Capital Budgeting and cash flows
Initial Investment
Cost of new asset
+ Installation cost
Installed cost (new)
500 000
50 000
550 000
Installed cost (Old)
-Accumulated Depreciation
Book Value
Proceeds from sale (Old)
- Tax on proceeds (40%)
After TAX Proceeds (Old)
300 000
(200 000)
100 000
(150 000) – 50 000 Profit
(20 000) [50 000x0.4]
30 000
Increase in A/R
Increase inventory
Increase A/P
Increase Accruals
Change in Working Capital
4000
2000
(2000)
(3000)
1000
Initial Investment
590 000
Operating Cash Flow
OCF = NOPAT + Depreciation
Where NOPAT = EBIT x (1-T)
Terminal Cash Flow
Installed cost (New)
-Accumulated Depreciation
Book Value
Proceeds from sale (New)
- Tax on proceeds (40%)
After TAX Proceeds (New)
300 000
(200 000)
100 000
(150 000) – 50 000 Profit
(20 000)
30 000
Installed cost (Old)
-Accumulated Depreciation
Book Value
Proceeds from sale (Old)
- Tax on proceeds (40%)
After TAX Proceeds (Old)
200 000
(150 000)
50 000
(75 000) – 25 000 Profit
(10 000)
15 000
Change in Working Capital
8000
Terminal Cash Flow
53 000
Capital Budgeting techniques
Payback period
Pb = Pb Year – (Profit in Pb year/Cash flow in Pb year)
Pb = 5 – (50000/150 000) = 4.667
Net Present Value (NPV) / Internal Rate of Return (IRR)
Cf0 – (1500 000)
Cf1 – 600 000
Cf2 – 550 000
Cf3 – 380 000
Cf4 – 350 000
I/YR – 10%
N–4
NPV – 24 554.33
IRR – 10.838
IRR Accept/reject decision
Always select the project with the highest NPV and then you look at the highest IRR
Projects with (Negative NPV) should not be accepted
Risk and refinement in Capital budgeting
Certainty Equivalent adjustment
N–4
I/YR – 10%
Year
0
1
2
3
4
NPV
IRR
Cash Inflows
(100 000)
30 000
40 000
50 000
9 000
Certainty
Equivalent
(CE)
1
0.2
0.4
0.6
0.8
Cash flow
x
CE
(100 000)
6000
16 000
30 000
7 200
(53 865.17)
- 17.57
Risk Adjusted Discount Rate (RADR)
Where no other Information available RADR = Required return
RADR = Rf + PI(Rm-Rf)
Annualised NPV (ANVP)
N–4
I/YR – 10%
Year
0
1
2
3
4
NPV
PV
N
I/YR
PMT
Cash Inflows
(100 000)
30 000
40 000
50 000
9 000
4043.43
4043.43
4
10
(1275.59)
Calculating the cost of Capital
Preference Shares
π
π =
π·π
ππ
Ordinary Shares / Retained Earnings
π
π =
π·
+π
π
New issue Shares /Equity
π
π =
π·
+π
ππ
Cost of L-t Debt
Ri = Rd x (1-T)
WACC, WMCC and Investment opportunity Schedule
(IOS)
Working Average cost of Capital
WACC = Weight x rate
Company with 40% Debt and 60% Equity structure, cost of Debt is 8% and Equity 10%
WACC (Debt) – 0.4 x 0.08 = 0.032
WACC (Equity) – 0.6 x 0.10 = 0.06
WACC (Total) = 0.032 + 0.06 = 0.092 (9.2%)
Source of Capital
L-T Debt
Preference Shares
Ordinary Shares
Weight
0.40
0.10
0.50
1.00 (100%)
Working Marginal cost of Capital (WMCC)
1 - Find Break Points
π΅π =
π΄πΉ
π€
AF – Available funding
W - Weight
2 – Calculate cost of capital
See “Calculating cost of Capital”
3 – Calculate WACC
Cost
6.6%
10.6%
13%
WACC
0.4 x 0.066 = 0.02640
0.1 x 0.106 = 0.0106
0.5 x 0.130 = 0.065
0.102 (10.2%)
Leverage
Degree of operating Leverage (DOL)
π·ππΏ =
%β πΈπ΅πΌπ
%β πππππ
Degree of Financial Leverage (DFL)
π·πΉπΏ =
%β πΈππ
%β πΈπ΅πΌπ
Degree of Total Leverage (DTL)
π·ππΏ =
%β πΈππ
%β πππππ
Operating break-even point
π=
πΉπΆ
π − ππΆ
Capital structure and firm value
Value of firm
π=
ππππ΄π
ππ΄πΆπΆ
Where NOPAT = EBIT x (1-T)
Where all earning are paid out as dividends:
π=
πΈππ
π
r – Required rate
Earnings per share (EPS)
πΈππ =
ππππππ‘ − ππππππππππ π βπππ πππ£πππππ
ππ’ππππ ππ ππππππππ¦ π βππππ
Coefficient of variation (CV)
πΆπ =
π
π
π − π π‘ππππππ πππ£πππ‘πππ
π − ππππ’ππππ πππ‘π’ππ
Dividend policy
Relevance theory of dividends
ο·
ο·
ο·
Advanced by Gordon and Linther
Direct relationship between a firms dividend policy and its market value
Bird-in-the-hand argument
o Investors see current dividends as less risky than future dividends or capital
gain
o I.e. a bird in the hand is worth two in the bush
Irrelevance theory of dividends
ο·
ο·
Advanced by Miller and Modigliani’s
Firms value is determined solely by the earnings power and risk of assets
(investments) and the way in which it is split between dividends and retained
earnings
Residual theory of dividends
ο·
ο·
Amount left over after all acceptable investment opportunities have been
undertaken
Dividend decision treated in 3 steps
o Determine optimal level of capital expenditure
o Estimate the total amount of equity finance
o Because cost of retained earnings is less than cost of new ordinary shares,
retained earnings should be used to meet equity requirements and where
inadequate sell new share
Factors affecting dividend policy
ο·
ο·
ο·
ο·
ο·
ο·
ο·
Legal constraints
Contractual constraints
Internal constraints
Flotation cost
Growth prospects
Taxation
Owner/Market consideration
Types of dividend policies
ο·
ο·
ο·
Constant-pay out-ratio
o % paid to owner in each dividend period
Regular
o Fixed-rand dividend in each period
Low-regular-and-extra
o Pays low regular dividends, supplemented by an additional ‘extra’ dividend
when earning are higher
Share split
Method used to lower the market price of a firms share
Mergers
Types of Mergers
ο·
ο·
ο·
ο·
Horizontal merger
o Merger of two firms in the same line of business
o Shoprite & Checkers
Vertical merger
o Merger where a firm acquires a supplier or a customer
o Parmalat acquire JPA Diary Ltd
Congeneric merger
o Where a firms acquires another firm that is in the same line of industry but
not the same line of business, supplier or customer
o Bovis Lend Lease acquires Construction Tool Manufacturing business
Conglomerate merger
o Merger of firms in unrelated businesses
o BMW merges with Nokia
Reasons for Mergers
ο·
ο·
ο·
ο·
ο·
ο·
ο·
Growth or diversification
Synergy
Fund raising
Increase managerial skills or technology
Tax consideration
Increase ownership liquidity
Defence against takeover