Revision Sheet – OSCM · Class 2: Fundamentals of Process Analysis
Operations and Supply Chain Management – Ali Shantia, HEC Paris
1. Process Types (Taxonomy)
Process: tasks connected by flows of goods and information that
transform inputs into outputs. Different products need different
processes.
From high variety / low volume to low variety / high volume:
Project (construction) → Job shop (luxury car) → Batch (apparel) →
Assembly line (economy car) → Continuous flow (oil refinery).
Feature
Job shop
Continuous flow
Product volume
Low
High
Equipment
specialization
Low
High
Machine setup
frequency
High
Low
Labor skills
High
Low
Fixed cost
Low
High
Variable cost
High
Low
2. Strategic Fit: Product–Process Matrix
• Match the process to the product: one of a kind → Project; low
volume, many products → Job shop; higher volume → Batch /
Assembly line; commodities, very high volume → Continuous flow.
• Above the diagonal (too flexible for a standard product): lost sales,
opportunity costs.
• Below the diagonal (too rigid for low volume): low utilization, high
capital costs.
Product life cycle → the process should evolve with the product:
• Introduction: low volumes, rapid design changes → flexible
process.
• Growth: process technology evolves; speed to market is critical.
• Maturity: stable volumes, design and technology; no first-mover
advantage → efficient flow process.
• Decline: falling volumes, no new variants; service parts and repairs
dominate.
Lessons: product and process are interrelated and both have life
cycles; competitive & marketing strategy → product attributes →
process design.
3. Process Analysis in 3 Steps
① Process Flow Diagram: inputs & outputs → tasks and their
sequence → resources per task → where inventory is held.
② Bottleneck analysis: capacity of each stage → identify the
bottleneck → capacity of the process.
③ Improvement decisions: recommend how to improve the system.
Symbols: rectangle = task · arrow = material flow · triangle = inventory
buffer · dashed arrow = information flow · diamond = decision point.
Configurations: single station, parallel stations (separate lines or
single line); multi-stage: serial, serial with buffers, mixed.
Why draw it? At Darty, mapping the process shows its benefits: no
need to display every item, and easier, more transparent inventory
management.
Exam recipe: for each stage, cycle time = time ÷ resources → capacity
= 1 ÷ cycle time → bottleneck = lowest capacity → process capacity =
bottleneck capacity → utilization = flow rate ÷ capacity.
4. Key Definitions & Formulas
• Flow (throughput) time: time one unit spends in a stage/process.
• Cycle time: average time between the completion of two
successive units.
• Flow rate (throughput): rate at which units flow through the
process.
• Capacity: maximum flow rate = 1 / cycle time (when working at
capacity).
Stage cycle time = task time ÷ number of parallel resources. Flow
time does not depend on the number of parallel resources.
Process capacity = bottleneck capacity · Process flow time = sum of
stage flow times (serial) · Flow rate = min(demand or input, capacity)
· Utilization = flow rate ÷ capacity.
5. Worked Example: Shopping at Darty
Order → Payment (cashier) → Retrieval (movers, warehouse) →
Reception → Completed order.
Stage
Time /
resources
Cycle time
Capacity
Utilization*
Payment
4 min × 1
4 min
15 /hr
80%
Retrieval
10 min × 2
5 min
12 /hr
100%
Reception
0.5 min × 1
0.5 min
120 /hr
10%
→ Bottleneck = Retrieval. Process cycle time = 5 min; capacity = 12
orders/hr; flow time = 4 + 10 + 0.5 = 14.5 min. *At 12 orders/hr.
Fix: add movers or simplify the pick-up process — add capacity only
at the bottleneck.
6. Managing the Bottleneck
Bottleneck = slowest stage; it sets the capacity and cycle time of the
whole process. An hour lost at the bottleneck is lost for the whole
plant; an hour saved elsewhere is a mirage.
Improvement cycle: identify → exploit → subordinate everything else
→ elevate (remove) → repeat, since a new bottleneck may appear.
Goal: bottleneck used at 100%, always kept running.
Supply- vs demand-constrained: if input/demand < capacity, demand
is the constraint, not the process. Managing the bottleneck → more
customers served in the same time. Nvidia: months-long GPU waits
due to TSMC CoWoS advanced packaging capacity, not chip design.
Horizon
Labor
Machines
Long term
Cross-train; adjust
headcount; subcontract
New equipment; outsource;
reliability; shorter setups
Medium term
Flexible time; part-time staff Preventive maintenance;
subcontract; priorities
Short term
Overtime; extra shifts
—
Reduce flow time = be more responsive. Zara: ~11,000 items/yr (vs
2,000–4,000 for rivals); new product in stores in 4–5 weeks,
modifications in 2 (industry: ~6 months).
Key Takeaways & Next Steps
• Flow time and cycle time differ: flow time refers to a unit; cycle
time to a stage or the whole process.
• Capacity and cycle time are inverses; process capacity = bottleneck
capacity.
• Next: Quiz 1 (Process Analysis) and read the Metalarm case
(Course Package). Teams of 4–5 registered within 2 weeks.