DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 2 Index SECTION ITEM PAGE NO. 1.0 Purpose 3 2.0 References 3 3.0 Materials 3 4.0 Handling & Storage 3 5.0 Personnel Responsibilities 4 6.0 Tools & Equipment 4 7.0 Installation Procedure 8.0 Training 9 9.0 Appendix 9 5 to 8 DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 3 1.0 Purpose - - The purpose of this Method of Statement for the Installation of earthing and lightning protection system is to outline the step-by-step procedure, materials and labor required to undertake the works in a safe and controlled manner, complying with relevant specifications, standards, and codes of practice etc. The method statement shall be briefed to all appropriate operatives to ensure that they are aware of the sequence of activities and any Client/Consultant project specific requirements. A constant monitoring and supervision duty shall be undertaken by Innovo MEP to ensure work activities are carried out in accordance with the method statement. Any irregularities shall be immediately actioned. 2.0 References - Project Specifications Tender Drawings Material Submittal Risk Assessment 3.0 Materials - As specified in the approved material submittal. 4.0 Handling & Storage - Materials arrived at site shall be inspected/approved via Material Inspection Request. On receipt of the material at site, necessary precautions shall be taken for offloading, shifting & storage in line with manufacturer recommendation. Material shall be stored in a covered/dry space at all times. Material found not suitable for site use will be removed from site immediately. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 4 5.0 Personnel Responsibilities Project Engineers / Site Engineers Specific responsibilities include: - To monitor the workforce to ensure that they are carrying out the work as per QA/QC &HSE requirements. To ensure all the Foreman / Supervisors are briefed and understood the sequence of work / tasks to be carried out. HSE Officers Specific responsibilities include: - To monitor the implementation of health, safety, and environmental requirements. To ensure the areas are barricaded, walkaways and permit systems are in place. Supervisor/Foremen Specific responsibilities include: - To ensure that all operatives and appropriate subcontractors, if any, have been briefed as to the content of the method statement and the works. To adequately control the works as required. To ensure the works are undertaken in a safe manner. To ensure all operators are adequately trained in their respective works. Reporting any unsafe practices on site to the site team. 6.0 Tools & Equipment - Portable Hand Tools Portable Drill Machine Sledgehammer of bigger capacity Measuring Tape Marker Pen. Cleaning Tools Drill Rig Welding Machine Insulation Resistance Tester (Megger) Earth Resistance Measurement Instrument Safety Equipment such as Fire Extinguisher, Fire Blankets, etc. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 5 7.0 Installation Procedure Ø Pre-Construction activity for Earthing · · · · · · · Ensure that the work area is ready and safe to start the installation of the earthing system. Ensure that proper safety precautions are taken, safety clearance is obtained prior to starting the installation works. All delivered materials shall be inspected prior to usage. Ensure the materials are stored properly and there is no mark of damage or deformity of any kind before issuing the material to site from store. The Site Engineer/Site Supervisor will give necessary instructions to tradesmen and provide necessary latest approved shop drawings. The Site Supervisor/Foremen will also check that proper tools and equipment are available to carry out the work. The Site Supervisor and safety officer will explain to the tradesmen regarding safety precautions to be followed. Ø Installation of Earthing pits, Bars, Cables and Bonding v Earthing Pit Installation: · · · · · · · · Verify the dimensions of the Earthing Pits according to the approved shop drawings and material submittal. Verify the location of the Earthing Pits and bars as per the approved shop drawing. The location of earth pits to be coordinated with other services like underground drainage pipelines and other services. Adjacent earth electrodes shall be spaced as shown in the approved shop drawings. On the marked area work to be carried out by using hammer and driving stud for the installation of earth rods. Upon the installation of reinforcement steel bar for the raft the necessary protection for steel tube and earth rod should be provided. After completion of the installation of inspection pit concreting will be done around the inspection pits in close coordination with civil team. The rod seal and inspection pit cover will be installed with its accessories under the guidance of an earthing specialist. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 6 v Earthing Bar installation: · · · · · · · Verify the location of the Earthing bars according to the approved shop drawing. Verify the dimensions of the Earthing bar as mentioned in the approved material submittal. Use a tape scale to measure the position and the height of the Earthing bar as mentioned in the approved shop drawings. Use a spirit level to ensure the alignment of the Earthing bar. Using a drilling machine, drill for the fixation bolts at the marked points. The sizes and numbers of bolts, nuts and washers are as per the manufacturer instructions. Install the Earthing bar and firmly fix it using the screws. Verify the alignment of the Earthing bar after the final fixation using the spirit level. v Earthing Cables and Bonding Installation · · · · · · · · · · Ø The metallic frame of all electrical equipment shall be connected to the nearest earth bar through PVC insulated copper earth cable. The cross-section area of the earthing cable will be as specified on the approved shop drawings. The sheaths and armor of low voltage cables will be solidly bonded to the earth at both ends for multi-core cables and one end for single core cables. Crimp type lugs will be used and will be compressed by automatic tool to achieve correct pressure and crimp depth. Connect the earthing cable to the metallic parts of the equipment through the earthing point specified on the equipment casing. The earthing continuity for cable trays, ladders and trunking shall be maintained by earth links on the tray and trunk run shall be connected to earth bar with flexible earthing bonding link. Separate earth conductors to be taken from earth bars to the various metal equipment frames, including switch boards, transformers, stand by diesel generators, power factor correction equipment etc. The conductors shall be either bare copper strip stranded insulated cable as detailed on the attached drawings and/or specifications. Conductor sizes shall be a minimum of 25mm sq for equipotential bond and 6mm sq for supplementary bonds unless otherwise indicated on the drawings. Earth cable shall be secured to the main system earth bar by a threaded bolt and double nut arrangement, which requires a tool to disconnect it. Check properly that there is no insulation between the earthing cable terminal lugs and the metallic parts of the equipment. Pre-Testing of Earthing & Bonding · · All the earth electrode in the earth pits is to be visually inspected to ensure proper installation and connections. All the protective conductors from the earth electrode to the main panel boards and distributions are to be visually inspected to ensure proper installation and connections. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 7 Ø Measurement of earth electrode resistance · · · · · · A proprietary earth electrode calibrated test device should be used. Auxiliary earth spikes should be applied at least 5m apart and 5m distant from the electrode under test. An earth resistance value of less than 1 ohm is required for the DEWA earth pits. The same shall be done with the megger tester device. An additional number of electrodes may be required (or deeper electrodes) to achieve the required earth resistance value. Sufficient time should be allowed if special chemicals or salts are added to the ground to improve the earth’s resistance values. Details of the proposed earth pits, quantity of rods per pit and number of earth pits shall be as per the requirements. Ø Continuity Test · · · The continuity resistance of protective conductors is to be measured with DC ohm meter and values to be recorded and verified with the permissible limits to ensure proper earthing. The continuity test between the main earth terminal at the distribution board and the metallic frame works of farthest equipment to be measured a DC ohm meter and the value to be recorded and verified with the permissible limit to ensure proper bonding. The same shall be checked between the earth pit and the farthest equipment / cable tray / trunking using a DO ohm meter and the value to be recorded and verified with the permissible limit to ensure proper bonding. Ø Pre-Installation for Lightning protection · · · · · Ensure that all safety requirements are in place in accordance with the approved safety plan. Ensure that the latest revisions of the approved shop drawings are being used. The latest drawings shall be issued to the concerned people and the superseded drawings shall be surrendered to the document controller. Ensure that all materials used have passed the material inspection request and have no damage or defect. Ensure that the materials used are as per the approved material submittal. Any non-conforming materials must be labeled by storekeeper and returned to quarantine area in accordance with the procedure. Before starting welding works between two steels, the permit to work shall be obtained from the safety officer. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 8 Ø Installation of Lightning Protection Tape · · · · · · · · · · · · · · Start to weld the dedicated steel for lightning protection system in the column. It must be followed up to the roof and the dedicated steel bar will be marked for easy reference. The air termination network will be supported by square tape clamp at every node/junction and test clamp for each down conductor using pre-welded test point. After completion of welding works, Welded rebars are marked and checked for continuity and will be offered for a consultant’s inspection. Copper tape shall be with dimensions as per project specification and approved material submittal. Mark the location of all the fixing clamps used to fix the copper tape over the fence. Install the copper clamps on the fence using the drilling machine and hand tools. All the fixing clips for the copper tape Shall be as per approved material submittal and shall be fixed at an interval of 500mm. Fix the clamps using the proper bolts as per the manufacturer recommendation. Connect the lightning protection to the exposed mechanical equipment on the roof through the cable to tape clamps as per the approved shop drawing. Make sure that the pathway for the cable connected to the equipment is finished, inspected and approved. Install a cable terminal lug on the cable end that will be connected to the equipment using a proper crimping tool. Connect the cable to the equipment on the specified point on the equipment casing. Tight the cable terminal using hand tools and accessories provided by the manufacturer. Check the overall fixation of the clamps and cables. Ø Test Point · · All test joints shall be provided in all down conductors at low level, at a height which is accessible without using any access equipment or at approximately 450 mm from finished floor level as per the approved typical details. Provide a testing point to enable resistance measurement as indicated on the shop drawings. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 9 8.0 Training All records of training shall be maintained. Prior to these works commencing, a review of the activities shall be undertaken in association with the operatives undertaking the duties. This will identify where additional training over and above existing knowledge or experience is required. This Method Statement shall be communicated to appropriate personnel connected with the undertaking of these works. This is essential to the safe and successful completion of the operation.The method statement shall be signed every time the operatives are briefed. 9.0 Appendix 1. ITP 2. Checklist 3. Risk Assessment AVA at PALM JUMEIRAH INSPECTION & TEST PLAN Activity Prepared by: Checked by: Approved By: Date: Date: Installation of Earthing and Lightning Protection System Inspection & Test Plan Number: Ihab Eid Date: 20-Sep-23 SECTION 1 - REFERENCES AND CONTROL DOCUMENTS Method Statements Installation of Earthing and Lightning Protection System Drawings Specifications SECTION 2 - INSPECTION & TEST PLAN Hold Point: Stop work until inspected and QA documents approved. Witness Point: Inspection Requested - work can continue Surveillance Point: Ensure the activity is reviewed to allow works to continue. Review Point: Results to be reviewed by a 2nd party. PRIMARY CONTROL SECONDARY CONTROL Inspection Details Consultant Code Frequency Check sheet/Verifying Document innovo Code Method Statement ALL AREAS Approved Method Statement HOLD REVIEW N/A Material Submittal ALL AREAS Approved Material Submittal HOLD REVIEW N/A Shop Drawing ALL AREAS Approved Shop Drawing HOLD REVIEW N/A ALL DELIVERIES MATERIAL INSPECTION HOLD HOLD N/A Safety Clearance ALL AREAS PROJECT SAFETY PLAN HOLD WITNESS N/A Inspection for installation of Earthing or Lightning Protection ALL AREAS HOLD HOLD N/A Inspection for Earth Resistance Measurements of Earthing or Lightning Protection ALL AREAS HOLD HOLD N/A Activity to be checked Client Code Document Review Material Verification Material Deliveries Installation Inspection METHOD STATEMENT WORK INSPECTION REQUEST METHOD STATEMENT WORK INSPECTION REQUEST SECTION 3 - CLOSE OUT This work has been undertaken and completed in accordance with this ITP and all associated reference documents. Completed check sheets etc. are available. Name: Ihab Eid QA/QC Department Site Representative Date: 20/09/2023 Project: AVA – THE PALM PROJECT Client : OMNIYAT Sub Consultant: RAMBOLL Main Contractor: INNOVO BUILD MEP Contractor: INNOVO MEP Lead Consultant: U+A MST Ref. no: i119 Job No: CHECKLIST for Earthing and Lightning Protection System Work Item 1.0 Pre-construction 1.1 Material Statement is Approved 1.2 Material Submittal is Approved 1.3 Shop Drawing is Approved 2.0 Grounding and Bonding System 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 Dimension of the Earthing bar as per approved shop drawings and material submittal. Dimension of the earthing bar is complying with the approved shop drawings The earthing bar is installed in the right location according to the approved shop drawings The earthing bar is aligned and fixed properly The cross-section area of the earthing cable is matching with the approved shop drawings The earthing cable is well tightened to its relevant equipment body No insulation is being between the earthing cable terminal lug and the equipment body The earthing cable is properly connected to the electrical switchgear earthing bar 2.9 Connection to the equipment is carried out properly 3.0 Earthing System 3.1 3.2 3.3 3.4 3.5 3.6 Dimension of the Earthing rod/pit as per approved shop drawings and material submittal. Dimension of the earthing rod/pit is complying with the approved shop drawings The earthing rod/pit is installed in the right location according to the approved shop drawings The earthing pit is aligned and fixed properly The cross-section area of the earthing cable is matching with the approved shop drawings The earthing cable is well tightened to the rod using the approved clamp Contractor's SE/PE Contractor's QA/QC Remarks Project: AVA – THE PALM PROJECT Client : OMNIYAT Sub Consultant: RAMBOLL Main Contractor: INNOVO BUILD MEP Contractor: INNOVO MEP Lead Consultant: U+A MST Ref. no: i119 Job No: CHECKLIST for Earthing and Lightning Protection System Work Item 4.0 4.1 4.2 4.3 Contractor's SE/PE Lightning Protection System Fixing clamps are installed properly in their locations Fixing clamps are fixed properly according to the manufacturer recommendations Spacing between the fixing clamps had been verified and accepted 4.4 Routing of the copper tape is verified and accepted 4.5 Connection between the copper tape and the bare copper cable, if any, is carried out properly 4.6 Ensure Test point and its back box installed properly 4.7 Copper tape is fixed properly along all the route 5.0 Earth Resistance Measurement 5.1 Ensure that Earth electrode test device calibration certificate is valid 5.2 Earth resistance values is as per the specified value For Site/Project Engineer: For QA/QC: Name: Sign: Date Name: Sign: Date Contractor's QA/QC Remarks 119 (AVA AT PALM) Document Reference: INNOVO-MEP-ELE-RA-004 Document Title: Rev. 00 Risk Assessment for Installation of Earthing and Lightning Protection System Page 1 RISK ASSESSMENT ACTIVITY: Installation of Earthing and Lightning Protection System LOCATION: Dubai Palm Jumeirah PROJECT: EQUIPMENT TO BE USED ▪ ▪ ▪ ▪ ▪ ▪ ▪ I-119 AVA AT PALM MATERIALS TO BE USED ▪ ▪ ▪ Portable Hand Tools Portable Drill Machine Sledgehammer of bigger capacity Measuring Tape Marker Pen Cleaning Tools Drill Rig ▪ RA No. INNOVO-MEP-ELE-RA-004 DATE: 25/09/2023 REVISION STATUS Welding Machine Insulation Resistance Tester (Megger) Earth Resistance Measurement Instrument Safety Equipment such as Fire Extinguisher, Fire Blankets, etc. REVISION NUMBER Rev REVISED DATE 00 POTENTIAL HAZARDS / CONDITIONS CONSIDERED (TICK BOX) PERSONS AT RISK (TICK BOX) WORKING FROM HEIGHT ELECTRICITY HAND TOOLS TASK LIGHTING CONFINED SPACE EXCAVATION/BACK FILLING EMPLOYEES PUBLIC FALLING MATERIALS MANUAL HANDLING PEDESTRIAN FATIGUE NOISE & VIBRATION HAZARDOUS SUBSTANCES SUBCONTRACTORS VISITORS MACHINERY/EQUIPMENT SLIPS / TRIPPING SITE VEHICLE SECURITY HEAT EXHAUSTION ENVIRONMENTAL (Use Environmental Impact- Severity Rating Section for these HAZARDS) FIRE RISK ADVERSE WEATHER ACCESS/EGRESS LIFTING OPERATION OTHERS (client & consultant) STAKEHOLDERS MATERIALSTORAGE MANDATORY HSE REQUIREMENTS (TICK BOX) SAFETY INDUCTION ADEQUATE VENTILATION WORK PERMIT PROPER TOOLS / EQUIPMENTS PROPER SUPERVISION TOOLBOX TALK DUST CONTROL PROPER PPE SAFE WORKPLACE PROPER BARRICADE AND WARNING SIGN IN THE AFFECTED AREA PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENT (TICK BOX) SAFETY HELMET GOGGLES / SAFETY GLASSES RESPIRATORY PROTECTION / BREATHING APPARATUS GLOVES OVERALLS SAFETY BOOTS EAR PLUGS / DEFENDERS FULL BODY SAFETY HARNESS HIGH VIZ SAFETY JACKET WELDING/METAL CUTTING PPE TO REFER OTHER RISK ASSESSMENTS 1. N/A Page 1 of 10 119 (AVA AT PALM) Document Reference: INNOVO-MEP-ELE-RA-004 Document Title: Rev. 00 Risk Assessment for Installation of Earthing and Lightning Protection System Page 2 RISK LEVEL H (HIGH-Potential to cause death, permanent injury or M (MEDIUM – Potential to cause loss time injury or Long-Term Severe Permanent Environmental Harm) Environmental Impact) SEVERITY (S) Health & Safety CLASS OF RISK (L X S) Environmental Impact 0 = Impossible 0 = No injury Short Term < less than 1 month 1 = Improbable 1 = Minor – (FAC) 0 = No harm 2 = Remote 2 = Major - (MTC) 3 = Minor HIGH 3 = Probable 3 = LTI (Lost Time Incident) Long Term > Greater than 1 Month 4 = Occasional 4 = Disabling Injuries 4 = Major 5 = Frequent 5 = Fatality 5 = Catastrophic NOTE: = 15 - 25 MEDIUM = 07 - 14 LOW = 01 - 06 5 5 10 15 20 25 4 4 8 12 16 20 3 3 6 9 12 15 2 2 4 6 8 10 1 1 2 3 4 5 1 2 3 4 5 X SEVERITY (S) 1. Risk assessment must be addressed to workers by the work in charge before starting job. 2. Risk assessment is a continuous process hence to be reviewed depending on activity and risk involved RISK ASSESSMENT TEAM Sr. No. 1 RISK MATRIX LIKELIHOOD (L) LIKELIHOOD (L) L (LOW – An injury treatable with First Aid or Short-Term Environmental Impact) NAME OFFICIAL SIGNATORIES FOR THE RISK ASSESSMENT DESIGNATION Dinoop Chandrasekharan MEP Project Manager Pardeep Singh HSE Coordinator Assessed By (Name): Signature: Date: 09/25/23 2 3 4 Assessed By (Name): Signature: Date: 09/25/23 5 Page 2 of 10 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System HAZARD HARM CONTROL MEASURES LXS L M 2 • Fall • Personnel injuries • Access/ Egress • Property damage • Slipping and • slip & trip Tripping Shifting and lifting of Earth rod pipe/ fitting accessories to workplace (copper strip must be cut into pieces as required length) • Personnel injuries • Property damage • Back and hand injuries 3x4 4x4 H CONTROLLED BY WHOM RESIDUAL RISK LXS L M 12M • PTW must be obtained. • Follow main contractor PTW system procedures. • Toolbox talks to be given for task. • Without site safety induction, nobody is not allowed to enter the site • Access to the site should be well sign SE/PE/FM/ posted. SO • Clear emergency route should be designated. • No material should be store and stack in access. • Pedestrian access should be designated and clear • Minimum mandatory PPE shall be worn at site/task area 1x4 4L 16H • TBT will be conducted prior to start the work • Ensure access is clear of obstacles • Bend knees and lift using leg power not back • Do not twist the body always face the direction of travel • Make sure you have a good grip before lifting the weight 1x4 4L Access to the work area 1 Page 3 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 Supervisor/ Foreman Page 3 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System HAZARD HARM CONTROL MEASURES LXS L M • Manual handling • Sharp edges Material Storage on the roof area (Copper strip & Related Materials) 3 • Fall of materials • Slip Trips of pedestrian’s due to improper stacking. Page 4 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 • Personal Injury • Property Damage 4x4 16H H CONTROLLED BY WHOM • Take care of Pinch point / sharp edges while handling • Protect the sharp edges with suitable materials (cotton waste, waste cloth, paper’s Etc.) • Ensure after cutting sharp edges must be removed by using file • Safety gloves to be worn (Rigger Type) • Close supervision & monitoring should be on place. • Provide plywood board as a platform for material storage at roof area • Stored materials must be properly tied with nylon rope for preventing slip and fly due to the heavy win • Always consider the weather changes SE/PE/FM/ and take precautions • Properly stack the material and protect SO the material from damage • Do not stack the materials to the access • Do not store the material near edge area • Provide temporary barricade the material storage area with proper signage • Coordinate with main contractor for safe stacking /storage of materials in roof area RESIDUAL RISK LXS 1x4 L M 4L Page 4 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System HAZARD Page 5 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 HARM CONTROL MEASURES LXS L M H CONTROLLED BY WHOM 4 Working on Roof Levels for installing Lighting/Earthing systems • Falling objects Falling person s 5x5 25H • Work at height permit will be followed. • Always co-ordinate with main contractor for working in roof area. • Work shall not proceed on roofs until adequate edge protection & access/egress is in place & a safety clearance form has been completed by concern supervisor. • Red/white tape or rope does not qualify as adequate edge protection. SE/Forman/ • All workers must wear safety harness Supervisor/ when working on roof and make sure SO safety belt hooked with life line • For temporary life line in roof area coordinate with main contractor • All tools/equipment’s will have tag lines to prevent falling from roof. • Tool box talk to be given • MSRA briefing must be given to all work force. • Assign watchman in that area for preventing unauthorized entry 5 Installation of Lighting/Earthing (air terminal/ copper tape) • Falling from heights could lead to fatalities. • Falling objects causing serious injuries. 5x5 25H • Work at height permit will be followed SE/Forman/ • Toolbox talks to be given for safe work at Supervisor/ height. RESIDUAL RISK LXS L M 1x5 5L 1x5 5L Page 5 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System HAZARD HARM CONTROL MEASURES LXS protection by using scaffold L M • Fractures • Property damage • Use of uninspected scaffold • Poor Platform • Failing to use harness and double hook lanyard. • Falling materials and tools from height 6 Installation of Lighting/Earthing protection by using Ladder Page 6 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 • Collapse • Fall from heights • Fatality • Minor /Major injuries 5x5 25H H • Scaffold must be erected/dismantling by Certified experienced person. • Green tag must be on scaffold to climb on. • Area at ground level should be barricaded off and proper signage. • Build scaffold on even and solid surface. • No material stacked or kept on scaffold. • While working on platform, all tools needs to have lanyard on that are attached to person. • Base plates fix firmly to ground. • Inspection of harness and lanyard before use. • Proper Supervision on the place. • Maintain good housekeeping in working platform. • Ladder will only be used other means of access is restricted. • Ladder will be inspected and record to be maintained. • Ladder must be used only for short duration work or for inspection purpose. • Ladder will be footed always. • One person is permitted to work on a ladder. CONTROLLED BY WHOM RESIDUAL RISK LXS L M Scaffold inspector/ SO SE/ Forman/ Supervisor/ SO 1x5 5L Page 6 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System HAZARD HARM CONTROL MEASURES LXS L M Use of Electrically Powered tools for drilling activity 7 8 • Working with • Serious Personal Injury • Property Damage damage electrical tools • Electric shock • Hand injury to the operatives Using Hand tools for installation Page 7 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 • General impact (puncture, cuts, abrasions injuries) • Hand Injury 4x5 20H 3x3 9M H CONTROLLED BY WHOM • Ladder may not use close to any access & egress / edges. • Top two run must be covered. • While using ladder it must be secure or hold by another person. • Only competent persons shall be use electrically operated equipment. • User shall ensure that electrically operated tools and equipment are inspected daily and that damaged or nonfunctioning equipment is returned to stores immediately. • All electrically operated tools and equipment’s shall be 110 Volt. Sup/FM • Lifting/lowering of tools should do by hand or ropes not with extension Leads/cables. • All power tools must be inspected by daily and monthly. • Color coding must be placed as per the HSE plan. • Barricade the area and provide proper signage. • TBT must be given to all operatives. • Adequate supervision must be taken SE/PE/SUP carry. RESIDUAL RISK LXS L M 1x5 5L 1x3 3L Page 7 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System HAZARD HARM CONTROL MEASURES LXS L M Testing of Lighting/ Earthing system • Electrocution • Fatality • Work with • Fire exposed Live • Damage to the equipment Conductors • Burns • Electrocution • Improper selection and training H CONTROLLED BY WHOM RESIDUAL RISK LXS L M • Competent person must be appointment for the specific task. • No homemade tools shall be used. • Safety gloves (dotted cotton gloves) mandatory. • Tools shall be of good quality and shall be replaced if faulty or broken. Lighting / Earthing Protection • earth rod / clamps/copper tapes (Hammer/scre w/spanner/scre w driver etc.) 9 Page 8 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 5x5 25H • Permit holder/ watchmen shall ensure no unauthorized entry. • LOTO system must be follow (if required) • Permits must be obtained from the relevant authorities for testing/commissioning. • Control measure in the permit system must be implemented on the work area. • All the testing equipment must be T/C Eng /SE /PE/SO calibrated with valid certificate. • Only competent persons must take carry this activity. • Safety signs and barricading must be used. • Appropriate personal protective equipment Safety shoes, Helmet goggles and Hand gloves, must be provided and used. 1x5 5L Page 8 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System HAZARD Page 9 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 HARM CONTROL MEASURES LXS L M H CONTROLLED BY WHOM RESIDUAL RISK LXS L M • In case of emergency follow the main contractor emergency response plan. 10 • Lack of Supervision • Poor quality of work • Chance of accident /incident • Property damage 4x4 16H 11 • Adverse Weather Condition. Heat Stress, Fog, Sand Storms and Rain • Heat Stress, • Heat Exhaustion • Muscle cramps serious injuries • Property damage. 4x4 16H • 12 Housekeeping • • Slip, trip & falls • Heavy Materials. • Personal Injury • Property Loss • Fire 3X4 12H • Ensure the availability of competent supervision at work place at all times during all task activities. • DSTI (Daily Safety Task Instruction) should be provided to the workers prior to the commencement of activity. • All personnel will be provided with Appropriate PPE (safety Shoes Helmets jackets etc.), • Cool drinking water and electrolyte solution to be provided during all shift activities. • Compliance with summer break law. • First aid kit and first aider will be provided on site always. • Shaded and adequately ventilated rest area & regular breaks will be provided to avoid heat exhaustion. • Adequate PPE provided. • Adequate access and egress • Proper cable management • Adequate training • Adequate illumination PE/SE/FM/ SO 1x4 4L PE/SE/FM/ SO 1x4 4L SE/FM/ CH 1X4 4L Page 9 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of Earthing and Lightning Protection System Page 10 Installation of Earthing and Lightning Protection System RISK S. N Rev. 00 HAZARD HARM CONTROL MEASURES LXS • Spillage • Fire Hazards L M H CONTROLLED BY WHOM RESIDUAL RISK LXS L M • Adequate material storage area. • Clear access to firefighting equipment. • Manual handling training. • Waste management/ Disposal and clear ups will be assured during and at the end of every shift - pictures to record site conditions at hand over to be implemented should it be required. Engineers Comments (HSE) 1. Ensure proper workplace isolation is maintained during activities such as lifting, loading/unloading, erection, assembling/dismantling, etc., and implement Foreign Object Debris (FOD) controls at site. 2. Guarantee effective supervision and Health, Safety, and Environment (HSE) monitoring throughout the activities. 3. Prioritize safe working at heights and strict adherence to lifting procedures. 4. The Temporary Works (TW) coordinator/lifting supervisor should confirm the presence of an approved task-specific lifting plan before commencing lifting activities (non-routine). 5. Maintain records of Permit to Work (PTW) both internally and externally at the site. 6. The Responsible Engineer, permit to work coordinator or Temporary Works Coordinator must oversee pre-task briefings and ensure activities align with safe working procedures. 7. INNOVO MEP should establish and communicate Fire and Emergency Preparedness measures to operatives and records of communication to be maintained. 8. Strictly adhere to statutory authority guidelines, including Dubai Municipality Requirements and Client HSE guidelines. Page 10 of 10 H METHOD STATEMENT SUBMITTAL PROJECT NAME: AVA AT PALM JUMEIRAH DUBAI Contract: INNOVO BUILD Ref: 21115-INB-000-ZZZ-MST-EX-700005 PROJECT NO: i119 Package No: Date: 25/09/2023 Method Statement for Installation of PVC Conduits and Subject: Accessories To The Engineer: U+A Attached Documents For Approval Signature:______________ For Information ENGINEER'S COMMENTS Approval Status A. Approved [ ] B. Approved with Comments [ ] C. Rejected Revise & Resubmit [ RESIDENT ENGINEER DATE : Distribution: Head Office Client Form No. UA-SITE-FRM-003, Rev.03 - 08-08-2023 QS Others ] D. For Information [ ] DOC No. Rev. 00 Project AVA at PALM JUMEIRAH Page 1 AVA at PALM JUMEIRAH CLIENT: OMNIYAT LEAD CONSULTANT: U+A MEP CONSULTANT: RAMBOLL MAIN CONTRACTOR: INNOVO BUILD MEP CONTRACTOR: INNOVO MEP Method Statement for Installation of PVC Conduits and Accessories Record of Amendments Rev Date. Description of Revision Prepared By 00 20 Sep. 23 Release for approval Ihab Eid Reviewed/ Approved By DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 2 Index SECTION ITEM PAGE NO. 1.0 Purpose 3 2.0 References 3 3.0 Materials 3 4.0 Handling & Storage 3 5.0 Personnel Responsibilities 4 6.0 Tools & Equipment 4 7.0 Installation Procedure 8.0 Training 7 9.0 Appendix 7 5 to 6 DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 3 1.0 Purpose - - The purpose of this Method of Statement for the Installation of PVC Conduits and Accessories is to outline the step-by-step procedure, materials and labor required to undertake the works in a safe and controlled manner, complying with relevant specifications, standards, and codes of practice etc. The method statement shall be briefed to all appropriate operatives to ensure that they are aware of the sequence of activities and any Client/Consultant project specific requirements. A constant monitoring and supervision duty shall be undertaken by Innovo MEP to ensure work activities are carried out in accordance with the method statement. Any irregularities shall be immediately actioned. 2.0 References - Project Specifications Tender Drawings Material Submittal Risk Assessment 3.0 Materials - As specified in the approved material submittal. 4.0 Handling & Storage - Materials arrived at site shall be inspected/approved via Material Inspection Request. On receipt of the material at site, necessary precautions shall be taken for offloading, shifting & storage in line with manufacturer recommendation. Material shall be stored in a covered/dry space at all times. Material found not suitable for site use will be removed from site immediately. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 4 5.0 Personnel Responsibilities Project Engineers / Site Engineers Specific responsibilities include: - To monitor the workforce to ensure that they are carrying out the work as per QA/QC &HSE requirements. To ensure all the Foreman / Supervisors are briefed and understood the sequence of work / tasks to be carried out. HSE Officers Specific responsibilities include: - To monitor the implementation of health, safety, and environmental requirements. To ensure the areas are barricaded, walkaways and permit systems are in place. Supervisor/Foremen Specific responsibilities include: - To ensure that all operatives and appropriate subcontractors, if any, have been briefed as to the content of the method statement and the works. To adequately control the works as required. To ensure the works are undertaken in a safe manner. To ensure all operators are adequately trained in their respective works. Reporting any unsafe practices on site to the site team. 6.0 Tools & Equipment - Portable Electrician Hand Tools Hack Saw Measurement Tape Spirit Level Hammer Portable Drill Machine Portable Air Blower Nylon Fish Cord Rope Binding Steel Wire PVC Solvent Cans Thermocol Sheets Masking Tape PVC Conduit Bending Spring Vernier Caliper DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 5 7.0 Installation Procedure Ø PRE-CONSTRUCTION ACTIVITY v Ensure that the work area is ready and safe to start the installation and works commencement. v Prior to starting the installation, refer to the approved shop drawings to the area of installation and ensure that required materials are available at site as per approved material submittals. v Ensure the materials show no mark of damage or deformity of any kind and are free of dust before issuing the material from site store. v Ensure the thickness of the delivered conduits is as per the approved material submittal by Vernier Caliper. v Ensure that the issued materials are as per the approved material submittal / specifications and as per the requirements of the area shop drawings (Make, Size, Model type etc.). v Separate conduits will be installed for each installation i.e., Lighting, Power, Data, FAS, CBS or Security System, etc. Ø CONDUITING IN SLAB v Location of light points. Switch dropping, power points, Fire alarm. Emergency lights and all ELV Systems points will be marked on the slab shutter as per approved drawings after getting area clearance / Permit from HSE department and prior to start bottom layer steel. v PVC circular junction boxes & GI Back boxes as per the service requirement will be fixed on the marked locations in shutter with the help of nails hammered into the shuttering ply and bonded with binding wire over it to hold the back boxes. v Back boxes will be packed with Thermocol and masking tape prior to fix on shutter to avoid concrete ingress while pouring. v Secure and support conduits using suitable supports. v Pull boxes shall be provided for conduit runs exceeding 15m interval or after two right angel bends. v After completed the bottom layer steel, PVC conduiting will be done with standard conduit lengths. couplers etc. connecting the respective services junction boxes as per the approved service shop drawings, Conduit dropping for service outlets on wall will be routed through the hole made in slab shutter at the respective points for further extension through wall in later stage. v The jointing of PVC conduits will be done with suitable couplers and solvent cement. The PVC conduits will be bonded tightly to the back box / pull box with suitable adapters and accessories. Expansion couplers will be used for all expansion joints as clarified on the shop drawings. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 6 Ø THE JOINTING PROCESS OF PVC CONDUITS v Both joining ends of conduits will be cleaned from inside as well as from outside prior to applying solvent, then a thin layer of solvent cement to be applied to the inner surface of the coupler. v Push the conduit to end fully into the coupler by slight twisting action & remove the spilled or surplus solvent cement from around the joints. v Make sure the conduit has entered fully into the box spouts or couplers. v Make sure that the joint is tight enough and entry of water into the conduit through Joints is not possible. v Approved connectors / adapters will be used for connections to back boxes / pull boxes where required, the conduits will be manually bent by using suitable bending spring to the required radius without flattening or denting the conduits. v Insulating bushings or insulated throats at all conduit terminations to protect conductors will be used. v Joints and connections will be secured to provide maximum mechanical strength. v To facilitate easy cabling / wiring sufficient pull box or junction boxes will be provided every two 90degree bends. v In longitudinal straight runs the pull boxes /junction boxes will be provided in every 20 meters. v Close bunch of PVC conduits in slab will be avoided to maximum possible extent, Sufficient gap Will be provided between conduits at crossing. v A minimum 100mm gap will be maintained between electrical conduits and non-electrical services. v Ensure all open ends of the conduits are capped / plugged properly before concrete pouring. v Ensure caps are provided for unused knockout holes where blanks have been removed. Ø CONDUITING AND BACK BOX FIXING WITHIN CORE WALL v Once the vertical steel work completed mark the location and height of outlet as per the approved shop drawing. v Thermocol of bigger size than backbox on the steel to be installed for fixing back box after deshuttering, then extend required conduits from the box and connect to respecting loop. v Secure and support conduits using suitable supports. v After de-shuttering the backbox to do fixed in level or recessed with plaster thickness. v The work area should be clean and safe to take up subsequent activities. Ø CONDUITING AND BACK BOX FIXING WITHIN BLOCK WALL v Once the block wall completed mark the outlet location and conduit to be routed as per the approved shop drawing for wall chasing. v After completed the wall chasing and chipping by the civil contractor and marking of the plaster thickness on wall, required back box to be fixed. v Secure and support conduits using suitable supports. v Back box to be fixed with cement mortar in proper level with the help of spirit level, Leave the box for one day to set properly with block work. v Conduit to be extended from the box and connect to respecting loop. v In vertical wall. the conduits will run vertically from the back box & horizontal runs to be. avoided on walls as much as we can. v Ensure the recessed position of outlet box is accurate to allow for surface finish thickness and check for box installed in concrete walls. DOC No. Project Rev. 00 AVA at PALM JUMEIRAH Page 7 8.0 Training All records of training shall be maintained. Prior to these works commencing, a review of the activities shall be undertaken in association with the operatives undertaking the duties. This will identify where additional training over and above existing knowledge or experience is required. This Method Statement shall be communicated to appropriate personnel connected with the undertaking of these works. This is essential to the safe and successful completion of the operation.The method statement shall be signed every time the operatives are briefed. 9.0 Appendix 1. ITP 2. Checklist 3. Risk Assessment AVA at PALM JUMEIRAH INSPECTION & TEST PLAN Activity Prepared by: Checked by: Approved By: Date: Date: Installation of PVC Conduits and Accessories Inspection & Test Plan Number: Ihab Eid Date: 20-Sep-23 SECTION 1 - REFERENCES AND CONTROL DOCUMENTS Drawings Method Statements Installation of PVC Conduits and Accessories Specifications SECTION 2 - INSPECTION & TEST PLAN Hold Point: Stop work until inspected and QA documents approved. Witness Point: Inspection Requested - work can continue Surveillance Point: Ensure the activity is reviewed to allow works to continue. Review Point: Results to be reviewed by a 2nd party. PRIMARY CONTROL SECONDARY CONTROL Inspection Details Consultant Code Frequency Check sheet/Verifying Document innovo Code Method Statement ALL AREAS Approved Method Statement HOLD REVIEW N/A Material Submittal ALL AREAS Approved Material Submittal HOLD REVIEW N/A Shop Drawing ALL AREAS Approved Shop Drawing HOLD REVIEW N/A ALL DELIVERIES MATERIAL INSPECTION HOLD HOLD N/A Safety Clearance ALL AREAS PROJECT SAFETY PLAN HOLD WITNESS N/A Inspection for Installation of PVC Conduits and Accessories ALL AREAS METHOD STATEMENT WORK INSPECTION REQUEST HOLD HOLD N/A Activity to be checked Client Code Document Review Material Verification Material Deliveries Installation Inspection SECTION 3 - CLOSE OUT This work has been undertaken and completed in accordance with this ITP and all associated reference documents. Completed check sheets etc. are available. Name: Ihab Eid QA/QC Department Site Representative Date: 20/09/2023 Project: AVA – THE PALM PROJECT Client : OMNIYAT Sub Consultant: RAMBOLL Main Contractor: INNOVO BUILD MEP Contractor: INNOVO MEP Lead Consultant: U+A MST Ref. no: i119 Job No: CHECKLIST for Installation of PVC Conduits and Accessories Work Item 1.0 Pre-construction 1.1 Material Statement is Approved 1.2 Material Submittal is Approved 1.3 Shop Drawing is Approved 2.0 Installation of PVC Conduits and Accessories 2.1 2.2 2.3 2.4 2.5 2.6 Check approved Material inspection Request to ensure approved material being used Dimensions and arrangement of the conduits are complying with the approved shop drawings The conduits routes are free from debris and obstruction of other activities All surfaces are safe for handling and that sharp edges and burs are removed after cutting works Boxes locations are matching to the approved shop drawings All boxes dimensions are complying with the standard details 2.7 All boxes are aligned properly 2.8 Conduits are connected to the boxes properly 2.9 2.10 Contractor's SE/PE Selected back boxes are matching with final fix accessories Ensure Back box knockout size matching with conduit size 2.11 Ensure Conduits are properly supported/Tied 2.12 Ensure Fabricated Standard bends are used for all sizes greater than 25mm For Site/Project Engineer: For QA/QC: Name: Sign: Date Name: Sign: Date Contractor's QA/QC Remarks 119 (AVA AT PALM) Document Reference: INNOVO-MEP-ELE-RA-004 Document Title: Rev. 00 Risk Assessment for Installation of PVC Conduits and Accessories Page 1 RISK ASSESSMENT ACTIVITY: Installation of PVC Conduits and Accessories LOCATION: Dubai Palm Jumeirah PROJECT: EQUIPMENT TO BE USED ▪ ▪ ▪ ▪ ▪ ▪ ▪ I-119 AVA AT PALM MATERIALS TO BE USED ▪ ▪ ▪ ▪ ▪ ▪ ▪ Portable Electrician Hand Tools Hack Saw Measurement Tape Spirit Level Hammer Portable Drill Machine Portable Air Blower RA No. INNOVO-MEP-ELE-RA-004 DATE: 25/09/2023 REVISION STATUS Nylon Fish Cord Rope Binding Steel Wire PVC Solvent Cans Thermocol Sheets Masking Tape PVC Conduit Bending Spring Vernier Caliper REVISION NUMBER Rev REVISED DATE 00 POTENTIAL HAZARDS / CONDITIONS CONSIDERED (TICK BOX) PERSONS AT RISK (TICK BOX) WORKING FROM HEIGHT ELECTRICITY HAND TOOLS TASK LIGHTING CONFINED SPACE EXCAVATION/BACK FILLING EMPLOYEES PUBLIC FALLING MATERIALS MANUAL HANDLING PEDESTRIAN FATIGUE NOISE & VIBRATION HAZARDOUS SUBSTANCES SUBCONTRACTORS VISITORS MACHINERY/EQUIPMENT SLIPS / TRIPPING SITE VEHICLE SECURITY HEAT EXHAUSTION ENVIRONMENTAL (Use Environmental Impact- Severity Rating Section for these HAZARDS) FIRE RISK ADVERSE WEATHER ACCESS/EGRESS LIFTING OPERATION OTHERS (client & consultant) STAKEHOLDERS MATERIALSTORAGE MANDATORY HSE REQUIREMENTS (TICK BOX) SAFETY INDUCTION ADEQUATE VENTILATION WORK PERMIT PROPER TOOLS / EQUIPMENTS PROPER SUPERVISION TOOLBOX TALK DUST CONTROL PROPER PPE SAFE WORKPLACE PROPER BARRICADE AND WARNING SIGN IN THE AFFECTED AREA PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENT (TICK BOX) SAFETY HELMET GOGGLES / SAFETY GLASSES RESPIRATORY PROTECTION / BREATHING APPARATUS GLOVES OVERALLS SAFETY BOOTS EAR PLUGS / DEFENDERS FULL BODY SAFETY HARNESS HIGH VIZ SAFETY JACKET WELDING/METAL CUTTING PPE TO REFER OTHER RISK ASSESSMENTS 1. N/A Page 1 of 10 119 (AVA AT PALM) Document Reference: INNOVO-MEP-ELE-RA-004 Document Title: Rev. 00 Risk Assessment for Installation of PVC Conduits and Accessories Page 2 RISK LEVEL H (HIGH-Potential to cause death, permanent injury or M (MEDIUM – Potential to cause loss time injury or Long-Term Severe Permanent Environmental Harm) Environmental Impact) SEVERITY (S) Health & Safety CLASS OF RISK (L X S) Environmental Impact 0 = Impossible 0 = No injury Short Term < less than 1 month 1 = Improbable 1 = Minor – (FAC) 0 = No harm 2 = Remote 2 = Major - (MTC) 3 = Minor HIGH 3 = Probable 3 = LTI (Lost Time Incident) Long Term > Greater than 1 Month 4 = Occasional 4 = Disabling Injuries 4 = Major 5 = Frequent 5 = Fatality 5 = Catastrophic NOTE: = 15 - 25 MEDIUM = 07 - 14 LOW = 01 - 06 5 5 10 15 20 25 4 4 8 12 16 20 3 3 6 9 12 15 2 2 4 6 8 10 1 1 2 3 4 5 1 2 3 4 5 X SEVERITY (S) 1. Risk assessment must be addressed to workers by the work in charge before starting job. 2. Risk assessment is a continuous process hence to be reviewed depending on activity and risk involved RISK ASSESSMENT TEAM Sr. No. 1 RISK MATRIX LIKELIHOOD (L) LIKELIHOOD (L) L (LOW – An injury treatable with First Aid or Short-Term Environmental Impact) NAME OFFICIAL SIGNATORIES FOR THE RISK ASSESSMENT DESIGNATION Dinoop Chandrasekharan MEP Project Manager Pardeep Singh HSE Coordinator Assessed By (Name): Signature: Date: 25/09/23 2 3 4 Assessed By (Name): Signature: Date: 25/09/23 5 Page 2 of 10 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: S. N 1 2 Risk Assessment for Installation of PVC Conduits and Accessories HARM RISK LXS L M H the • Fall • Personnel injuries • Access/ Egress • Property damage • Slipping and • slip & trip Tripping Delivering/ Shifting/ storing of materials • Personnel injuries (PVC Conduits • Fatality and Accessories) • Property damage • Back and hand injuries • Manual handling • Sharp edges Rev. 00 Page 3 Installation of PVC Conduits and Accessories HAZARD Access to work area INNOVO-MEP-ELE-RA-004 3x4 12M 4x5 20H CONTROL MEASURES CONTROLLED BY WHOM • PTW must be obtained. • Follow main contractor PTW system procedures. • Toolbox talks to be given for task. • Without site safety induction, nobody is not allowed to enter the site • Access to the site should be well sign SE/PE/FM/ posted. SO • Clear emergency route should be designated. • No material should be store and stack in access. • Pedestrian access should be designated and clear • Minimum mandatory PPE shall be worn at site/task area • Vehicle must be registered, and driver must possess valid driving license. • Competent banks man shall control heavy equipment / vehicle movement Supervisor/ inside the site. Foreman • All vehicle/heavy equipment shall be fitted with reverse alarm. • The load shall be secured properly. • Follow vehicle routes and speed limits. RESIDUAL RISK LXS L M 1x4 4L 1x4 5L Page 3 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: S. N HAZARD INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of PVC Conduits and Accessories Page 4 Installation of PVC Conduits and Accessories HARM RISK LXS L M H • Collision with other vehicle, pedestrians, fixed objects. • Over turning of vehicle. • Fall of load Use of Power tools/Hand tools 3 Rev. 00 • Fatality • Disability • Hand Injury • Electrocution. • Burn • Fire. • Electrocution. • Sharp Edges. • Property damage • Slip and fall of • Fire tools 4x5 20H CONTROL MEASURES CONTROLLED BY WHOM • Vehicles to be parked in the designated parking/unloading areas. • Transport assembly area must be cordoned off. • Start unloading work after switching off the engine and apply hand brakes. • Only the essential personnel shall be allowed to approach the working area. • Only experienced and trained workmen to be engaged. • Remove materials on the edges first to create work area /free movement. • Use only 110 V rated power tools. • Only competent person should be allowed to operate the power tools. • Ensure all tools are inspected and colour coded prior to use. SE/PE/FM/ • Adequate sign Boards. SO • Proper cable management. • All Parts must meet the manufacturer Specifications. • Faulty Parts and equipment must be removed immediately. • Always use right tool for the right job. RESIDUAL RISK LXS 1x5 L M 5L Page 4 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: S. N HAZARD INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of PVC Conduits and Accessories 4 Page 5 Installation of PVC Conduits and Accessories HARM RISK LXS L M H Installation of PVC Conduits and Accessories by using scaffold • Use of uninspected scaffold • Poor Platform • Failing to use harness and double hook lanyard. • Falling materials and tools from height Rev. 00 • Falling from heights could lead to fatalities. • Falling objects causing serious injuries. • Fractures • Property damage 5x5 25H CONTROL MEASURES • Ensure that loose splintered or cracked handles on tools are replaced through proper inspection. • Adequate training. • Ensure adequate supervision. • Ensure use of appropriate PPE. • Work at height permit will be followed • Toolbox talks to be given for safe work at height. • Scaffold must be erected/dismantling by Certified experienced person. • Green tag must be on scaffold to climb on. • Area at ground level should be barricaded off and proper signage. • Build scaffold on even and solid surface. • No material stacked or kept on scaffold. • While working on platform, all tools needs to have lanyard on that are attached to person. • Base plates fix firmly to ground. • Inspection of harness and lanyard before use. • Proper Supervision on the place. • Maintain good housekeeping in working platform. CONTROLLED BY WHOM SE/Forman/ Supervisor/ Scaffold inspector/ SO RESIDUAL RISK LXS 1x5 L M 5L Page 5 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: S. N 5 HAZARD PVC Conduits and Accessories by using Ladder INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of PVC Conduits and Accessories Finger caught in between pinch points Page 6 Installation of PVC Conduits and Accessories HARM RISK LXS L M H • Collapse • Fall from heights • Fatality • Minor /Major injuries 5x5 25H • Laceration, • Physical injuries (minor/ major) 3x4 12M Cutting of pipes 6 Rev. 00 CONTROL MEASURES • Ladder will only be used other means of access is restricted. • Ladder will be inspected and record to be maintained. • Ladder must be used only for short duration work or for inspection purpose. • Ladder will be footed always. • One person is permitted to work on a ladder. • Ladder may not use close to any access & egress / edges. • Top two run must be covered. • While using ladder it must be secure or hold by another person. • Choose correct blade for the material being cut. • Secure the blade with the teeth pointing forward. • Keep the blade rigid and the frame properly aligned. • Use entire length of blade in each cutting stroke. • Avoid horse play while cutting the pipes. • Use mandatory PPE for job task. CONTROLLED BY WHOM RESIDUAL RISK LXS L M SE/ Forman/ Supervisor/ SO 1x5 5L PE/SE/ Sup/FM 1x4 4L Page 6 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: S. N 7 INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of PVC Conduits and Accessories HARM • Eye injury into • Hand injury • Noise • Dust RISK LXS L M H 3x5 15H 4x5 20H Handling of PVC solvent cement 8 Page 7 Installation of PVC Conduits and Accessories HAZARD Drilling concrete Rev. 00 • skin, • eye • Contamination • inhalation, of soil and • ingestion, surrounding • fire / burns/spills areas. CONTROL MEASURES • Only competent person drilled into concrete • 110v operated electrical drill machine used which are periodically inspected/ color coded and serviced by competent person • Supervisor ensures that PPE (safety glass/ear plug/dust mask and gloves) provided and using properly by operatives. • Chemicals acknowledged at the project store with the Material Safety Data sheet (MSDS) and retained at project office. • All the chemicals must store in cooled and ventilated area • By the store keeper/material controller. COSHH assessments generated for the chemicals and supervisors communicated the safe of chemical to the user’s prior assign tasks with chemicals. • Required chemicals only be stored in minor quantities to reduce fire risk and the risk of environmental impact. • Chemicals shall be stored in accordance with MSDS guidance CONTROLLED BY WHOM RESIDUAL RISK LXS L M Forman/ Supervision 1x5 5L SE/PE/FM/S O 1x5 5L Page 7 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: S. N HAZARD INNOVO-MEP-ELE-RA-004 Rev. 00 Risk Assessment for Installation of PVC Conduits and Accessories Page 8 Installation of PVC Conduits and Accessories HARM RISK LXS L M H CONTROL MEASURES CONTROLLED BY WHOM RESIDUAL RISK LXS L M • MSDS suggested PPE’s provided to the users in addition to the mandatory PPE. • Partially used/surplus chemicals returned to site stores and safely placed at the COSHH store. • Chemicals shall not transferred/stored in unidentified containers/ discarded containers. • Ensure chemical containers lid and cap securely places. • Empty containers disposed at the designated skips/bins.. 9 Lack of Supervision • Poor quality of work • Chance of accident /incident • Property damage 4x4 16H 10 Adverse Weather Condition. Heat Stress, Fog, Sand Storms and Rain • Heat Stress, • Heat Exhaustion • Muscle cramps serious injuries • Property damage. 4x4 16H • Ensure the availability of competent supervision at work place at all times during all task activities. • DSTI (Daily Safety Task Instruction) should be provided to the workers prior to the commencement of activity. • All personnel will be provided with Appropriate PPE (safety Shoes Helmets jackets etc.), • Cool drinking water and electrolyte solution to be provided during all shift activities. • Compliance with summer break law. PE/SE/FM/ SO 1x4 4L PE/SE/FM/ SO 1x4 4L Page 8 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: ACTIVITY: S. N 11 • Slip, trip & falls • Heavy Materials. • Spillage • Fire Hazards Page 9 Installation of PVC Conduits and Accessories HARM RISK LXS L M H Housekeeping • Rev. 00 Risk Assessment for Installation of PVC Conduits and Accessories HAZARD • INNOVO-MEP-ELE-RA-004 • Personal Injury • Property Loss • Fire 3X4 12H CONTROL MEASURES CONTROLLED BY WHOM • First aid kit and first aider will be provided on site always. • Shaded and adequately ventilated rest area & regular breaks will be provided to avoid heat exhaustion. • Adequate PPE provided. • Adequate access and egress • Proper cable management • Adequate training • Adequate illumination • Adequate material storage area. SE/FM/ CH • Clear access to firefighting equipment. • Manual handling training. • Waste management/ Disposal and clear ups will be assured during and at the end of every shift - pictures to record site conditions at hand over to be implemented should it be required. RESIDUAL RISK LXS 1X4 L M 4L Engineers Comments (HSE) 1. Ensure proper workplace isolation is maintained during activities such as lifting, loading/unloading, erection, assembling/dismantling, etc., and implement Foreign Object Debris (FOD) controls at site. 2. Guarantee effective supervision and Health, Safety, and Environment (HSE) monitoring throughout the activities. 3. Prioritize safe working at heights and strict adherence to lifting procedures. Page 9 of 10 H 119 (AVA AT PALM) Document Reference: Document Title: INNOVO-MEP-ELE-RA-004 Risk Assessment for Installation of PVC Conduits and Accessories Rev. 00 Page 10 4. The Temporary Works (TW) coordinator/lifting supervisor should confirm the presence of an approved task-specific lifting plan before commencing lifting activities (non-routine). 5. Maintain records of Permit to Work (PTW) both internally and externally at the site. 6. The Responsible Engineer, permit to work coordinator or Temporary Works Coordinator must oversee pre-task briefings and ensure activities align with safe working procedures. 7. INNOVO MEP should establish and communicate Fire and Emergency Preparedness measures to operatives and records of communication to be maintained. 8. Strictly adhere to statutory authority guidelines, including Dubai Municipality Requirements and Client HSE guidelines. Page 10 of 10