ETCS Level 1 Project REQUEST FOR INFORMATION (RFI) Of: Contract No: PEG-1193 RFI No: PEG-1193-24/75-CN-SI-RFI-0022 To: Mr. Jesus Emilio Martinez Team Leader/Project & Contract Management – Hill Intl -Transurb SA JV Subject: Static Speed Profile Package No: 24/75 Date: 01 August 2024 From: Siemens Mobility GmbH DISCIPLINE: REFERENCE: SPECIFICATION: BOQ ref: DRAWING: Location/Zone: Information Requested: Please provide the complete ETCS Static speed profile. For points it is requested to have the speed also in diverging directions. Besides that the speed for the tracks after the diverging point is not available and herewith requested. Speed of all point machines for normal and diverging direction Existing information’s as example: Point Machine Type: The Type of some point machine is missing in the plan. Needed information’s as example: Request For Information (RFI) Procedures ETCS level 1 Project Document No: PEG-1193-PP-09-02-FM Rev.0 Revision Date: Nov 2023 ETCS Level 1 Project Point Machine Speed: The speed of all points machine is missing. Point P01 P02 P03 P04 P05 Speed L ? ? ? ? ? Speed R ? ? ? ? ? Point P06 P07 P08 P09 P10 Speed L ? ? ? ? ? Speed R ? ? ? ? ? Point P11 P12 P13 P14 P15 The missing information about speed L/R [km/h] should be fulfilled. Does the siding track have the same speed limit as the point? Speed L ? ? ? ? ? Speed R ? ? ? ? ? Static speed profile (SSP) - table of the permanent restricted speed: Cairo/ Shubra Km2.500 Km5.500 Up/ Dawn 50 Curves According to the table of the permanent restricted speed from Cairo to Shubra, we have a speed limit of 50km/h for 3km due to curves. due what there is a speed restriction of 3km? Is the restriction applicable for all tracks or only main tracks? Is the speed of the main line (outside this restriction from table) 160km/h? Gradient Profile (GP) Is the following gradient profile applicable of all tracks? Request For Information (RFI) Procedures ETCS level 1 Project Document No: PEG-1193-PP-09-02-FM Rev.0 Revision Date: Nov 2023 ETCS Level 1 Project Reason Requested: The PoE creation needs to be created for ETCS Trackside purpose based on gradient profile (GP) and static speed profile (SSP) for all areas, tracks, points (incl. diverging direction/turn out) on the plan, where it is possible to go with the train. GP & SSP profile shall be provided completely for all stations in whole line (main line, siding tracks) without missing data for some areas, tracks, points (incl. diverging direction/turn out), otherwise can lead to dangerous/safety moments on the track because assumed speed will be too high. 01.08.2024 .................... Jan Birka ................ RFI DATE REQUESTED BY Hill-Transurb JV Receive: Moebes Hans ............................................. Digitally signed by Moebes Hans DN: cn=Moebes Hans, c=DE, o=Siemens, email=hans.moebes@siemens.com Date: 2024.08.01 11:04:31 +02'00' CONTRACTOR’S AUTHORISED REP. Contractor Receive: RESPONSE TO CONTRACTOR Response…………………………………………………………………………………………….…………… ………………………………………………………………………………………………………………………… ……………………………… REVIEWER ……………… DATE …………………………………. PROJECT MANAGER …………….. DATE NOTE: This is not a variation document. If the CONTRACTOR considers any part of this response a variation to its cost or time of performance, the CONTRACTOR is required to give notice in accordance with the terms of the General Conditions of Contract. Request For Information (RFI) Procedures ETCS level 1 Project Document No: PEG-1193-PP-09-02-FM Rev.0 Revision Date: Nov 2023