1. What is project management?
Application of knowledge, skills, tools, and techniques to meet project requirements.
2. List the five PMI Process Groups.
Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
3. What is a project?
A temporary endeavor undertaken to create a unique product, service, or result.
4. What is a program?
Related projects managed in a coordinated manner.
5. What is a portfolio?
Collection of projects, programs, and operations managed as a group.
6. What is a project life cycle?
The series of phases that a project passes through from start to completion.
7. Difference between predictive and adaptive life cycles?
- Predictive: scope, time, and cost defined early.
- Adaptive: iterative and flexible.
8. What is a deliverable?
Any unique and verifiable product, result, or capability.
9. What is a phase gate?
A review at the end of a phase to decide to proceed, modify, or terminate.
10. What is benefits management?
Planning and measuring the benefits to be delivered by the project.
50 Exam Questions with Answers
1. What process formally authorizes the start of a project?
Answer: Develop Project Charter.
2. What is the purpose of planning?
Answer: Establish the scope, refine objectives, and define the course of action.
3. Which process focuses on completing the work to satisfy requirements?
Answer: Executing.
4. Which Process Group monitors progress?
Answer: Monitoring and Controlling.
5. When is a project considered complete?
Answer: When objectives are met, cannot be met, or project is terminated.