DBIA Certification Practice Exam – Set 1 20 Questions | 30–40 minutes Based on official DBIA materials
(Design-Build Done Right®, Red Flag Exercise, Code of Professional Conduct, Progressive Design-Build
Deeper Dive, Project Delivery Primer, etc.)
Instructions: Choose the best answer for each question. This exam mirrors the style and content of the actual
DBIA certification test.
Section 1: Project Delivery Systems & Fundamentals
1. A municipality needs to build a new police station. The city is sophisticated in building and construction and
has adequate in-house design and construction management staff for project programming and oversight.
Standard city prescriptive specifications are to be strictly followed, and the building occupancy date is not
critical.
A project budget has been established, and the project will be canceled if the construction price exceeds the
budget. Alternative project delivery methods are allowed by statute. The public procurement statute requires an
open selection process with no shortlisting or prequalification. Based on the owner’s profile and specific project
conditions, which project delivery method would be most effective?
A. Design-Bid-Build
B. Negotiated Design-Build
C. Construction Management at Risk
D. Multiple prime contracting
2. The single contract for both design and construction under one entity is the fundamental difference between
Design-Build and all other delivery systems. This creates:
A. A system of checks and balances between separate designer and contractor
B. Linear, sequential phases with no overlap of design and construction
C. Owner control over every design detail through prescriptive specifications
D. Single-source responsibility and integrated team dynamics
3. Which delivery system is historically and statistically more prone to formal disputes, protests, and changeorder battles because it creates adversarial relationships between design professionals and construction
professionals?
A. Design-Build (Best Value or Progressive)
B. Design-Bid-Build
C. Integrated Project Delivery (IPD)
D. Progressive Design-Build
4. An experienced Owner wants early involvement of key trade contractors, constructability input before design
is 30% complete, and maximum schedule compression through overlapping design and construction. Which
delivery system best supports this?
A. Design-Bid-Build
B. Multiple Prime
C. Low-Bid Design-Bid-Build
D. Design-Build (any variation)
5. In the Project Delivery Primer, the three key components of an Owner’s Strategic Acquisition Plan are
Project Delivery System, Procurement Method, and:
A. Commissioning Plan
B. Contract Format (Lump Sum, GMP, Cost-Plus, etc.)
C. Sustainability Rating System
D. Stakeholder Engagement Matrix
Section 2: Design-Build Done Right® Best Practices
6. According to Design-Build Done Right®, the Owner should implement a procurement plan that:
A. Focuses primarily on lowest price with minimal qualifications evaluation
B. Requires the Design-Builder to price 100% complete prescriptive drawings
C. Provides no draft contract until after award
D. Focuses heavily on qualifications and demonstrated history of integration/collaboration, while maximizing
performance-based requirements
7. Which of the following is explicitly listed as a core Guiding Principle in Design-Build Done Right®?
A. Universal Ethical Conduct + Demonstrated Competence + Supporting Diversity, Equity & Inclusion
B. Lowest responsible bidder wins
C. Owner completes design to 90% before procurement
D. All risk is transferred to the Design-Builder
8. Best Practice for “Design-Build Oriented Procurement Plan” recommends providing proposers with the draft
design-build contract at the:
A. RFP phase only
B. RFQ phase
C. After shortlist
D. After award
9. In the execution phase, Design-Build Done Right® emphasizes:
A. Owner-directed changes for every design decision
B. Waiting until 100% design to involve trade contractors
C. Separate commissioning consultant hired by Owner only
D. Iterative design commitment, trend management, co-location where possible, and proactive dispute
avoidance
10. The Red Flag Exercise handout asks teams to classify items as GO/NO-GO red flags. Item 4 (Owner
provides 30% complete plans; successful A/E-GC proposer must complete them and assume full responsibility
for accuracy) would most likely be classified by experienced teams as a:
A. Non-issue
B. Best practice
C. GO red flag (we can live with it, but it’s risky)
D. NO-GO red flag (cannot live with it)
Section 3: Procurement, Progressive Design-Build & Red Flags
11. In Progressive Design-Build (per the Deeper Dive), the design-builder is typically selected primarily on:
A. Lump-sum price at time of selection
B. 60% design submittal
C. Low-bid after full design
D. Qualifications (QBS or heavily weighted), with price negotiated later after validation phase
12. A key advantage of Progressive Design-Build over traditional Best Value Design-Build is:
A. No off-ramp option for Owner
B. Owner must accept the first price proposal
C. Design-builder assumes all environmental risk upfront
D. Validation phase allows collaborative definition of realistic scope/schedule/budget before price commitment
13. Which item from the Red Flag list is most likely a NO-GO for most Design-Build teams?
A. Stipend not provided
B. Budget range of $50–100M provided
C. Performance specification (Div 2-16) provided
D. Owner has developed plans to 85% complete, then assigns its A/E to the DB team for “complete
responsibility” while proposers only price construction
14. In the Ostrich Egg negotiation activity (Day 3 handout), the key learning points include:
A. Price is always the only factor
B. Always make the first offer
C. Never disclose your interests
D. Trust, common values/shared purpose, sharing information, asking good questions, and integrative (win-win)
solutions (yolks vs. shells)
15. DBIA’s position on Virtual Design & Construction (VDC) states that VDC is best enabled by:
A. Traditional Design-Bid-Build
B. Owner completing 100% BIM before procurement
C. Separate BIM consultant hired by Owner only
D. The whole-team approach inherent in Design-Build Done Right®
Section 4: Contracts, Risk, Ethics & Collaboration
16. Per the Code of Professional Conduct (Rule 3.1), if a material conflict of interest arises, a Professional must:
A. Ignore it if it benefits their firm
B. Only disclose after award
C. Transfer the conflict to a subcontractor
D. Disclose it promptly to affected parties and take appropriate action (remove cause or obtain written consent);
offer to withdraw if unresolved
17. Best Practice for Design-Build Contracts (Section II of Design-Build Done Right®): Contracts should be:
A. Fair, balanced, and clear, and should promote the collaborative aspects inherent in the Design-Build process
B. Heavily skewed to protect the Owner from all risk
C. Based on 100% prescriptive specifications
D. Oral only for speed
18. In the Red Flag Exercise, Item 13 (Maximum Allowable Price with design score reductions if items are
deleted to meet MAP) is typically viewed as:
A. Best practice
B. A red flag (GO or NO-GO depending on team risk tolerance)
C. Never a concern
D. Required by all public statutes
19. Post-award first steps in Collaborating for Exceptional Outcomes (Day 2) emphasize:
A. Immediately starting detailed design without validation
B. Owner directing all means and methods
C. Withholding the contract until 30 days after award
D. Alignment of expectations, project planning, and establishing integrated team dynamics
20. The DBIA Code of Professional Conduct (Rule 8.2) requires a Professional who becomes aware of conduct
that violates building codes or materially affects public health/safety to:
A. Do nothing if the client disagrees
B. Only document it internally
C. Bill the client extra for the issue
D. Advise against it, refuse to consent, and report to Owner and authorities unless resolved
End of Exam
Answer Key & Explanations (for self-grading – do not look until finished)
1. A 2. D 3. B 4. D 5. B 6. D 7. A 8. B 9. D 10. C
2. D 12. D 13. D 14. D 15. D 16. D 17. A 18. B 19. D 20. D