Name: Krupp Refrigeration, Inc., is trying to reduce inventory and wants you to install a Kanban system for compressors on one of its assembly lines. Determine the size of the Kanban and the number of kanbans (containers) needed. Setup Cost: $10 Annual holding cost per compressor: $100 Daily production: 200 compressors Annual usage: 25,000 (50 weeks X 5 days each X daily usage of 100 compressors) Lead time: 3 days Safety stock: 0.5 day’s production of compressors đ đ A) Size of container (Q) = √2đˇđ/đģ(1 − ) 100 = √2đ500đ10/100(1 − 200) = √10,000/(100đ50) = 100 B) Number of Kamban (Container) = Demand during lead time + Safety Stock / Size of Container = (3X100) + 100/ 100 = 300+100/ 100 = 400/100 = 4 Containers