Present - Virginia Department of Transportation

advertisement
Dulles Connector Sound Wall
PARDON OUR DUST MEETING
July 25, 2013 – 7:00 PM to 9:00 PM
McLean High School
1633 Davidson Rd, McLean, VA 22101
Project website:
http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp
WELCOME!
• John C. Muse
District Environmental Manager
• Chan B. Basnayake
Area Construction Engineer
2
http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp
Tonight's Objective:
• Introduction of the Construction
Team
• Present Project Scope of Work
• Construction Elements
– Sequence of Construction
– Lane Closures
– Night Work
• Questions and Answers
3
http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp
Project Team
• Virginia Department of Transportation
• Contractor: Lane Construction Corporation
4
http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp
Tonight's Objective:
• Introduction of the Construction
Team
• Present Project Scope of Work
• Lane Closures
5
Construction Team & Contact Information
VDOT Construction Management Team:
• Chan B. Basnayake, PE, PMP – Area Construction Engineer
– (703) 259-2947 chan.basnayake@vdot.virginia.gov
• Giles Njumbe P.E. – Construction Manager
– (703) 259- 3250 giles.njumbe@vdot.virginia.gov
• Divakar R. Reddy – Office Engineer
– (571) 329-0187 divakar.reddy@vdot.virginia.gov
• Abdul Razak – Project Inspector
– (571) 722-2201 abdul.razak@vdot.virginia.gov
• John P. Godwin– Sr. Inspector (Structural)
– (571) 898-5227 john.godwin@vdot.virginia.gov
VDOT Field office :
6
8245 Boone Blvd, Suite 530,
Tysons Corner, VA
Tel: (703) 847-1710
Hours of Operation:
Mon-Fri – (7:00 AM to 3:30 PM)
Construction Team & Contact Information continued
VDOT Design Team:
• Lee Ann Hall, P.E. – Assistant Section Mgr. L&D
– (703) 259-2746 LeeAnn.Hall@vdot.virginia.gov
• Hamid R. Misaghian, P.E.– L & D Consultant Mgr.
– (703) 259-1795 H.Misaghian@vdot.virginia.gov
• Brad Stimpson, P.E.– Design Consultant
McCormick & Taylor
Contractor: Lane Construction Corp.:
• Jan Sherman– Assistant District Manager
– (703) 222-5670 jasherman@laneconstruct.com
• Jim A Ballentine– Project Manager
– (571) 358-5390 jaballentine@laneconstruct.com
• Will Haynie – Superintendent
– (703) 371-0648 ewhaynie@laneconstruct.com
7
Project Location
8
Project Timeline
• Contract Executed:
May 21, 2013
• Notice to Proceed Date:
June 5, 2013
• Start of Construction:
June 14, 2013
• Substantial Completion:
November 21, 2014
• Final Completion:
May 29, 2015
9
Project Information
BEGIN NB
Sound Wall
END NB
Sound Wall
BEGIN SB
Sound Wall
END SB
Sound Wall
10
Allowable Lane Closure:
•Single lane closures on NB and SB Dulles Connector Road are
allowed from 9:30 PM to 5:00 AM, with the exception of Friday
night and Saturday night when these closures are permitted from
10:00 PM to 6:00 AM.
•Shoulder closures during the day are permitted from 10:00 AM to
3:00 PM (NB), and 10:00 AM to 2:00 PM (SB).
•Total closure of the roadway for a maximum duration of 20 minutes
is permitted from 12:00 AM to 5:00 AM.
11
Tonight's
Objective:
• Construction Elements
– Sequence of Construction
– Night Work
12
Construction : Sequence
Construction Phases:
• Phase-1 (Southbound), Chain Bridge Road to I-66.
• Phase-2 (Northbound), I-66 to Chain Bridge Road.
• Work on each Phase is divided into three segments. Clearing
& Grubbing shall be confined to those areas required for
access to and physical placement of the new sound barrier
wall, erosion control devices and temporary safety fence. To
the extent possible, all other existing vegetation shall remain.
13
Phase 1: Southbound
Aug 15, 2013 to Mar 26, 2014
• Section 1 – Sta. 10+00 to Magarity Road
• Section 2 – Magarity Road to Pimmit Run
• Section 3 – Pimmit Run to Sta. (107+15.16)
14
Phase 1: Southbound
Typical Section-A
15
Phase 1: Southbound
Typical Section-B
16
Phase 1: Southbound
Typical Section-C
17
Phase 1: Southbound
Typical Section-D
18
Phase 1: Southbound
Typical Section-E
19
Phase 1: Southbound
Typical Section-F
20
Phase 1: Southbound
Typical Section-G
21
Phase 2: Northbound
Mar 27, 2014 to Oct 20, 2014
• Section 1 – Sta. 118+65.72 to Pimmit Run
• Section 2 – Pimmit Run to Magarity Road
• Section 3 – Magarity Road to Sta. (11+48.59)
22
Phase 1: Northbound
Typical Section-H
23
Phase 1: Northbound
Typical Section-I
24
Phase 1: Northbound
Typical Section-J
25
Phase 1: Northbound
Typical Section-K
26
Phase 1: Northbound
Typical Section-L
27
Phase 1: Northbound
Typical Section-M
28
Night Work
Sensitive work such as
• Caissons, Posts & Panel on an as needed
basis.
29
Project Schedule
30
Project Schedule- continued
31
Project Schedule- continued
32
Question & Answer Session
33
http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp
Download