PW(MARR) PROJ. COMP. If the PW of any project under consideration is evaluated at the MARR, denoted PW(MARR), then the sign of the PW evaluated at the MARR will allow you to determine if the projects rate of return satisfies this minimum condition: Does your A/P land at the correct "one period before first payment"? Does your A/F land at the correct "at last payment"? Did you correctly shift any resulting values forward/back? 1000/year, 6% comp./year 1000/year, 6% comp./semi-ann. REPEATED LIVES APPROACH To find IRR, use trial and error method via given formula and solving for i*. Notice that it’s PW = 0 rearranged. If cannot be solved analytically (no factor matches), use linear interpolation. Linear interpolation: Use if don’t know N value that corresponds to i %. Find two N values that straddle the value needed at i. Use equation. If i* = MARR, the project is acceptable. For INDEPENDENT projects, do this for all projects. For example, take a project with MARR of 20%. Bring all cash flows to present: MUTUALLY EXCLUSIVE IRR PROJ. COMP Alt. 2 is preferable, cheaper than Alt. 1. STUDY PERIOD APPROACH If a project has a longer service life than what will be required of it, estimate its worth at the cut off point. Consider Alt. 1 & 2 from above, but the required service life is 10 years. Compare 10 years worth of both alternatives (Alt. 2 will be cut down): NOTE: FOR THIS APPROACH, DIFFERING SERVICE LIVES ARE NOT REQUIRED. The only requisite for this approach to be appropriate is that a project service life exceeds the required service period. PAYBACK PERIOD APPROACH Payback period can be used to compare two projects to each other. The project with the shorter payback period is more ideal. For projects with a constant cash flow, use the equation given. Let’s suppose the current interest rate is 12% compounded semi-annually. What is the worth of a bond maturing in 15 years with a face value of $5,000, a semi-annual coupon and a nominal coupon rate of 7%? Coupon payments are unchanged since they are determined by the coupon rate and the face value. If asked for current value of bond, it means value of the bond with the time left on it. If the first payment is immediate, do not apply interest to it. Payments left after 10 years, with i = 4%: Turn PWr into x * PWoutp, solve for x. Remember to bring all cash flows to PW. Remember, A payments will be the same during all the cash flows. BRING EVERYTHING TO SAME TIME, PERIOD 0. Projects for whom the IRR = MARR have a marginally acceptable rate of return. A project for whom IRR > MARR is associated with situations where PW(MARR) > 0. Setup the equation like so, then solve for i*: - If PW(MARR) = 0, then the project earns the same rate or return as the MARR, and it is marginally acceptable. - If PW(MARR) > 0, then the project earns a higher rate of return than the MARR and it is acceptable. - If PW(MARR) < 0, then the project earns a lower rate of return than the MARR and it is not acceptable. If cash flows match with comp. rate, use r/m INDEPENDENT IRR PROJ. COMP. PW(MARR) > 0, project is acceptable When annual savings or inflows are not constant, the payback period is computed by deducting each period of savings from the first cost, keeping track of the cumulative balance of the project, until the first cost is fully recovered. This method can be performed with AW(MARR) or FW(MARR). All rules remain the same, but take the cash flows to be annuities or in the future, respectively. For example, consider a project that has a first cost of $20,000 and annual savings that follow an arithmetic gradient series increasing by $1,000 increments with the first cash flow in period 2. What is the payback period for this project? When comparing different projects with IDENTICAL service lives, use the above method for each project. With DIFFERING service lives, use the repeated lives approach, study period approach, or simply AW(MARR), as the length doesn’t matter when looking at AW (all payments are the same). Repeated Lives Approach: repeat projects as needed until their lengths are the same, then compare. For ex., if project one lasts 5 years and project two lasts 10, repeat project one twice (common multiple) in PW(MARR) calculations. Can be done with future worth too. Only compound first costs of coming projects. Study Period Approach - cut down longer project length to that of the shorter project by estimating value of the longer project after the cutoff date. If the cash flows were constant, then: 5k/6k = 5/6 , so PP is 6 and 5/6 years. For MUTUALLY EXCLUSIVE projects, do NOT do the above method and simply pick the project with the best IRR. Use incremental IRR method: - Rank each alternative project by their first cost - Find the IRR for the lowest first-cost alternative - If that project has an IRR that exceeds the MARR, then it is seen as the “current best candidate.” Otherwise discard and move to next candidate. Find the incremental investment by subtracting the cash flows, period by period, of the current best candidate from the challenger. This is the incremental investment. - Find the IRR of the incremental investment. If the incremental IRR>MARR, then the current defender is discarded and the challenger becomes the new defender. If the incremental IRR<MARR, challenger is discarded, and the new challenger is the next most costly project. The comparisons between alternatives happen in pairs. The incremental investment and then incremental IRR are calculated for only two alternatives at a time. ERR Marginal Analysis With atypical cash flows, sometimes a factor can appear more than once when solving for IRR. This will result in a quadratic, which cannot apply. Instead, find the ERR Once an asset has been installed and has been operating, the costs of installation, and all other costs incurred up to that time which cannot be recovered, are no longer relevant to any decision to replace the current asset. These costs are referred to as sunk costs. Therefore, EAC must be modified to fit this new situation: PRECISE ERR METHOD - look at the cash flows linearly, and create two blocks. A receipt at time 0 helps pay off a disbursement at time 1, so combine these two into a single net disbursement/receipt. Basically, turn non-simple cash flow into simple cash flow: Our goal is to find the minimum value in the concave-up graph of EAC values for both defender and challenger. It is important to TURN ALL COSTS into positives, and TURN ALL BENEFITS into negatives in the cash flow diagram. Remember to always assume you sell at salvage value for that time period, and if not, add it back in as a cost in the next time period for the cash flow diagram. Then use same method as if solving for IRR. APPROXIMATE ERR METHOD - net all receipts forwards to the final cash flow at rate = MARR. Net all disbursements forwards to the final cash flow at rate = i*ea. Set the two future worths equal to each other, then solve for approximate ERR. USE THIS METHOD PRINCIPALLY When i∗ea>MARR, both ERR and approximate ERR indicate the project is acceptable. When i∗ea<MARR, both ERR and approximate ERR indicate the project is not acceptable. IF EAC at n+1 < EAC at n, n is not the economic life of the project. For example if n = 1, then 1 is not the economic life, and n = 2 must now be compared to n = 3. See example question: The Jiffy Printer Company produces printers for home use. Jiffy is considering installing an automated plastic moulding system to produce parts for the printers. The moulder itself costs $200k and the installation costs are estimated to be $50k. Operating and maintenance costs are expected to be $300k in the first year and to rise at 5% per year up to a maximum of seven years. Jiffy estimates depreciation will follow the declining balance model using a rate of 40%. The moulder’s costs are fixed (do not vary with production levels) and do not include material costs. Jiffy’s MARR is 15%. Jiffy has an indefinite need for the service. How long should Jiffy keep a moulder before replacing it with a new model? EAC1=250,000(F/P,15%,1)−200,000(0.6)+300k=467,500 Balance Sheet REMEMBER: if O&M costs do not increase monotonically, 1 year rule cannot be implemented. Gives a snapshot of an enterprise’s financial position at a particular point in time, normally the last day of an accounting period. Data included referred to as “across variables”, which are measures of the value of assets such as cash, inventory, and equipment, the level of a company’s indebtedness, and the amount of equity accruing to a company’s shareholders. The left column lists the assets (current and long term), the middle column shows pertinent numbers for a given asset (e.g., equipment less the accumulated depreciation of that equipment), and the right column shows subtotals for each asset category, with a total amount in the last row. Any accumulated depreciation needs to be deducted from buildings and equipment. Land is not subject to depreciation. The total assets must be equal to the total liabilities and owners’ equity. Liabilities, claims on the business’s assets by non-owners, are divided into current and long-term liabilities. Current liabilities are debts that are normally paid within a year. Examples include accounts payable, taxes, wages payable, bank loan payable, etc. Long-term liabilities are debts that are normally paid beyond the current year. The owners’ equity measures the difference between assets and liabilities, and it is a measure of the company’s worth to its owners, or shareholders. Income Statement Summaries an enterprise’s revenues and expenses over a specified accounting period. The income statement is comprised of “through variables” such as revenues, expenses, income before taxes, taxes, and net income. In general, the major components of the income statement are revenues, expenses, and profits/incomes. When calculating EBIT, only the operating expenses of the business are deducted from revenues. Income tax and interest on loans are excluded from this measure because they are not directly associated with the sales and operating expenses that are within the control of managers. Any sources of revenues and expenses are each separately totaled, and then total expenses are deducted from total revenues to derive income before taxes. Taxes are then deducted from income before taxes to derive the net income.