planning and of data quality financial modelling Standardised information about quality and outcomes of services provided Workforce with skills to deliver care their patients require CPP09 – Delay to e-pathways functionality – impact on PCP and evidence of care package delivery Further capacity being resourced Director Informatics negotiating with CSE Status Transforming Services – Workforce Programme 1 2 Summary status Comments Programme is on track but there is risk later in the programme due to the dependencies on systems & processes part of PCP. Need to develop the programme for non-PCP areas Linked projects 3 Key Milestone Status Milestone Status Target Forecast Staff equipped with skills for PCP go-live in Sun & STy Mar 14 Mar 14 PCP workforce designed for Sun/ STy: skills, jobs, structure, OD Oct 13 Nov 13 HR process/principles in place to establish PCP community team Oct 13 Oct 13 Principal Community Pathways; Leadership 4 Key Benefits & Measures Benefit / Measure Close skills gap by 50% Baseline 0 Target 50% by Mar 2014 Progress Key Risks and Issues Risk/Issue WKF09: Timescale and capacity to develop PCP workforce needs WKF01: HR process for PCP will be different – risk re: staff and staff-side relations Mitigating Actions Status