Document Numbering Procedure H.P.P Project Rev.: 00 Date: 97/3/8 Doc. No.: 1- Purpose and scope: In order to ensure that the ability of identification and tracking of all H.P.P project documentation and technical data exist, all documents are numbered according to the project document numbering procedure that described below. Also, on all documents, client’s document number shall be written by the contractor. 2- Definition: Client: DSDA Co. Contractor: Any person, firm or company, employed by Client to perform any work or duty on their behalf. 3- Document Numbering Structure: AAX – A– AA – A – AAA – XX – XX AAX st 1 part H31 A nd AA A 2 part nd 3 part 4 part Phase ID System ID Discipline ID AAA XX XX nd 5 part nd 6 part nd 7 part Document Category Unit ID Serial No. nd 1st part: this part of document code is as bellow: Project Name: Salsal Moghan Pardis1 Pardis2 Bilaghan Azimiye Kordan 1st Part Code: SL1 MG1 PD1 PD2 BG1 AZ1 KD1 Project Name: Badinabad1 Badinabad2 KaniSib1 KaniSib2 KaniSib3 1st Part Code: BA1 BA2 KS1 KS2 KS3 2nd part- Phase ID: this part includes one numerical character and refers to phases of documents of project as following table. ID 0 1 2 3 4 Description Feasibility Study Phase Proposal Phase RFP (Request of Proposal) Design, Supply, Manufacturing, … Commissioning Phase General 3nd part- System ID: this part includes 2 alphabetical characters and is according to following table. System System Description (related to the power plant) ID HE TU GO IV HYDROMECHANIC EQUIPMENT HYDRAULIC TURBINE GOVERNER INLET VALVE Document Numbering Procedure H.P.P Project Rev.: 00 Date: 97/3/8 Doc. No.: System ID System Description (related to the power plant) MA CR LE GE BU EA HV PT EP IC CS RP GN MECHANICAL AUXILIARY EQUIPMENT CRANE LIFT & ELEVATOR GENERATOR & EXCITOR BUSDUCT ELECTRICAL AUXILIARY SUBSTATION / TAKE OFF YARD / OVERHEAD LINE / HV CABLE POWER TRANSMISSION EMERGENCY PACKAGE INSTRUMENTATION & CONTROL COMMUNICATION SYSTEM RELAY & PROTECTION GENERAL System ID System Description (related to Civil) A*… DAM DAM INTAKE SPILLWAY POWER PLANT SURGE SHAFT (TANK) PENSTOCK TAILRACE BASIC STUDY GENERAL AD DI SP PP SS PN TR BS GN 4nd part- Discipline ID: this part includes one alphabetical character that shows engineering discipline according to following table. Discipline ID Engineering Discipline Description G E M I C A P General Electrical Mechanical Instrumentation and control Civil Piping & Layout & Process Planning 5nd part- Document Category ID: this part includes 3 alphabetical characters and shows the classification of documents according to following table. Document Category ID Document Category Description BBS Bar Bending Schedule BAS Basic of Design CAL Calculation Sheet DSH Data Sheet Document Numbering Procedure H.P.P Project Rev.: 00 Date: 97/3/8 Doc. No.: Document Category ID Document Category Description DES Description DSD Design Data DIG Diagram (Schematic, Logic, Connection) DWG Drawing FNB Final Book FRM Form DOC General Document INX Index ITR Inspection & Test Report ISO Isometric LYT Lay out & Arrangement SMB Legend & Symbols LST List MNL Manual & Procedure (Instruction, maintenance, etc.) MRQ Material Requisition MTO Material Take Off/ Bill Of Material PID P&ID PFD PFD PPN Plot Plan POS Purchase Order Specification RPT Report SCH Schedule SKT Sketch SPC Specification TBE TBE CTL Catalogue 6nd part- Unit ID: this part includes 2 numerical characters and identifies the unit number. In fact, this code illustrates that the document is related to which unit/ units of power plant, as following table. Unit Unit Description ID 01 02 03 04 00 Unit No. 1 Unit No. 2 Unit No. 3 Unit No. 4 Not related to any unit (General) Related to all units 7nd part- Serial No.: this part includes 2 numerical characters that shows serial number of engineering documents. This number will be from 00 until 99.