TABLE OF CONTENTS LIST OF SUBJECTS THE PRACTICAL APPROACH TO REFINERY STORAGE TANK INSPECTION REFERENCE API GUIDE FOR INSPECTION OF REFINERY EQUIPMENT CHAPTERS II and XIII CORROSION AND CORROSION CONTROL, 2nd Edition By: HERBERT H. UHLIG CORROSION ENGINEERING, 2nd Edition By: FONTANA and GREEN ASME SEC. V NON-DESTRUCTIVE EXAMINATION 2013 Ed. NACE SURFACE PREPARATION HANDBOOK API 650 Welded Tanks for Oil Storage, 12th Ed., ERRATA 2, Dec. 2014 API 653 Tank Inspection, Repair, Alteration, and Reconstruction, 5TH Ed. Nov. 2014 TABLE OF CONTENTS INTRODUCTION CODES and HISTORY 1.0 CHECKLIST INSPECTION 2.0 CHECKLIST FORM 3.0 THE INSPECTOR 4.0 INSPECTION REPORT AND RECORD 5.0 FREQUENCY OF INSPECTION 6.0 NON-DESTRUCTIVE EXAMINATION IN TANKAGE 6.1. LIQUID PENETRANT METHOD 6.2. MAGNETIC PARTICLE EXAMINATION 6.3. ULTRASONIC INSPECTION 6.4. INDUSTRIAL RADIOGRAPHY 6.5. MAGNETIC FLUX LEAKAGE TEST 6.6. Phased Array Ultrasonic Testing (PAUT) in Lieu of Radiography 7.0 OTHER METHODS OF TESTING PNEUMATIC LEAK TEST HYDROSTATIC TEST 8.0 LOCATING LEAKS ON TANK FLOOR VACUUM TESTING FLOODING METHOD: a. INTERNAL FLOODING b. EXTERNAL FLOODING 9.0 PRACTICAL TEST FOR ATMOSPHERIC TANKS 10.0 DETERIORATION OF STEEL TANKS 11.0 APPROACH TO TANK INSPECTION 12.0 SAFETY IN TANK INSPECTION 13.0 PRACTICAL WAYS OF SUPRESSING CORROSION IN TANKAGE 14.0 Tank Farm Corrosion Control Using Cathodic Protection APPENDIX I SUGGESTED APPROACH TO REFINERY TANK EXTERNAL INSPECTION APPENDIX IIa OUTLINE OF THE COMMON FORMS OF CORROSION AND MAJOR CORROSION PROMOTING SUBSTANCES INSIDE REFINERY STORAGE TANKS APPENDIX IIb SUGGESTED APPROACH TO REFINERY TANK INTERNAL INSPECTION APPENDIX III SAMPLE REPORT A AND B APPENDIX IV RETIRING LIMITS OF PLATE THICKNESS APPENDIX V SUGGESTED APPROACH FOR FLOOR RENEWAL OF SMALL CAPACITY TANKS (20, 000 – 30, 000 bbls.) APPENDIX VI MAINTENANCE PAINTING GUIDELINE APPENDIX VII MISCELLANEOUS DATA AND TABLES APPENDIX VIII NDE Requirements Summary API 653 Table F.1 APPENDIX IX NDE Requirements Summary API 650 Annex T Copyright 2000 All Rights Reserve 1 PAGES 1 2 2 6 7-11 12 13-15 16-17 18-23 18 19 19 20 22-23 23-24 25-27 25 25 28-31 28 29 29 32 33-34 35-37 38-40 41 42-47 48-51 52 53-56 57-58 59-60 61-62 63 64-70 71-73 74-77 INTRODUCTION In service, steel tanks are bound to fail and the cause of failure is principally blamed to corrosion. Although broken parts can be considered another cause of failure. It is generally attributed to the weakening effects of corrosion unless breaking its caused by any mechanical means or natural disaster like earthquake. Tanks built before 1945 may be of a riveted construction. Tank built up to about 1965 BS 2654 have tank shells designed with a joint efficiency factor of 0.85 and the weld would only have been inspected visually during construction. After 1965 it became normal practice to have shells designed with a joint efficiency factor of 1.00 and with weld quality inspected by spot radiography during construction. Basically, the rate of corrosion in tankage is dependent on the type of atmospheric condition to which the tank is exposed and the type of service it is employed. It is therefore important that periodic inspection is carried out so that remedial measures can be taken before serious deterioration of the tank develops. This booklet is divided into 13 equally important sections and the presentations are made in such a manner that a practical approach to tank inspection can be followed. Because it is considered difficult to work by memory alone, the used of an inspection checklist is emphasized. Considering that good inspection requires good Inspector, the criteria of the qualifications and characteristics of the Inspector are given. Blaming corrosion in most failures of the tank, the principal type of corrosion and the major promoting substances in tankage are briefly viewed. Because atmospheric vertical storage tanks are the most common Petroleum refineries, discussions of methods in suppressing corrosion and safety practices are primarily based on these tanks. Likewise, the illustrations for non-destructive examinations and testing considered to be practical are referred to the same type of tanks namely the Cone Roof and the Annular Pontoon Floating Roof tanks. See figures 1 and 2 respectively. CODES and HISTORY Conventional atmospheric or low-pressure storage tanks are generally built in accordance with the following codes - - British Standard, BS 2654 (Manufacture of Vertical Welded NonRefrigerated Storage Tanks with Buut-Welded Shells for the Petroleum Industry) American Standard, API Std 650 (Welded Steel Tanks for Oil Storage German Code, DIN 4119-1 and -2 (Aboveground Cylindrical Flatbottomed Tank Installation of Metallic Material French Construction code, CODRES (code Francias de Construction des Reservoirs Cylindriques Verticaux en Acier UCSIP et SNCT 2 3 4 5 1.0 CHECKLIST INSPECTION 2.0 In checklist inspection, visual inspection, which is the primary nondestructive examination, is first performed. The inspector walks around the tank and notes down all his initial findings on the checklist. He is usually equipped with the following inspection tools: 1. 2. 3. 4. 5. 6. 7. 8. Checklist form, pencil and hardboard Marker such as chalk or crayon Inspection mirror and magnifying lens Flashlight Pit gauge, ruler or caliper Pocket knife or scrapper, inspection digger Ball peen hammer Ultrasonic thickness measuring device After completing the checklist, the inspector reviews the part that seems to be in poor condition. In some cases, applicable non-destructive examinations are conducted just to confirm this condition. Good judgment is of utmost importance, otherwise unnecessary and costly repairs may arise. CHECKLIST FORM Two forms are generally used: the external and internal checklists. The simplest form being considered is the one where in the tank parts are listed according to accessibility. Like the foundation it is listed no. 1 because this is the most accessible part of the tank. The shell is always no. 2 because bulges, buckles and paint failures are visible even at a distance. Moreso, its inspection can be performed almost simultaneously with the foundation. Next to the shell are the stairways and platforms. The no. 4 is the roof. Manways, nozzles, valves can be listed last or under the headings of the parts where they are attached. The form should include the following tank data: 1. 2. 3. 4. 5. 6. 7. Identification and the tank location Service of the tank Nominal and safe filling heights Nominal and safe filling capacities Tank inside diameter Date tank last cleaned For gasoline tanks, leaded must be indicated See sample checklist forms or check API 653 Annex C 6 7 PONTOON FLOATING ROOF TANK INTERNAL INSPECTION CHECKLIST PONTOON FLOATING ROOF TANK INTERNAL INSPECTION CHECKLIST DATE ____________________ NO _________________________ TANK IDENTIFICATION _________ SERVICE _______ AREA ___________ NOM. CAPACITY _____________ SAFE FILLING CAPACITY _____________ INSIDE DIAMETER ______ HEIGHT ______ SAFE FILLING HEIGHT _______ DATE TANK LAST INSPECTED _______ DATE TANK LAST CLEANED______ INSPECTED BY ____________________ OTHERS: _____________________ DATE ____________________ NO _________________________ TANK IDENTIFICATION _________ SERVICE _______ AREA ___________ NOM. CAPACITY _____________ SAFE FILLING CAPACITY _____________ INSIDE DIAMETER ______ HEIGHT ______ SAFE FILLING HEIGHT _______ DATE TANK LAST INSPECTED _______ DATE TANK LAST CLEANED______ INSPECTED BY ____________________ OTHERS: _____________________ PARTS CONDITION REMARKS 1. Foundation 2. Shell a. Paint b. Thickness c. Manway/Clean-out Door & Others 3. Stairway/Platform & Handrail 4. Roof a. Paint b. Pontoon c. Manholes d. Drains e. Vents f. Roof Leg Sleeve g. Anti Rotation Sys. h. Foam Dam i. Others 5. Rolling Ladder & Track 6. Windgirder/Walkway & Handrail 7. Nozzles/Valves 8. Level Gauge 9. Nameplate/Base Miscellaneous VP-Very Poor; P-Poor; F-Fair; G-Good; N-Not Accessible/Not Inspected PARTS CONDITION REMARKS 1. Tank Floor a. Welds b. Plate Thickness c. Annular Plate d. Roof Leg Pads 2. Shell Internal wall a. Seam Welds b. Manway/Nozzles Necks welds to Shell 3. Roof Deck Underside a. Seal Pan b. Center Roof Drain Pit c. Roof Drain Sys. Hose Or Pipe Swivel d. Roof Leg e. Monkey Ladder 4. Roof Seal a. Mechanical Type - Counter Weights b. Rubber Seal Type 5. Water Draw-Off Sys. a. Sump & Pipe Miscellaneous VP-Very Poor; P-Poor; F-Fair; G-Good; N-Not Accessible/Not Inspected 8 9 CONE ROOF TANK EXTERNAL INSPECTION CHECKLIST FORM CONE ROOF TANK INTERNAL INSPECTION CHECKLIST FORM DATE ____________________ FILE NO ________________ TANK NO_________ SERVICE _______ LOCATION ___________________ NOM. CAPACITY _____________ SAFE FILLING CAPACITY _____________ INSIDE DIAMETER ______ HEIGHT ______ SAFE FILLING HEIGHT _______ DATE TANK LAST INSPECTED _______ DATE TANK LAST CLEANED______ INSPECTED BY ____________________ OTHERS: _____________________ DATE ____________________ FILE NO ________________ TANK NO_________ SERVICE _______ LOCATION ___________________ NOM. CAPACITY _____________ SAFE FILLING CAPACITY _____________ INSIDE DIAMETER ______ HEIGHT ______ SAFE FILLING HEIGHT _______ DATE TANK LAST INSPECTED _______ DATE TANK LAST CLEANED______ INSPECTED BY ____________________ OTHERS: _____________________ PARTS CONDITION REMARKS 1. Foundation 2. Tank Shell a. Identification b. Painting c. Seam Weld d. Thickness e. Manways f. Clean-out door g. Other Attachments 3. Stairway/Platform a. Landing b. Handrail 4. Roof Deck a. Painting b. Thickness c. Manholes d. Vents e. Sampling Hatch f. Handrail g. Others 5. Windgirder 6. Level Gauge/Pipe 7. Nozzles/Valves Miscellaneous VP-Very Poor; P-Poor; F-Fair; G-Good; N-Not Accessible/Not Inspected PARTS CONDITION REMARKS 1. Shell Internal Wall a. Pitting Condition b. Seam Weld c. Others 2. Bottom Plate a. Pitting Condition b. Seam Weld c. Thickness d. Water Draw-off Sump e. Water Draw-off Pipe f. Others 3. Roof a. Roof Underside b. Roof Support c. Others 4. Level Gauge Float a. Cable Connection b. Guide Wire 5. Foam Deflector Miscellaneous VP-Very Poor; P-Poor; F-Fair; G-Good; N-Not Accessible/Not Inspected 10 11 3.0 THE INSPECTOR The Inspector should have an inquisitive mind and never satisfied with superficial appearance that readily absorbs details. He should have a passion for thoroughness. He must have practical knowledge of the effects of time, wear and corrosion on tank parts. He should know all defects that are found so that he can assist in prescribing the necessary repair procedure. The Inspector should have the basic knowledge of engineering and must be familiar with the design specifications presented in the following standards. 1. Atmospheric tank ----API Std. No. 650 2. C-15 psig tank ----API Std. No. 620 3. Full vacuum to atmospheric ----ASME Code Sec. VIII API Std. No. 620 4. Over 15 psig tank ----ASME Code Sec. VIII API Std. 620 – for max. compression 4.0 INSPECTION REPORT AND RECORD It is not possible to evaluate tanks without records. Inspection reports should be maintained and all information must be updated and kept in permanent files for immediate and future references. Reports should be concise and definite. If at all possible, highly technical presentations should be avoided. It should be remembered that simple yet descriptive terms makes reporting easy and effective. In case there is a need to include layouts or drawings, the orientations should be clear. Inspection is considered complete when reports and the possible recommendations are submitted. See sample report Appendix III. These inspection reports and complete records along with inspector recommendations and documentation of disposition shall be maintained by the owner/operator for the life of the tank. Local jurisdictions may have additional reporting and record keeping requirements for tank inspections. 4.1 Because tanks are built with parts for specific usage, the Inspector should be aware of them. He must be well verse in all refinery and chemical process industrial practices. A good Inspector knows his limitation. Consultations with Technical Experts and accepted standard practices are made when needed. b. Inspection History The inspection history includes all measurements taken, the condition of all parts inspected, and a record of all examinations and tests. A complete description of any unusual conditions with recommendations for correction of details which caused the conditions shall also be included. This file will also contain corrosion rate and inspection interval calculations. 4.2 12 Records a. Construction Records Construction records may include nameplate information, drawings, specifications, construction completion report, and any results of material tests and analyses. Reports a. Report Contents Reports shall include at a minimum the following information: i. date(s) of inspection; ii. type of inspection (external or internal); iii. scope of inspection, including any areas that were not inspected, with reasons given (e.g. limited scope of inspection, limited physical access; iv. description of the tank (number, size, capacity, year constructed, materials of construction, service history, roof and bottom design, etc.), if available; 13 v. vi. vii. viii. ix. x. xi. xii. list of components inspected and conditions found (a general checklist such as found in Annex C may be used to identify the scope of the inspection) and deficiencies found; inspection methods and tests used (visual, MFL, UT, etc.) and results of each inspection method or test; corrosion rates of the bottom and shell; settlement survey measurements and analysis (if performed); recommendations per 6.9.3.1; name, company, API 653 certification number and signature of the authorized inspector responsible for the inspection; drawings, photographs, NDE reports and other pertinent information shall be appended to the report. c. Nondestructive Examination (NDE) Personnel performing NDE shall meet the qualifications identified in 12.1.1.2, but need not be certified in accordance with Annex D. The results of any NDE work, however, must be considered in the evaluation of the tank by an authorized inspector. b. Recommendations Reports shall include recommendations for repairs and monitoring necessary to restore the integrity of the tank per this standard and/or maintain integrity until the next inspection, together with reasons for the recommendations. The recommended maximum inspection interval and basis for calculation that interval shall also be stated. Additionally, reports may include other less critical observations, suggestions and recommendations. It is the responsibility of the owner/operator to review the inspection findings and recommendations, establish a repair scope, if needed, and determine the appropriate timing for repairs, monitoring, and/or maintenance activities. Typical timing considerations and examples of repairs are: i. ii. iii. iv. v. prior to returning the tank to service—repairs critical to the integrity of the tank (e.g. bottom or shell repairs); after the tank is returned to service—minor repairs and maintenance activity (e.g. drainage improvement, painting, gauge repairs, grouting, etc.); at the next scheduled internal inspection—predicted or anticipated repairs and maintenance (e.g. coating renewal, planned bottom repairs, etc.); monitor condition for continued deterioration—(e.g. roof and/or shell plate corrosion, settlement, etc.). 14 15 5.0 FREQUENCY OF INSPECTION Because of the cost involved, it is unreasonable to take tanks out of service just for inspection. Unless special reasons indicate that inspection must be made, full inspection can be performed in conjunction with a properly planned maintenance program or schedule. With continuing in-service inspection records, full tank inspection and maintenance program can be scheduled with a frequency proportional to the rate of corrosion in the tank. 5.1 5.2 5.3 5.4 Routine In-service Inspections - The external condition of the tank shall be monitored by close visual inspection from the ground. The interval of such inspections shall not exceed one month. External Inspection - All tanks shall be given a visual external inspection by an authorized inspector. Shall be conducted at least every five years or RCA/4N years (where RCA is the difference between the measured shell thickness and the minimum required thickness in mils, and N is the shell corrosion rate in mils per year) whichever is less. Ultrasonic Thickness Inspection - External, ultrasonic thickness measurements of the shell can be a means of determining a rate of uniform general corrosion while the tank is in service, and can provide an indication of the integrity of the shell. Intervals not to exceed the following: 5.3.1 When the corrosion rate is not known, the maximum interval shall be five years 5.3.2 When the corrosion rate is known, the maximum interval shall be the smaller of RCA/2N years (where RCA is the difference between the measured shell thickness and the minimum required thickness in mils, and N is the shell corrosion rate in mils per year) or 15 years. Internal Inspection - The interval from initial service date until the first internal inspection shall not exceed 10 years unless a tank has one or more of the leak prevention, detection, corrosion mitigation, or containment safeguards listed in API 653 Table 6.1. The initial internal inspection date shall be based on incremental credits for the additional safeguards in API 653 Table 6.1 which are cumulative. 16 For example, the maximum interval for a ¼ in. bottom that has a release prevention barrier and a fiberglass lining would be determined as follows: 10 years (initial) + 5 years (fiberglass lining) + 10 years (release prevention barrier) = 25 years. The initial inspection interval shall not exceed 20 years for tanks without a Release Prevention Barrier, or 30 years for tanks with a Release Prevention Barrier. 17 6.0 NON-DESTRUCTIVE EXAMINATION IN TANKAGE The use of noninvasive techniques to determine the integrity of a material, component or structure. The standard non-destructive examinations in tankage are the following: 1. Liquid Penetrant Method 2. Magnetic Particle Method 3. Ultrasonic Examination 4. Industrial Radiography 5. Magnetic Flux Leakage Test The recommended practices laid out in ASNT, ASME, and API standards are equal in the performance of these methods. 6.1 Liquid Penetrant Examination Liquid penetrant method is an effective means of locating surface discontinuities. The typical application of this method is in finding cracks and pinholes or porosities on welds of manways and nozzles necks attachments to the tank shell. b. Penetrating Oil Testing: In this method, penetrating oil is applied on the inspection side of the surface and seepage is observed at its opposite side. Usually, diesel or kerosene is used as penetrants. Cracks that may possibly develop at the heat-affected zone of the shell opening can also be detected with this method. The method is applicable on the lapped joints of the roof deck and bottoms of pontoons. When renewal of tank floors are being made, the circumferential fillet welds at the juncture of the bottom and shell plates are tested by this method as shown in fig.-3. Basically, two modes of applications are employed under this method. The first is the standard “Dye-Penetrant” and the other is the conventional “Gas-Oil” test. a. Dye-Penetrant test (PT): As the term implies, it calls for the used of a dyed penetrating liquid and a developer. To a properly prepared surface for inspection, a dye penetrant (red) is applied and allowed to penetrate sufficiently. Then all the excess penetrant is cleaned with appropriate solvent. When using solvents in aerosol cans, it is important not to spray directly on the surface to be inspected. There is a risk of cleaning out the dye that had possibly penetrated a discontinuity. Cleaning is best carried out by wiping off the area with solvent soaked lint free rugs. After the removal of the excess penetrant is completed, a white developer is the n applied on the same area. The appearance of deep colored dye locates the defect. For good developing, developers in aerosol cans are used. 18 Gas-oil such as diesel or kerosene is applied on the inspection area and allowed to penetrate for a certain time. Preferably, penetration is allowed overnight. Evidence of wetting of the side opposite the inspection side locates a leak. 19 6.2 Magnetic Particle Examination (MT) Under this method, advantages offered by liquid penetrant are achieved with greater sensitivity. Subsurface defects are also detected. However, sensitivity decreases as the depth of the defects increases. Common defects in tankage that are detected with this method are cracks and laminations. However, to reveal these defects satisfactorily, the surface to be inspected should be fully cleaned. Sometimes abrasive blast cleaning is necessary. To reveal fine defects, the surface should be smooth ground. Rough surface hampers the mobility of the magnetic particle due to mechanical trapping that leads to false indications. 6.4 Radiographic Examination (RE) With permanent record, interior macroscopic flaws as cracks, porosities, non-metallic inclusions are indicated. In tankage, radiography is mainly applied whenever there are works that involves the shell plate butt-welding joints. Installing new insert type manways and nozzles also requires radiographic examination. The adjoining butt joint of new annular ring section of the tank floor also requires random radiographic examination. 6.3 Ultrasonic Examination (UE) In tankage, ultrasonic inspection is mainly applied for wall thickness measurements. Flaw detection is rarely performed. The API Std. No. 650 “Thickness by One-Foot Method” is considered to be practical. Usually only the bottom shell course and spots accessible along the stairway are surveyed for thickness. However, if the result showed suspects of deteriorations, then scaffoldings or sky-climbers are provided in order to conduct full thickness survey on the tank shell. Ultrasonic meters operating under the basis of electronic transittime measurements are used. With this meter, using normal probes, flaws chiefly of the laminar type that has substantial component parallel to the inspection surfaces can be detected. The presences of such flaws are indicated by a change or disappearance of the normal thickness readings. Corroded or fitted backwall also gives the same indications. 20 21 6.5 Magnetic Flux Leakage Test MFL is the “Best” method to evaluate a tank bottom condition quickly and cost effectively. a. Magnetic Flux Leakage Test Principle b. Magnetic Flux Leakage Test Limitations i. Tank Floor Cleanliness ii. Tank Surface Condition iii. Floor and coating thickness iv. Sensitivity v. Coverage - physical limit Pipe Floor corner Around Patch repair Plate edge Around Wear pads MFL Untested Areas The untested areas mentioned above are to be inspected by: - Ultrasonic Testing - Each corner 140x140mm, near shell to bottom weld. - Ultrasonic Testing /HandScan - 10 mm on all four edges, underneath pipes, around wear pads and existing patch repairs. 6.6 Phased Array Ultrasonic Testing (PAUT) in Lieu of Radiography API 650 Annex U This alternative is limited to joints where the thickness of the thinner of the two members joined is greater than or equal to 10 mm (3/8 in.) The UT shall be performed in accordance with a written procedure which has been reviewed and approved by the Purchaser and conforms to the requirements of Section V, Article 4 CODES: a. ASTM E 2491-06 Standard Guide for setting up phased arrays b. ASME B31.1 – Code Case 168 c. ASME B31.3 – Code Case 181 Use of Alternative UT Acceptance Criteria d. ASME B31.1 – Code Case 179 Use of UT in Lieu of RT (1.5 in or less thk) e. ASME Section III – Code Case N-659 Use of (UT) an alternative to (RT) for nuclear power plant components and transport containers f. ASME Section V – Code Case 2557 – Use of Manual PA S-scan UT g. ASME Sec. V Mandatory Appendixes 22 23 h. ASME Section I & VIII, Division 1 & 2 – Code Case 2235 Use of UT in Lieu of RT i. ASME Section XI – Code Case N-713 Examination Requirements for Portions of Class 1 and 2 Systems and Components within the Containment System Boundary Main Features of PAUT: a. Multiple elements are housed in one probe. Each element is wired independently and can be pulsed separately. b. Capable of generating range of angles (e.g. 35°-70°) resulting in an increased probability of detection (POD) of weld imperfection. c. Specialized computer software is used for visualization and interpretation of acquired inspection data. 7.0 OTHER METHODS OF TESTING IN TANKAGE 7.1 Pneumatic Leak Test In tankage, the method is generally applied the tightness check of the reinforcing pad at the shell attachment. The test is performed by injecting air not to exceed 15-psig to the pad through its telltale hole. Soapy solution is then applied on all seam welds at the reinforcing pad and at the attachment welding to the shell. Indications of bubbles locate the leak. See figure 4a for application. The tightness of the pontoons of the floating roofs is also tested with this method. However in this case, air not to exceed 9-inches water pressure is injected instead. See figure 4b for application on pontoons. 7.2 Hydrostatic testing of shell Generally, water-filling test is conducted in order to check the integrity of the tank shell, Because of the scales that usually develops at the shell; it is sometimes necessary to blast clean the scaled wall of the tank. It should be considered that a small hole or crack can be easily covered by thin scale and thus, leaks may not show during the test. Cone roof tanks are water filled to a height 2-inches above the top leg of the top angle. Floating roof tanks are filled up to the recommended safe filling height. In some cases, when there is a need to adjust the safe filling height of the tank because of thinning of the shell, the recommendation laid-out in API Std. No. 650 is followed. Buckling and bulging of the shell and leaks at the seam welds are observed during the test. The telltale holes of the reinforcing pads of the shell attachments are also observed for leakage. Leaks originating on this part indicates the possibility of either defects on the attachment welding to the shell or crack at the heat affected zone of the opening The shell shall be tested by one of the following methods: a. If water is available for testing the shell, the tank shall be filled with water to the maximum design liquid level, H; b. If sufficient water to fill the tank is not available, the tank may be tested by painting all of the joints on the inside with a highly penetrating oil, such as automobile spring oil, and carefully examining the outside of the joints for leakage; 24 25 Minimum fill and discharge rate: 7.3 Tank external shell settlement evaluation (API 653 Annex B) A settlement survey shall be conducted for all existing tanks that undergo a hydrostatic test, except for tanks that have a documented service history of acceptable settlement values, and no settlement is anticipated to occur during the hydrotest. Shell elevation measurements shall be made at equally-spaced intervals around the tank circumference not exceeding 10 m (32 ft). The minimum number of shell measurement points shall be eight. Six sets of settlement readings are required for new tanks: a. Before start of the hydrostatic test; b. With tank filled to 1/4 test height (±600 mm [2 ft]); c. With tank filled to 1/2 test height (±600 mm [2 ft]); d. With tank filled to 3/4 test height (±600 mm [2 ft]); e. At least 24 hours after the tank has been filled to the maximum test height. f. After tank has been emptied of test water. Three sets of settlement readings are required for existing tanks: a. Before start of the hydrostatic test; b. During filling; c. At least 24 hours after the tank has been filled to the maximum test height. 26 27 8.0 LOCATING LEAKS ON TANK FLOORS Locating leaks on tank floors is usually done by visual inspection. But because of the usual dirty condition of the floor; small holes or cracks are often missed. To effect better visual inspection, dirty floors are cleaned by means of abrasive blast cleaning method. Advantage of this method of cleaning is that wet spots usually appear and this locates the leak. This is attributed to the capillary flow of liquid from wet to dry surface. The disadvantages of this method is that additional holes may be generated that can add to the problem of locating leaks. This is particularly true whenever the floor is exhibiting isolated thin spots. Because of this, other methods had been developed in order to improve locating leaks on the tank floors. The most common and perhaps the most popular are the vacuum and flooding methods. 8.1 Vacuum Testing Vacuum testing requires proper surface preparation. The need to clean the surface to be inspected free from scales that are capable of plugging small holes or cracks is of utmost importance. Otherwise, Testing will not yield good results. In the performance of the test, the surface is first coated with films of soapy solution. The n the open side of the vacuum box is placed on top of the test area. With the used of a vacuum pump or an air ejector, partial vacuum of at least 12-psig is maintained inside the box. Leaks can simply be located by the appearance of continuous bubbles at any point on the test area. Observation is made at the top glass of the box. The effectivity of this method is enough to locate even hairline cracks. Care should be exercised that heavy soapy solution is not applied. It usually gives false indication. The main disadvantage of this method is its difficulty to apply on non-flat surfaces. Moreso, in large tanks, it is considered to be time consuming and labor intensive. 8.2 Flooding Method Basically, there are two ways of conducting flooding test in finding leaks on tank floors. It can be Internal or External flooding. a. Internal Flooding Under this method, the tank floor is internally flooded with water to a depth sufficient enough to cover the highest level of the floor. Leaks are simply located by looking for bubbles on the water when air not to exceed 6-inches water pressure is injected at the floor underside. Care should be observed that water is pump first into the tank before injecting air. b. External Flooding As the term implies, flooding with water done outside the tank by constructing a temporary dike. The dike is constructed in such a way that it can maintain a hydrostatic height of at least 12-inches water from the highest level of the floor. Leaks are simply located by looking for entry of water from the floor underside. See figure 6. In addition to the construction of the dike, several couplings with nipples of at least 12-inches long are welded on the floor. The number of coupling depends upon the size of the tank. Large tanks would require more couplings than small tanks. The purpose of the coupling is to be able to see whether water had reached that portion of the floor. Moreso, it allows water to flow faster since water flows only as fast as it can displace air. After all the leaks are located and repaired, the nipples are simply removed and the couplings are plugged. Another way is coating with films of soapy solution instead of pumping water. This time, air not exceed 3-inches water pressure is injected at the underside. Indication of soap bubbles locates the leak. 28 29 In both ways, the preparation calls for the placing of sufficient temporary seal around the tank outside periphery at the bottom. This is to be able to build-up air pressure to the desired value. Two couplings are installed at the floor as shown in figure 5, one is employed as the inlet for the air and the other is for the installation of the U-tube type pressure gauge. After the completion of the test, the couplings are simply closed with bulb plugs. The method being limited to low pressure, it may not be sufficient to blow out scales on pits that may be among the cause of the leak. The need of jarring the floor is sometimes needed in order to pop out scales from the pits Tanks that are used for storing asphalts, wax or other similar materials are tested with this method but steam instead of air is injected. In conditions where it is considered hazardous to inject air, higher cost inert gases such as nitrogen or argon are used. See also API 650 Annex I Undertank Leak Detection and Subgrade Protection 30 31 9.0 PRACTICAL TESTING FOR ATMOSPHERIC TANKS Because of the cost involved, testing methods for tankage should be chosen according to their most practical way of application. Say for tanks where floor renewal had been done, it would be unreasonable to conduct water-filling test since the method is more of testing the shell rather than the floor. The practical test that can be considered is either vacuum or flooding for a leak free floor. The same thing goes for floating roofs, to check for leakage, floating with water is unnecessary. Gas-oil or vacuum test are reliable. Cone roofs can be visually inspected easily. Thus, methods other than this are not required. It should be considered that unnecessary testing adds up to the cost of tank maintenance and should be avoided. See table 1 for some suggestions for testing atmospheric tanks. Table 1 – Suggested testing of Atmospheric Tanks Tank Parts Test Method Shell Water filling Test (1) (2) Cone Roof Visual Inspection Roof Floating Roof Gas-oil or Vacuum Test Pontoon Pneumatic Leak Test Old Flooding Test (3) Floor New Vacuum Test (4) (5) Neck to Shell Dye-Penetrant or Manways and Welding Magnetic Particle Nozzles Reinforcing Pad Pneumatic Leak Test Roof drain system (6) Hydrostatic Test (7) See Appendix VIII and IX Notes: 1. 2. 3. 4. 5. 6. 7. Major works that includes plate renewal or insert type window closure would require radiographic examination as laid in API Std. No. 650 Minor welding repair may not require water-filling test. Dye-Penetrant or vacuum testing can be satisfactory. Not suggested for tanks that employs “Earth-Pad” type foundation. Vacuum testing can be performed. Test conducted on all seam welds. The circumferential weld between the shell and the floor can be inspected with “Gas-oil” method. Applicable for pipe and swivel drain line only. Pressurized the line 50 psig for at least 10 minutes. Check for evidence of leak. Then reduced the pressure to 5 psig and check the swivel joints for evidence of leaks (swivel joints are self locking that at high pressure leakage may not be detected. However, if the seal are defective, leaks will result at low pressure). 32 10.0 DETERIORATION OF STEEL TANKS Basically, corrosion is the primary cause of steel tank deterioration. In Petroleum Refineries, the forms of corrosion that are usually encountered in tankage are weld decay, pitting and crevice, and vapor space corrosion. Weld decay is an example of the effects of localized corrosion. The occurrence of this corrosion is due to the possible existence of some heterogeneities in the metal and this is well exhibited by the geometry of the structure of the weld metal. Weld metal maybe anodic to the steel and in the presence of an electrolyte, a corrosion cell is created thus causing this form of corrosion. See figure 7 showing the mechanics of weld decay corrosion. Pitting and crevice are forms of highly localized corrosion. They deserve special mention because they are considered to be the most harmful types of corrosion that could take place on metals. With only small percent weight loss of the metal, they could result to costly tank failure. Perforation that causes leakage usually resulted. The initiation of the attack or crevice corrosion as the term denotes will require crevice where small volume of solution can be deposited and remain stagnant. Additionally, the attack may also be produced by surface deposits that could create a stagnant condition thereunder, In tankage, this form of attack commonly occurs at the external parts like skip-welded lapped joints, nuts and bolts, rivet heads, and surfaces where there are deposits of sand, dirt or even the corrosion product itself. Compared to crevice, pitting is considered more vicious because it does not require crevice to initiate. It is self-initiating. Pitting results when a small anodic area develops on the metal surface because of certain irregularities in the physical and chemical structure of the metal. Another possible cause of pitting is the presence of mill scale. Mill scale easily break and flake under small variation of temperature and in the presence of an electrolyte, an electrical corrosion cell is created between the broken mill scale and the metal. Since mill scale is cathodic to the metal, pitting will result on metal. Pitting takes long periods to initiate but once started, it will penetrate the metal at an ever-increasing rate. It also tends to undermine or undercut the metal surface as they grow. Another effect of pitting is that it acts as stress raiser that could result to fatigue cracking. See figures 8 a and b illustrating pitting formation due to broken mill scale and cross sections of different types of pitting respectively. 33 The third form of corrosion that can be encountered in tanks is the vapor space corrosion. It basically occurs in Cone Roof type tanks because of the presence of the vapor space above its working portion. Moisture and oxygen are introduced into tanks in different ways. They can either be drawn in the tank with the stock or by breathing during temperature changes. However, much is drawn during the emptying operation of the tank. 11.0 APPROACH TO TANK INSPECTION To minimized cost, the length of time a tank will be placed\ out of service should be to the minimum. It is therefore advisable that external inspection is conducted while the tank is still in service. Internal inspection can then be performed in conjunction to a schedule maintenance program. 11.1 The moisture that may condense above the working portion of the tank will act as the electrolyte. Thereby establishing corrosion in the vapor space. The extent of this corrosion will depend heavily on the activity of the tank. The more the tank is active, the more severe the vapor space corrosion will occur. Since in Refineries, the intermediate products tanks are the most active, such corrosion is usually severe. Moreso, for tanks that are used to carry high sulfur crudes, the vapor space corrosion occurs at an accelerated rate. This is the number 1 reason why Floating Roof Tanks are employed for this stock. 34 External Inspection The primary concern of external inspection lies mainly in the paint failures, broken parts and area where water can be collected and trapped such as pockets, crevices, and other deposits like dirt. The evaluation of these areas shall pertain to the possible effect of atmospheric corrosion. 35 Atmospheric corrosion is principally galvanic. The base metal is the anode and the oxide of the base metal as the cathode. In the presence of the condensates o the moisture in the atmosphere, a corrosion cell is established. The severity of atmospheric corrosion depends on the type and amount of moisture present in the atmosphere. Condensate near marine and industrial areas contains salt and other contaminants thereby making it better electrolyte and more corrosive that condensates in an inland or rural areas even under equal humidity and temperature condition. Since painting is the only practical means of protecting the tank from atmospheric corrosion, faulty paintworks will result to its accelerated deterioration. Another factor to which the Inspector should be on the looked out is the presence of deposits that can initiate crevice corrosion as mentioned in Sec. 10.0. See Appendix I for some suggestions to the approach to tank external inspection. 11.2 Internal Inspection The concern of the internal inspection is the evaluation of the extent of the possible corrosion that could take placed inside the tank. As compared to atmospheric corrosion that takes place on the external parts of the tank, internal corrosion is usually more severe. Sometimes it reached a degree that maintenance repair is no longer economical and it is more preferable to erect new tank as replacement. The corrosion promoting substances that are common in refinery tanks are the following: - Hydrogen Sulfide Moisture and Dissolved oxygen Contaminated water Hydrogen sulfide is not actually corrosive but whenever it is in contact with water, an acid of sulfate evolves and is responsible to corrosion. Moisture as itself does not really have a part in the corrosion cell but it is bound to condense and it is the condensate that will act as the electrolyte to establish corrosion. The presence of dissolved oxygen will stimulate corrosion because of its depolarizing effect. 36 The detrimental effect of the first two groups of corrosion promoting substances are commonly experienced in Cone Roof type tanks as vapor space corrosion above the working portion of the tank. Furthermore, the condensates of moisture and the depolarizing dissolved oxygen plays an important role in the occurrence of pitting corrosion at the mid-section of the working portion of the shell of this tank. This is because the area undergoes more wetting and drying than others. Such corrosion is usually encountered on tanks that are used to carry light stocks such as kerosene, gasoline, and light charge. Tanks that are used to carry heavy stocks like crude oil does not exhibit this corrosion because more or less a permanent film is formed on the shell and thus serve as protection. Perhaps the most harmful corrosion promoting substances that are encounter so in refinery tanks is the contaminated water. The role that it plays is perhaps the most important part in a corrosion cell, which is the electrolyte. Its presence will always result in the tank; the floor and the lower portion of the shell course will usually exhibit weld decays and pittings. In some cases, the extent of the corrosion that may take place will reach a degree that floor renewal will be necessary. Water is weak electrolyte but when contaminated it becomes a strong electrolyte and corrosive. In tankage, it is principally introduced during transportation of the stocks. Say from the Oil Well to the Super Tankers and then to the storage tanks of the refineries. Normally, tanks that are used to carry refinery products like gasoline, diesel, etc. are not contaminated with water. However, when the stocks are transported from one refinery to another, or the bulk plant, chances of introducing water to the tank are high especially when ship tankers are employed as transportation. See Appendix II for some suggestion to the approach to tank internal inspection. 37 12.0 SAFETY IN TANK INSPECTION Because of the risk involved, Inspection should only be conducted by a team of at least two Inspectors or an Inspector aided by an Assistant or Trainee Inspector. No one Inspector should be allowed to work alone. Before any inspection proceeds, valid work permits should be issued and the area where the inspection us to be conducted should be clearly identified. 12.1 Safety tips for tanks in-service inspection: 1. Inspection should only be carried out with tools or equipments that will not generate or emit sparks. 2. Only inspection procedures that will not generate spark or electricity should be conducted. However, if the need arises, it should be confined to light structures. If magnetic particle examination is needed, only magnets should be used. 3. The Inspector should wear only work clothes that are made of materials that will not generate static electricity. 4. If inspections are to be conducted at high places, proper scaffoldings or skyclimbers should be provided. The Inspector should be equipped with safety belts or lifelines. 5. Because of he risk involved, inspection should not be conducted on the roof while the tank is still in service. However, if the need arises, the following safety precautions should be observed: a. Floating Roof Tank: - - Inspection should be carried-out only when the roof level is at high position. The most ideal level for inspection is when the tank is filled up to its maximum safe filling height. Inspection while the roof is at the low position is possible if the space is declared gas-free. At all times, an air mask and lifelines should be used. Only one Inspector should go down the roof and the assisting Inspector as the lookout atop the tank. Added safety precaution is that the operation personnel are properly notified in advance so that the operation of the tank is programmed in such a way that all activities of the tank is suspended at least until the duration of the inspection. On the other hand, the Inspector should see to it that the inspection is performed in the shortest time possible. This is practically considered when inspecting tanks that are used to carry intermediate products. 38 b. Cone Roof Tank: - If plate thinning is suspected, wooden planks at least long enough to span between two rafters or trusses should be securely placed to serve as the Inspector’s access. One safety practice is for the Inspector to walk over the roof along the lapped welded joints. This is the area considered to be stronger than others. Lastly, irrespective whether it is Floating or Cone Roof type tanks, only visual inspection should be carried out. 12.2 Safety requirements for inspecting tanks that are out of service are not as rigid as for tanks that are still in service. However, when it calls for tank entry, the following preparations should be followed: a. Preparation of tank: - Remove all stocks possible through existing connections. - Remove all sources of ignition from the area. - Open all manways. - Remove balance of stocks through manways, clean-out door and or through the water draw-off nozzles. - Blank off all lines connected to the tank. - Install ventilating system. No entry shall be made unless the tank is declared gas-free. Preparation of the Inspector for tank entry: - Check for proper attire. If needed, air mask must be used and check for fit and operation. Check for sufficient air supply. Check air line hose and safety line to keep free and untwisted. Perhaps the most important consideration to be taken for every tank entry understands the difference between “Gas Free” and “Lead Hazard Free”. Notwithstanding the importance of good judgment needed for every inspection. Safety plays an important role on why only qualified Inspectors are allowed to do inspection. An experienced Inspector can be able to predict the type of possible corrosion that could exist depending on the type of tank that is employed for certain services. Say for Cone Roof tanks that are used for intermediate product or heavy stock such as crude oil, the Inspector will readily be on guard when roof inspection is needed. This is because that such tanks usually exhibits intensive vapor space corrosion that could lead to the weakening of the roof structure. 9 It should be remembered that each worker is responsible to his own safety and that he can never do a good work without knowing how to do it safely. 13.0 PRACTICAL WAYS OF TANKAGE SUPPRESSING CORROSION IN Basically, the only practical means of protecting the tank from atmospheric corrosion is by application of protective coatings as mentioned in Sec. 11. Coating systems are selected depending on the type of atmospheric condition of the surroundings. For highly contaminated marine or industrial atmospheres, high performance Epoxy system with Zinc-rich primers are used. In mild atmospheric conditions, an Alkyd paint system will perform satisfactorily. The underside of the tank floor is usually considered buried. Thus, it has been a common practice that high resistivity pads or cushions are compacted under the floor. The most common material are bituminous sand and concrete asphalt. In addition to these compactions, properly monitored impressed current cathodic protection system may be provided. However, in the case of concrete asphalt, this is not applicable because of its very high resistivity unabling plates are laid between the pad and the tank floor. In large diameter tanks, monitoring the protection at the center of the floor is only effective if reference electrode is installed at the center. However, this may not be necessary in small diameter tanks because the indication of protection of the floor near the shell can be more or less considered an indication at the center. Suppressing corrosion inside the tank does not really very from the external parts. In cone Roof tanks, the underside of the roof and the nonworking portion of the shell can be protected by coating application as well. In this case, it will definitely call for high performance Epoxy system. Cement mortar is also satisfactory but because of its weight, it has its restriction. The floor topside plus 1-meter of the shell is usually protected by application of glass reinforced Epoxy (GRE) or Polyester (GRP). Protecting intermediate product tanks that carries light stocks usually requires gas blanketing. This will eliminate the drawing in of excessive moistures. 40 41 14.0 TANK FARM CORROSION CONTROL USING CATHODIC PROTECTION When designing an internal cathodic protection system for such an important facility as an oil storage tank farm, careful consideration should be given to the size and nature of the problem. It is in many ways more complex than a conventional aqueous storage tank system. When the criteria for internal cathodic protection are examined, one begins to realize the extent to which the engineer is involved in instrumenting a successful cathodic protection system. Under normal conditions, the major factors governing the design of external cathodic protection are the total surface area of the structures to be protected, the quality of the coating, soil resistivity and the required life of the system. When protecting tank farm facilities however, additional thought should be given to structures, which come under the influence of the cathodic protection current. Because of the complexity of tank farm layouts, it is wise to include all facilities under the same protection system. For safety reasons, all oil storage tanks are lifted with a grounding system. This usually takes the form of bare copper cable looped round the tank and may have additional bare earthing mats or rods. The system may also be interconnected throughout the tank farm, making isolation of tanks or groups of tanks impossible. Fire hydrant systems are also a cause for concern when planning a protection scheme. Although relatively easy to isolate, when constructed of steel they also require protection. As the piping layout will inevitably the throughout the whole of the tank farm, it is wise to include it under the same system as the storage tanks. This will eliminate the possibility of interaction, which may be a serious problem. Water wells supplying storage tanks and hydrant systems can have their natural potentials reversed by interaction from deep well ground beds if not connected to the same source of protection. CRITERIA FOR INTERNAL CATHODIC PROTECTION Safety Aspects Due to the potentially dangerous environment and the need to minimize the risk of excessive current flows, sacrificial anodes are preferred to impressed current systems. All anodes should be attached directly to the structure, thus eliminating the possibility o “shorting”. The fact that the electrolyte fluctuates in level and can fall to only a few inches in depth also makes the use of sacrificial anodes more practical. 42 Surface Area to be protected When calculating the surface area to be protected, consideration should be given to the maximum basic sediments and water level in the tank together with the surface area of any ancillary equipment, which may be installed. Type and Quality of Coating Before an estimate of current requirement can be made, full facts relating to the type and quality of coating must be obtained. This is crucial as it may be years before the tank is opened for maintenance. Lack of information about the coating may result in premature anode failure. Electrolyte Composition Detailed analysis of the electrolyte is recommended as this may contain bacteria harmful to the type of coating in use, and ultimately affect current requirements. Information relating to pH values and resistivities of media will also be of assistance when choosing coating and anode materials. Monitoring the system It is not normal practice to have facilities installed to measure anode current outputs. Practical and safety reasons dictate that anodes are connected directly to the tank’s surface. However, it is important to measure structure to electrolyte potentials. Tank design will normally determine the location of electrodes should be placed at areas of high turbulence. Selection of Protective Materials Care needs to be taken when selecting the coating so as to guard against the possibility of cathodic disbanding. The integrity of the coating should be such that resistance to chemical attack by the known constituents within the media is guaranteed. History of Leak Rate and Anode Failure Information relating to anode failure and leak rate must be studied to as certain the possible need for different types of anodes, the quantity and their positioning. Tank Maintenance Timetable Before completing the list of requirements for cathodic protection it is necessary to consult the appropriate department to as certain the time span between tanks being opened. This is required to ensure that anode life will be maintained throughout the tanks’ service life. Other Equipment to be protected In addition to the protection of oil storage tanks there is usually the need to protect other vessels such as firewater storage tanks and wash tanks etc. Internal protection of fire hydrant standpipes is also a possibility. 43 Completion of Cathodic Protection System On completion of the installation the tank is ready to become operational. Due to the differing specific gravities, basic sediment and water will separate out naturally from the oil to form the electrolyte, but this will take place over a period of time. To avoid contamination of anodes and reference electrodes it is wise to fill tanks with water to drain off level prior to filling with crude. This will help in preventing the anodes and electrodes from becoming contaminated. It will also serve as a means of testing structure potentials, although these will change slightly once the natural electrolyte is formed. Monitoring the System To establish protection levels it is necessary to install permanent test facilities so that stable and accurate potentials may be recorded. The critical factors involved are the locations of the half-cell and the connection to the structure being monitored. Because tank farm locations are often subject to made up ground and imported backfill during the construction stage, halfcell positioning can be critical when determining protection levels. Large variations in potential readings have been recorded over a radius of three feet and less. Depth of half-cell and soil contamination from oil etc., may also affect readings. (Fig. 1). Costs Having collected all necessary information relating to the cathodic protection system to be adopted, a cost appraisal should be made to justify the expenditure. Type of Cathodic Protection to be used Due to such high soil resistivities and the size of most tank farm layouts, the current requirements dictate that impressed cathodic protection be used. Seasonal changes may also mean that current outputs have to be adjusted. CRITERIA FOR EXTERNAL CATHODIC PROTECTION Safety Aspects Safety aspects need to include the positioning of all negative cable connections away from flanges and valves, etc. Resistor boxes must be remote from all potentially hazardous environments. Surface Area to be protected When calculating the surface area to be protected, consideration should be given to all ancillary equipment, such as valves, connecting pipework and drain lines, etc. Type and Quality of Coating Information relating to all coated parts need to be taken into consideration when calculating current requirements. In the case of old tank farms it is very often the case that there is no reliable information available. It is quite normal to find a mixture of bare and coated structures throughout a tank farm. History of Leak Rate and Anode Failure Information relating to past leaks should be studied to help evaluate the effectiveness of previous and existing ground beds. Potential values need to be examined to help in the analysis when investigating records relating to leaks. Additional Current Requirement due to Ancillary Equipment Consideration to all ancillary equipment related to the tank farm layout must be taken into account. Items such as drain lines, flow lines, valves and cable conduit are usually part of the same electrical circuit as the main structures being protected. Influence on Other Structures It is most important that care be taken when introducing cathodic protection that there is no interaction with other structures, which are not under the same scheme. This is particularly so when using deep well ground beds as they tend to have a greater throwing power (Fig. 2). Ground Conditions Ground conditions have to be investigated and soil resistivity data obtained to provide as accurate a picture as possible regarding the overall electrolyte media. Other Equipment to be protected Other equipment to be protected may include water storage tanks, which can be protected by drawing current from other ground beds via a variable resistor box (Fig. 3). It is possible to protect a group of tanks in this way either internally or externally. By installing one or more anodes in or around such tanks and then regulating the current flow until the desired potential is achieved. 44 45 Costs Unlike internal cathodic protection where some tanks and vessels have a limited life span, external cathodic protection when applied to the above structures is always justified. Summary While it is recognized that long standing accepted data for design is the preferred option, due to the irregularities encountered in the application of cathodic protection under discussion, a certain amount of arbitrary measures and to some extent estimations have to be applied. When calculating the current requirement, it is wise to assume that surfaces are bare or poorly coated unless reliable information is to the contrary. To assist in the lowering of the groundbed to earth resistance (shallow groundbeds) excellent results have been achieved by increasing the groundbed size and by supplying a trickle feed of water from nearby hydrant standpipes. Although this may lead to over design of groundbed life, it is compensated for by the lower driving voltage required and the long-term savings of groundbed replacement. Results have shown that protection levels are best achieved by locating groundbeds evenly throughout the area to be protected. Transformer outputs were as follows: T/R V A 1 28 90 2 60 65 3 40 140 4 17 18 5 30 80 6 20 40 7 12 48 A total of 481 amps was required to protect the 19 storage tanks. Based on a surface area of 683.395 ft², actual current density = 0.7 mA/ft². Example of Current Requirement All field data and calculations below are based on actual information gained from an operational tank farm. Tank Farm A 19 tanks 214 ft dia. Surface area = 683, 395 ft² Current requirements for bare steel in soil = 1-3mA/ft² Current requirements for poorly coated steel in soil = 0.1 mA/ft² Based on bare steel current = 683 A – 2.050 A. Based on poorly coated steel current = 68 A. To protect fully the above tank farm, seven impressed groundbeds were installed, three deep well and four shallow. 46 47 APPENDIX I SUGGESTED APPROACH TO REFINERY TANK EXTERNAL INSPECTION Any evidence of deterioration that is considered dangerous to the operation of the tank must be considered enough reason to place the tank out of service for immediate corrective measures. 1. Foundation: - Evaluate evidence of foundation settlement. Excessive settlement is considered dangerous to the operation of the tank. a. Concrete ring wall: - Evaluate extent of concrete cracking and spalling. - Investigate the condition of any reinforcing steel bars. Diameter measurements and hammer testing can reveal their condition. - Surface concrete cracks can be repaired by dressing up the cracked area with mortar plasters. But if defect is general and considered to be serious, immediate repair must be considered. b. Earth Pad: - Evaluate extent of erosion (if any). Excessive erosion can cause excessive foundation settlement. 2. Shell: a. Investigate evidence of shell deformations such as bulging and buckling. In Cone Roof tanks, such deformation usually indicates faulty pressure-vacuum vents. This is considered dangerous to the operation of the tank. In Floating Roof tanks, deformations such as these are hardly experienced. b. Investigate evidence of leakage. Spots where there is paint discoloration or loss of paint films under a discolored spots indicate leak. The nature of the leak should be fully evaluated whether from stress cracking or corrosion. In Floating Roof tanks, it is possible to repair the leak even the tank is still in service by lowering the roof level to at least one-foot from the leak point. However, only cold work must be performed. In Cone Roof tanks, repair is only possible when the tank is out of service because of the inherent risk involved. c. Conduct ultrasonic thickness measurements on the shell wall. Such inspection can give good indication of the condition of the internal wall. However, if the internal wall can be inspected visually like in Floating Roof tanks, ultrasonic thickness measurement may not be required if there is no visible corrosion observed. 48 d. Evaluate the condition of the paint. An area that shows paint failures such as flaking, peeling-off, blistering, rust creepage, etc., should be given proper attention. Whenever accessible, the metal under this defects must be investigate the extent of corrosion that may have taken placed. After where there are deposits of sand, dirt and other foreign materials should also be investigated whenever possible. Such deposit usually creates a stagnant condition thereunder and thus, may initiate crevice corrosion. Isolated paint failure must be repaired by spot cleaning and spot painting following a sound procedure for maintenance painting. If failure were general, it would be wiser to submit the tank to a sound general repainting procedure. Another acceptable method of determining the remaining service life of the paint is by film thickness measurement. If the remaining film thickness is considered insufficient to protect the tank, repainting should be recommended. 3. Stairway/Platform/Walkway/Handrail: On these areas, failure usually occurs on spots where crevices are present. Crevice corrosion is always initiated on these spots. The extent of this form of corrosion should be evaluated. Shaking the handrails can give good indication of their condition. The inspection should show that these parts would remain in good condition at least until the next inspection. If this cannot be satisfied, an earlier program for maintenance repair should be recommended. 4. Manway/Clean-out door/Nozzle: Check for leakage on the manway and clean-out door cover. Leak indicates loose bolts or defective gaskets. Sometimes, it is the result of corroded flange mating surfaces between the cover and these attachments. Conduct ultrasonic thickness measurements on the necks of all these shell attachments. Refer to Appendix for the retiring thickness. Check the roof drain nozzle valve for any evidence of passing product. If found positive, this indicates faulty roof drain connection and the valve should be closed. Immediately, the check valve of the roof center sump should be investigated for possible product overflow. 49 All the telltale holes of the reinforcing pads of these attachments should be investigated for evidence of leakage. As the term denotes, it will tell you a tale about a leak. Leaks on this hole indicate either a crack at the heat-affected zones of the shell opening or weld defect of the shell attachment. 5. Roof: Because of the risk involved, inspecting the roof while the tank is still in service is not advisable. However, when the need arises, safety precautions laid-out on Sec. 12 of this booklet must be satisfied. Evaluate the condition of the wheel; the pinion block of the bearing must be fully lubricated. To check the bearing, it is advisable to lift the wheel to a certain extent that it can be rolled freely. e. Roof leg pipe sleeve/sampling hatch/Auto bleeder: Visual inspection can satisfactorily show their condition as per paint failure, broken parts and corrosion. a. Pressure-Vacuum Vents: Check condition of the vent. If found in poor condition, immediate repair should be recommended. It is dangerous to operate the tank with faulty pressure-vacuum vent because it could lead to the total failure of the tank. Records should be maintained with respect to the testing and calibrations of this vent. The vent must be set to open at 1.30 inch-water pressure and 0.06 inch-water vacuums. b. Roof deck and pontoon of Floating Roof tank: Investigate the roof deck and pontoon bulkheads for flooding. Unreasonable flooding is dangerous to the operation of the tank. Small leak that appears like a weep can be located by looking for signs of paint discoloration. Excessive leak that causes excessive flooding should be corrected without delay. Evaluate of the condition of the paint follows the outline given on item 2d. c. Roof center sump and check valve: The center sump should be free from any foreign materials or debris. The check valve if found open should be evaluated with respect to the cleanliness of the ball and the seat. If found closed, do not attempt to disturbed because this is an indication of product overflow due to the faulty roof drain connection inside the tank. Disturbing the valve may not maintain its tightness because of the possible presence of dirt. d. Rolling ladder and track: Check condition of all members in the manner the parts on item 3 is evaluated. 50 51 APPENDIX IIa APPENDIX IIb OULTINE OF THE COMMON FORMS OF CORROSION AND MAJOR CORROSION PROMOTING SUBSTANCES INSIDE THE REFINERY STORAGE TANKS SUGGESTED APPROACH TO REFINERY TANK INTERNAL INSPECTION Basically, internal inspection calls for the evaluation of the degree of corrosion that take place inside the tank. Referring to appendix IIa, the parts that are commonly attacked by corrosion are the floor, roof and the shell. The severity of corrosion is dependent on the type of the tank and the service to which it is employed. Since tank entry is required, it is of utmost importance that all the safety requirements laid-out for the aspect must be fully satisfied. Refer to Sec. 12.0 for safety requirements for tank entry. 1. Floor: As compared to the other parts of the tank, perhaps the floor is the hardest hit with corrosion. This is because of the usual settlement of contaminated water at the bottom. For mother tanks wherein heavy deep sludge are formed at the bottom, corrosion of the floor is usually less because more or less the sludge act as protection. But sometimes, whenever small pocket of water is trapped underneath, it results to highly localized corrosion that usually develops into a hole. Because of the usual dirty condition of the floor, it is advisable to make as standard practice the cleaning of the floor by means of abrasive blasting. It is only under this condition that proper and effective evaluation of the floor can be made. a. Evaluate the degree of corrosion on the floor: Referring to Sec. 10.0 and Appendix IIa, weld decay, pitting and crevice are the common forms of corrosion that are encountered in tankage. Thus as the primary step of evaluation, it is suggested that the Inspector should first conduct an overall visual inspection. If it is observed that severe general corrosion had taken-placed, renewal of the floor should be recommended. If the condition shows that renewal is not necessary, the following steps for evaluation are suggested: - 52 Investigate all seam welds. An area that exhibits weld decay should be repaired by grinding the decayed area and weld build-up. Conduct pitting survey. Perhaps this is the most difficult part of the inspection. Although still not considered a conclusive evaluation method, pitting depth measurement with the aide of a pit gauge can be satisfactory. 53 Isolated pittings with depths exceeding 25% of the original thickness should be repaired by weld filling. Areas wherein concentration of deep pitting is being exhibited, repair is made by patching. If it is observed that unreasonable scattered shallow and deep pittings are being exhibited, application of extra heavy thick coating as corrosion protection should be considered as principal remedial measure. b. Conduct thickness survey: This can be done with the of an ultrasonic thickness measuring device as described in Sec. 6.0 Usually, two properly oriented straight-line patterns across one another are satisfactory. If the thickness survey indicates suspect of corroded underside, it is advisable to cut coupons in progressive sizes (12” x 12” with increment o at least 2” at both sides) in order to evaluate the degree of the underside corrosion and at the same time verify the thickness of the plate. If severe underside corrosion is evaluated, renewal of the floor must be recommended. Refer to appendix IV for plate retiring thickness. c. Locating leaks: If the tank has been found leaking during service, methods described in Sec. 8.0 can be applied whichever is practical. In most cases, because of abrasive blast cleaning leak are simply located by looking for traces of wetting. Leaks can be repaired either by weld filling or patch plates. d. Look for spots exhibiting crevices: All crevices should be seal welded because they initiate crevice corrosion. e.g. - floor reinforcing plate under roof legs and columns. - strip plate underneath the level gauge float cable connection on the tank floor. e. Annular plates: In large tanks, this is the principal supporting member at the bottom region of the shell. It is important that the integrity of this section is always maintained. Refer to Appendix IV for the retiring thickness of the annular plate. 54 Evaluation of this section is similar to the floor plate. However, repair procedure is somehow more stringent. If patch repair is to be made, the patch plate should not be welded up to the shell. If unreasonable amount of scattered deep and shallow pittings are being exhibited, renewal of the plate should be considered. 2. Roof and Supports: Inspection of the roof and its support is not difficult to undertake. Most of the inspection performed is on the cone roof and practically very little inspection is needed on the floating roofs. a. Locating leaks: Leaks are simply located by men of visual inspection even without the use of mobile scaffolding. Hole can be easily seen by looking for light passage through the roof plate. In some cases wherein the roof tightness is required, vacuum testing as mentioned in Sec. 8.0 is also applicable. Repairs can be by soft patch or by welding patch plate. Sometimes, soldering is satisfactory. b. Evaluate the degree of vapor space corrosion: Requiring mobile scaffolding, visual inspection is a satisfactory method in the evaluation of the extent of vapor space corrosion that may take place on the roof plate and support members (truss or rafters). UT thickness survey is good for the roof plate while caliper measurement o the dimension of the support member is considered an effective yardstick in the determination of its serviceability. The remaining dimension of the support member must be within the limits of the section modulus given for the design load of the roof. For asphalt tanks where accumulation of heavy asphalts at the roof structure is possible, recommendation for the removal of this accumulation must be made. It could cause additional load to the roof and may result to overloading. 3. Shell: The shell is the least attack by corrosion but when corroded, sometimes it reached a degree that it would be better to erect new tank as replacement. 55 Tanks that are most susceptible to corroded shell are the Cone Roof types that are used to carry light intermediate products because these are the tank that undergoes more filling and emptying operations. Corrosion is always in the form of wide shallow and deep elliptical pittings and generally concentrated at the mid section of the working portion of the shell. At the lower portion of the bottom shell course, narrow deep pitting is usually exhibited because of the usual settlement of corrosive water. APPENDIX III SAMPLE REPORT A ANNULAR PONTOON FLOATING ROOF TANK EXTERNAL INSPECTION CHECKLIST Date 20-10-83 No. INP-143/83 Tank Identification T-1219 Service L-Crude Oil Area TF-4 Nom. Capacity 359, 959 bbls. Safe Filling Capacity 325, 712 bbls. Inside Diameter 57 mtr. Height 16.24 mtrs. Safe Filling Height 14.74 mtrs. Date Tank Last Inspected 28-8-82 Date Tank Last Cleaned 15-10-73 Inspected by R. S. Ibe Other Last internal inspection – 10/73 Parts 1. Foundation 2. Shell a. Paint b. Thickness c. Manway/Clean-out Door & Others 3. Stairway/Platform & Handrail 4. Roof a. Paint b. Pontoon c. Manholes d. Drains e. Vents f. Roof leg sleeve g. Anti Rotation Sys. h. Foam Dam i. Others 5. Rolling Ladder & Track 6. Windgirder/Walkway & Handrail 7. Nozzles/Valves 8. Level Gauge Pipe 9. Nameplate/Base Miscellaneous Condition G G VP G G VP VP VP G G P G G F G F P P VP G F G Remarks 1. Only superficial cracks were found on the foundation. 2. The tank is exhibiting general paint failure. 3. The platform chequered plate, stairs and the handrailings were found badly corroded and considered unsafe 4. The roof center sump was full of dirt and the drain check valve is in poor condition 5. The anti-rotation rafters are in poor condition. 6. The walkway is exhibiting scattered shallow and deep pittings Handrails are badly corroded. 7. The railing ladder track chequered plate is badly corroded 8. Galvanize coating of level gauge pipe has badly weathered Recommendations, Placing tank out-of-service - Dress up the foundation plasters & check grounding - Renew all parts found badly corroded. - Weld build-up all deep pitting found on the walkway plates - Clean roof center sump, service center checkvalve, ladder wheel bearings, anti-rotation rafters, all gate valves and among thermal relieve valves - Submit the tank to general repainting in the earliest time possible. The use of high performance point system must be considered. VP-Very Poor; P-Poor; F-Fair; G-Good; N-Not Accessible/Not Inspected 56 57 APPENDIX III SAMPLE REPORT B APPENDIX IV RETIRING LIMITS OF PLATE THICKNESS ANNULAR PONTOON FLOATING ROOF TANK INTERNAL INSPECTION CHECKLIST 1. Tank Shell: To maintain the safe operation of the tank, the shell plate thickness must not be less than the minimum thickness laid-out in API Std. 650. The retiring thickness is reached when the corrosion allowance is gone. Date 06-02-84 No. INP-005/84 Tank Identification T-1219 Service L-Crude Oil Area TF-4 Nom. Capacity 359, 959 bbls. Safe Filling Capacity 325, 712 bbls. Inside Diameter 57 mtrs. Height 16.24 mtrs. Safe Filling Height 14.74 mtrs. Date Tank Last Inspected 20-10-73 Date Tank Last Cleaned 15-10-73 Inspected by R. S. Ibe Other Last internal inspection – 10/73 Considering one-foot strip from the bottom of the shell course. Calculation of the shell thickness is as follows: t = 66(H-1) x D x G + CA Parts 1. Tank Floor a. Welds b. Plate Thickness c. Annular Plate d. Roof leg pads 2. Shell Internal Wall a. Seam Welds b. Manway/Nozzle Necks welds to Shell 3. Roof Deck underside a. Seal Pan b. Center Roof Drain Pit c. Roof drain sys. or Pipe swivel d. Roof leg e. Monkey ladder 4. Roof Seal a. Mechanical type - counter weights 5. Water draw-off sys a. Sump & Pipe Miscellaneous Condition P P G F G G G G G G F G G G G G G P Remarks 1. The floor and the annular plates are exhibiting scattered shallow and deep pitting about 50% of the pittings have Vertical cross-sectional shape. 2. About 50% of the floor lapped weld exhibits weld decay. 3. The roof leg pads were found skip-welded only to the floor. 4. About 1-meter of the shell from the floor is exhibiting scattered narrow-deep pitting. 5. Seal pan of roof emergency drain was found with thick accumulation of scale Recommendations: - Grind and weld build-up weld decays. - Seal weld all leg pads to the floor. - Consider the application of glass reinforced Epoxy (GRE) or polyster (GRP) lining on the floor plus 1-meter of the shell. - Clean seal pan - Service roof drain swivel joints and check valve. Others: All recommendations given in our internal Inspection report (06-01-84) still stands. VP-Very Poor; P-Poor; F-Fair; G-Good; N-Not Accessible/Not Inspected S where: t = minimum thickness in millimeters H = height of the tank in feet D = tank diameter in feet G = specific gravity of liquid to be stored - use 1 if G is less than 1 - use the actual value if G is neared than 1 S = maximum allowable stress in psi - for bottom course, both high and low strength steels: the lesser value of: 2/3 of the yield strength or 3/8 of the tensile strength - for all courses above the bottom course, for low strength steels; the lesser value of: ½ of the yield strength or 0.85 of the tensile strength - for all courses above the bottom course, for high strength steel; the lesser value of: 2/3 of the yield strength or 2/5 of the tensile strength CA = corrosion allowance taken to be 3 mm (1.5 mm is satisfactory for atmospheric exposure but additional 1.5 must be considered for the internal corrosion) 58 59 2. Floor and Roof: The minimum plate thickness for new plate should not be less than 6 mm for the floor and 5 mm for the roof including corrosion allowance. The retiring thickness is ½ of the original thickness. APPENDIX V SUGGESTED APPROACH FOR FLOOR RENEWAL OF SMALL CAPACITY TANKS (20, 000-30, 000 bbls.) Annular plate thickness must not be less than 7 mm including corrosion allowance. The retiring thickness is reached when the corrosion allowance is gone. 1. Removal of old floor: The complete floor shall be fire cut from the inside edge of the ring wall or 100 mm from the internal wall of the shell s shown in figure A. In order to have minimum distortion, the floor shall be gauge in 6-phases (A to F) diametrically opposite as illustrated in the welding sequence figure B. After completing the gauging of phase A, wedge or conical pins shall be used to lift the shell in order to provide sufficient clearance for taking out the old plates as well as bringing in the new ones. When the old plates are removed completely, compact bituminous sand with a slope of at least 1/100 from the center to the outside edge of the ring wall. At the center if there is a center column, a flat area slightly larger than the base plate of the column shall be left to assure good stability from the column. See figure C. 2. Installation of the new plates and welding sequence: All plates designated “P” in figure B and the center (CP) plate shall be installed first. The n all plates (PA) within phase A since it is the only phase open. At this stage, welding of welds “W1”, “W2” and “W4” is possible (fig. B). The shell shall be tack-welded (50-250 mm) to the new plate at this phase. Operate the same for phase B up to F in successive order with respect to the welding sequence. At the site, the sequence of some welds (W) may be modified for convenience. However, it must not be included in the shrinkage (S) frame. After all the plates are installed and tack-welded to the shell, the roundness of the tank must be checked before weld “W3” proceeds. As good practice, W3 must be carried out following the backstep method. Make sure that the lapped joints at the edge of the floor is formed in such a manner that it will provide a smooth contour to the shell as shown in detail Z on figure B. After all the welds are completed, if there is a center column, the plumbness of the column must be check before welding its clip guides. 60 61 Testing: APPENDIV VI MAINTENANCE PAINTING GUIDELINE Method laid out in Section 9 of this booklet is applicable: Lapped joints – vacuum testing Fillet “W3” welds – Gas-oil Tank note that gas-oil must be done before the external “W3” proceeds. 1. Sound paint not intended to b removed must not be damaged during the process of surface preparation. 2. Large areas intended for repainting and where abrasive blast cleaning is not practical, hydroblasting to a pressure of at least 6,000 psi should be performed. The process is good enough to remove not well-bounded paints, scums and other surface contaminants. This is followed by touch-up cleaning to ensure the further removal of the contaminants that were not removed during hydroblasting. Areas where surface profile is to be maintained should be abraded by means of mechanical abrader or other suitable means. 3. Hand tool or power tool cleaning are satisfactory methods of surface preparation of small areas. However, in case of live pipings or surfaces and areas considered hazardous, the use of power tool is not allowed. Only sparkle brushes and scrappers are allowed. 4. Junctions between the spot cleaned areas and sound paints should present a smooth feathered appearance. All spot cleaned areas must be spot primed and must overlap the adjacent sound paint to a slight extent for assurance of full coverage. 5. Before the work has progress too far, adhesion of newly applied paint over any existing sound paint must be investigated. It is advisable to explore beneath the surface of the new paint coveredover rust and loosening of film. If such conditions are discovered, the surface must be cleaned and repainted. 6. The effect of newly applied paint over the old underlying film should be noted. Any evidence of curling, lifting and excessive wrinkling must be repaired. If defects are general rather than existing in few isolated areas, the use of difference paint system must be taken into consideration. 62 63 APPENDIX VII MISCELLANEOUS DATA AND TABLES 1. Pascal’s Law: At any point in a fluid at rest, the pressure is the same in all direction. 2. Pressure: The intensity of a pressure exerted at any point is the amount of force per unit area. calculated in the formula below: PD T = (12.7) St where: t - minimum wall thickness in millimeter P - allowable pressure in psi D - inside diameter of the pipe in inches St - tensile stress in psi F P = 6. Doubling the diameter of the pipe will increase its carrying capacity four times. A where: P - the unit pressure. F - force exerted on a certain area and at all times acting normal to the plane surface of that area. A - the cross-section of the area subject to the force F. 7. Rule of thumb: If in a branch connection, twice the design pressure exceeds the allowable pressure at the header, reinforcing is required. For full calculations, methods laid-out in ANSI B31.1 and B31.3 are generally followed. 3. Variation of pressure with respect to the depth of the fluid. 8. For relatively short headers where multiple branch connections are intended, increasing the thickness of the header can be applied if reinforcing is not possible. P = wh where: P - the pressure due to the available head in psf. w - density of the fluid in lb./cu.ft. h - available head in feet. To convert psf to psi, divide by 144. Thus, if w = 62.4 lb./cu.ft. (water): p = 0.433h 9. To find the area of a circle, multiply the square of the diameter by 0.785, or multiply the square of the circumference by 0.0796. 10. To find the diameter of a circle equal in area to a given square, multiply a side of the square by 1.128. 11. To find the side of a square equal in area to a given circle, multiply the diameter of the circle by 0.886. 4. Relationship of height of a certain liquid to another liquid. a. To convert the height of any liquid to height of water, multiply the height of the liquid by its specific gravity. b. To convert the height of water to height of liquid, divide the height of water by the specific gravity of the liquid. 12. To find the surface area of a sphere, multiply the square of the diameter by 3.14. 5. The retiring thickness of the pipe is considered reached when the corrosion allowance is gone. As a good guideline, the remaining thickness must not be lower than the thickness 14. °C = (F-32) : °F = (°C x 1.8) + 32 1.8 15. °C + 273 = °Kelvin : °F + 460 = °Rankine 64 13. To find the volume of a sphere, multiply the cube of the diameter by 0.524. 65 TANK DIAMETER, AREA, VOLUME Tank Diam. (m) 5 6 8 10 12 15 16 18 20 22 25 26 28 30 32 35 36 38 40 42 45 46 48 50 Shell Area /meter ht. (m²) 15.70 18.84 25.12 31.40 37.68 47.10 50.24 56.52 62.80 69.08 78.50 81.64 87.92 94.20 100.48 109.90 113.04 119.32 125.60 131.88 141.30 144.44 150.72 157.00 Bottom Plate Area (m²) 19.625 28.260 50.240 78.500 113.040 175.630 200.960 254.34 314.00 379.94 490.63 530.66 615.44 706.50 803.84 961.63 1017.36 1133.54 1256.00 1384.74 1589.63 1661.06 1808.64 1962.50 TANK VENT REQUIERMENTS Volume (bbl) Per meter ht. 123.44 177.75 316.01 493.77 711.02 1110.97 1264.04 1599.80 1975.06 2389.82 3086.06 3337.85 3871.12 4443.89 5056.15 6048.92 6399.19 7129.97 7900.24 8710.02 9998.74 10448.07 11376.35 12344.13 Over 50 meters, multiply bottom plate area by 6.29 to get bbl. Per meter ht. of shell. Tank Size I.D. (meter) Max. Pumping Rate (bbl/hr) Vent Req’d No Size 3–6 1, 000 1 4” 7–9 3, 000 1 6” 10 – 15 5, 000 1 8” 16 – 20 5, 000 1 10” 16 – 20 10, 000 1 12” 21 – 30 5, 000 1 10” 21 – 30 10, 000 1 12” 21 – 30 15, 000 2 10” 31 – 35 5, 000 1 12” 31 – 35 10, 000 2 10” 31 – 35 15, 000 2 10” 31 – 35 20, 000 2 12” 31 – 35 25, 000 2 12” 36 – 45 5, 000 2 10” 36 – 45 10, 000 2 12” 36 – 45 15, 000 2 12” 36 – 45 20, 000 3 12” 36 – 45 25, 000 3 12” Over 45 Straight line extrapolation of API 2000 Vent Req’d Heated Tanks No Size 1 12” 1 12” 1 24” 1 24” 1 24” 1 24” 1 36” 1 36” 1 36” 1 36” 1 36” 1 36” 1 36” 1 36” 1 36” 1 36” 1 36” 1 36” The Pressure Vacuum vents shall be used when the ff. conditions apply: - Flash point of the stock is less than 100 °F. - Temperature of the stock is above or within 15 °F of its flash point at the highest of plating temperature. - The stocks are valuable and have low vapor pressure. The Pressure-vacuum vent should be set to open at 1.30 inch water pressure and 0.66 inch water vacuum. Flame arrestors are not required. 66 67 TABLE – VARYING SURFACE CONDITION TABLE – WORK DONE WITH DIFFERENT NOZZLE SIZES Surface Condition Division 1 – New Construction Class 1 Notes: 1. Removed of heavy mastic, grease and other materials difficult to remove by sandblasting were not considered. 2. Figures were based on surfaces that are immediately accessible. 3. Brush off grace, light blast cleaning that will remove only loose mill scale, rust and other foreign matter. 4. Commercial blast grace, thorough blast cleaning that will remove at least two-thirds of all tightly adhering mill scale, rust and other foreign matter. 5. Near-white metal grace, very thorough blast cleaning that will remove at least 95% of the total tightly adhering mill scale, rust and other foreign matter. 6. White metal grace, blast cleaning to pure metal. All tightly adhering mill scale rust and other foreign matter are completely removed. Description : Steel with tight mill scale Class 2 : Steel with loose mill scale and Fine amorphous rust, no pits. Class 3 : Practically no mill scale, over rust, some pitting Division 11 – Maintenance Class 4 : Thin finish coat, some primer showing, rust negligible Class 5 : Thin finish coat, considerable primer showing, 10% of surface contains rust, loose mill scale and loose coating film. Class 6 : Finished coat thoroughly weathered and badly bustered about 30% of surface contains rust with pitting and hard scale Class 7 : Badly pitted steel with rust nodules. Note: 1. Class 4 and 5 requires blasting cleaning. 2. Class 1, 2, and 3 requires blast cleaning to remove mill scales and to provide the desired anchored pattern for better adhesion. The importance of the removal of mill scale is that it is cathodic to steel and being cathodic, establishes and electrical corrosion cell that will result to subsequent ptiing. Moreso, it flakes in slight variation of temperature thus causing premature failure to coating. 3. Class 6 and 7 requires blast cleaning because of being considered as general deterioration. SUGGESTED PRACTICE FOR BLAST CLEANING 1. Cleaning should proceed by sections, bays, or other identifiable areas of work. Cleaning of each section must be entirely completed, inspected and accepted before the application of coating. 2. The substrate should be decrease, all rough edges and protrusions should be removed and ground to smooth contours before blasting proceeds. 3. No blast cleaning should be done on surfaces that are moist or will become moist before the application of coating. It should only precede when surface temperature is over the dew point or when the relative humidity is below 80%. 4. No blast-cleaned surface should be allowed to remain uncoated overnight unless special precautions are taken. Under favorable condition, only a maximum of 4 hours is allowed for blast-cleaned surface to remain without coating. 5. To eliminate traces of blast product on the surface, cleaning are satisfactorily carried out with the use of clean brushes made of hair bristles, blowing with dry air and vacuum cleaners. Wiping with cloth or rug should be avoided. They usually introduce lints that are detrimental to coating adhesion. 68 69 6. To minimize the nuisance of the dusty blast products and to make blasting faster, the nozzle should be at least aimed 2 to 3 feet from the surface to be cleaned and at an angle. Ideally, blasting at 45° angle is most satisfactory. 70 APPENDIX VIII NDE Requirements Summary API 653 Table F.1 71 Acceptance Standards: Air Test: None Pen Oil: None MTPT: ASME Section VIII, Appendix 8 (paragraphs 8-3, 8-4, 8-5) RE: ASME Section VIII (paragraph UW-51(b)) Tracer Gas: None UE: API Std. 650, Section 8.3.2.5 VB: None VE: API Std 650, Section 8.5.1 Examiner Qualifications: Air Test: None Pen Oil: None MTPT: API Std 650, Section 8.2.3 RE: ASNT SNT-TC-1A Level II or III. Level I personnel may be used under the supervision of Level II or Level III personnel with a written procedure in accordance with ASME Section V, Article 2. Tracer Gas: None UE: ASNT SNT-TC-1A Level II or III. Level I personnel may be used under the supervision of Level II or Level III personnel with a written procedure in accordance with ASME Section V, Article 2. VB: API Std 650, Section 8.6.4 VE: API Std 650, Section 8.5.1 Procedure Requirements: Air Test: API Std 650, Section 7.3.5 Pen Oil: None MTPT: ASME Section V RE: ASME Section V, Article 2 Tracer Gas: API Std 650, Standard 8.1.11.c UE: ASME Section V VB: API 650, Section 8.6 VE: None 72 73 APPENDIX IX NDE Requirements Summary API 650 Annex T 74 75 Acceptance Standards: MT : ASME Section VIII, Appendix 6 (Paragraphs 6-3, 6-4, 6-5) PT : ASME Section VIII, Appendix 8, (Paragraphs 8-3, 8-4, 8-5) RT : ASME Section VIII, Paragraph UW-51(b) Tracer Gas : API Std 650, Section 8.6.11.b UT : For welds examined by UT in lieu of RT, acceptance standards are in Annex U.6.6. For UT when RT is used for the requirements of 7.3.2.1, the acceptance standard is as agreed upon by the Manufacturer and Purchaser. VB : API Std 650, Section 8.6.9 VE : API Std 650, Section 8.5.2 Examiner Qualifications: MT : API Std 650, Section 8.2.3 PT : API Std 650, Section 8.4.3 RT : ASNT SNT-TC-1A Level II or III. Level-I personnel may be used under the supervision of a Level II or Level III with a written procedure in accordance with ASME Section V, Article 2. Tracer Gas : None UT : For welds examined by UT in lieu of RT, the inspector must be ASNTTC-1A or CP-189 Level II or Level III per API Std 650 Annex U.4.1. For UT when RT is used for the requirements of 7.3.2.1, the required qualifications are ASNT-TC-1A Level II or Level III. A Level I may be used with restrictions, see API Std 650, Section 8.3.2. VE : API Std 650, Section 8.5.1 VB : API Std 650, Section 8.6.4 Definitions: MT Pen Oil PT RT VB VE = Magnetic Particle Examination = Penetrating Oil Test = Liquid Penetrant Examination = Radiographic Testing = Vacuum-Box Testing = Visual Examination 76 Procedure Requirements: MT : ASME Section V, Article 7 PT : ASME Section V, Article 6 RT : A procedure is not required. However, the examination method must comply with ASME Section V, Article 2. Acceptance standards shall be in accordance with ASME Section VIII, Paragraph UW-51(b). UT : For shell welds examined by UT in lieu of RT, ASME, Section V, Article 4 and API Std 650 Annex U.3.5. For welds when RT is used for the requirements of 7.3.2.1, ASME Section V. VB : API Std 650, Sections 8.6.2, 8.6.5, 8.6.6, 8.6.7, and 8.6.8 VE : None Tracer Gas : API Std 650, Section 8.6.11.a 77