Uploaded by miguel.morales

51180 IOM Rev0

advertisement
COMBUSTION RENTALS & RAPID EXECUTION
Flare System
Installation & Operation Manual
Elevated Flare
24” Modular Stack Design
Retractable Pilot Components
Zeeco, Inc.
22151 East 91st St.
Broken Arrow, OK 74014
Ph: +1 918 258 8551 | F: +1 918 251 5519
24 HR FIELD SERVICE: +1 844 GO ZEECO (844 469 3326)
Table of Contents
Equipment Installation .................................................................................................................................. 4
Stack Assembly .......................................................................................................................................... 4
Installation of Retractable Tubing and Components ................................................................................ 6
Thermocouple Probes ............................................................................................................................... 6
Ignition (HEI) Probes.................................................................................................................................. 7
Stack Erection ............................................................................................................................................ 7
Guy Wire System ....................................................................................................................................... 8
Piping/Tie-Ins........................................................................................................................................... 10
Control System Set Up and Wiring.............................................................................................................. 11
Purging Requirements ................................................................................................................................ 11
System Operation Overview ....................................................................................................................... 12
Pilot Ignition/System Commissioning ......................................................................................................... 13
Start-up Sequence ................................................................................................................................... 13
Alarm Conditions ..................................................................................................................................... 14
Waste Gas Introduction .............................................................................................................................. 14
Troubleshooting .......................................................................................................................................... 15
Pilot Maintenance ....................................................................................................................................... 17
EMERGENCY PROCEDURE - OPERATOR ALARM RESPONSE AND TRAINING
EMERGENCY PROCEDURE - REIGNITION OF PILOT
SYSTEM CHANGE LOG
PILOT OUTAGE LOG
PROJECT DRAWINGS
Revision
Date
Description
0
7/1/22
Initial Release
2
The following is a reference for setup and operation of the described flare system. This
information should be used in conjunction with facility safety practices and work protocols.
WARNING
All facility safety procedures and guidelines must be followed during the installation of the flare
stack. Coordinate with site safety personnel to determine what precautions must be taken
before beginning any installation of or repair to the system.
If site operators are not comfortable with the setup and operation of flaring equipment, it is
recommended that Zeeco Global Field Services be contacted for any questions, installation
services, or support for commissioning/training.
3
Equipment Installation
The following sections outline the steps and recommended practices to successfully assemble
and erect the described flare system.
WARNING
The supplied equipment may contain components and parts with small ports/openings that can
become plugged. It is mandatory and critical to proper operation that all components and
piping of the system be blown out and inspected to be free of scale, debris, trash, liquids, etc.
All aspects of the system installation should be governed by the field installation crew. The field
installation crew should familiarize themselves with the local safety procedures and regulations
governing this installation.
Zeeco flare stack assemblies utilize one of two base types: Foundation-mount ring and Skid. If
the stack assembly uses a Foundation-mount base ring, the stack should be installed on an
appropriately designed foundation pad. The design and installation of the referenced
foundation pad is the responsibility of the customer/end-user. If the stack assembly uses a Skid
base, it is common to install the flare stack assembly on either a foundation pad or directly on
grade. If installing the stack assembly directly on grade, the below recommendations are
offered:
• Remove loose debris and any problematic soil (e.g. high expansive clays) in the area
near the flare stack assembly
• Level and compact soil to 95% density (Proctor)
• Top 4”-6” to be compacted #2 limestone or crushed stone (typical)
• Area shall be properly drained, and considerations taken such that area will not hold
standing water at any time
• Grade shall not have a slope exceeding 1° witnessed; Zero (0°) slope is highly preferred
• If necessary, helical piers or other acceptable means of anchorage/support may be used
It is recommended that either before the stack erection process begins, or simultaneous to the
steps outlined below, the guy wire system anchors be installed. This is recommended to reduce
the required amount of crane time at site.
Stack Assembly
Sections of the flare stack assembly should arrive in a horizontal configuration on freight carrier
trailers. Wherever possible, stack sections will be oriented on the trailer deck such that the
section can be lifted directly vertical and placed onto assembly supports without the need to
rotate the section along the longitudinal axis. In some cases, sections may have constraints
during shipping to avoid damage to attachments and may require rotation as part of the
offloading process.
4
Before offloading stack sections onto assembly supports, care should be taken by the field
installation crew to identify the best location for assembly relative to the lifting process and
final target location for placement of the flare stack base.
As stack sections arrive and are prepared for offloading, refer to Zeeco project drawings and
any relevant markings on stack sections to identify the proper assembly configuration. The
temporary flare stack assembly is designed such that a top section (including flare tip), base
section, and middle section(s) are used to complete configurations of varying heights. The stack
assembly is designed to be modular such that middle sections can be added or removed to
achieve the desired height configuration for the designed application.
After all stack sections have been identified, offloaded, and placed on assembly supports,
appropriate fasteners and hardware can be retrieved from the provided Zeeco job box. The
provided job box will contain all necessary hardware, fasteners, gaskets, fittings, guy wire
components, etc. for proper assembly of the flare system.
Stack sections should be fit-up and alignment of all utilities and flange connections verified.
Flanged stack connections should be made using the provided hardware and gasket materials.
Torque values and bolting patterns should be in accordance with gasket manufacturer
recommendations and typical industry practice on raise face flanged connections. After each
flanged connection is made, a flange torque record sheet entry should be made as part of the
installation documentation package.
Depending on the application, the flare stack assembly may also be using one or more external
risers for assist media. Follow the same protocol as established by the field installation crew for
connecting external riser sections together after the applicable stack joint is made. Care should
be taken to review the project drawings and mechanical connection points for the external
riser(s) to properly utilize any ANCHOR or GUIDE supports as intended.
WARNING
External riser sections will be tightly anchored to their supports for transit purposes. When
assembly takes place, it is critical that all external riser fasteners (u-bolt typical) be loosened
and properly anchored to serve as a GUIDE in the proper locations in accordance with project
drawings. Common practice is to remove double nuts on u-bolt, remove u-bolt, install nuts such
that they tighten on either side of support material creating a rigid loop that is not tightly
affixed to external riser piping. This allows riser piping to move if needed due to thermal
expansion or other forces.
Once all stack sections are assembled together, the pilot gas line should be connected across
the entire assembly. Starting at the flare tip, the top section of the stack should already have
the pilot gas line connected to the pilot manifold and mounted to the appropriate utility
brackets. Following the line down the stack, connections will need to be made using the
appropriate threaded hardware near each stack joint. Depending on shipping configuration,
pilot gas line sections may need to have the fasteners loosened to allow adjustment of each
5
pilot gas piping run to allow for successful mate up with the adjacent piping run. Once all
sections are connected, the pilot gas spool inlet at the base of the flare stack assembly should
be at or near the elevation listed on the project drawings. Care should be taken to review the
project drawings and mechanical connection points for the external riser(s) to properly utilize
any ANCHOR or GUIDE supports as intended.
Installation of Retractable Tubing and Components
Zeeco rental pilots are designed to be static with respect to the flare tip. The pilot is rigidmounted but the critical components (ignition and thermocouple probes) are designed to be
retractable from grade for ease of service/maintenance. The probes are retractable via
dedicated guide tubing runs routed up the stack.
The sections of flare stack will be outfitted to the greatest extent possible with utilities and
retractable tubing without risking critical damage during shipment. Depending on the stack
section design, some components (e.g. tubing sticks, fittings) may ship loose to protect integrity
prior to arrival at site.
When stack sections are aligned and assembled, utility brackets oriented under each pilot
should align with each other down the entire stack assembly from flare tip to base. These utility
brackets hold any relevant piping runs and the retractable guide tubing for both the ignition
and thermocouple probes. After stack sections are aligned and bolted together, the retractable
tubing can now be aligned and connected.
The brackets that support the tubing should align such that each tubing run is straight and free
of kinks or severe bends. Some sweeping bends are allowed but should not exceed a 10’ bend
radius whenever possible. The flare stack assembly is designed such that upper most bracket
(directly under the pilot connection) will serve as an ANCHOR for the retractable component
guide tubing. All other brackets running down the stack are to serve as a GUIDE only and will
not fit tight to the tubing.
WARNING
It is critical to verify on all tubing runs that the upper most bracket is tight, and all others are
loose. Failure to do so can result in damage to the guide tubing and the relevant probe inside.
Once all tubing connections are made, the applicable probes can be installed. It is
recommended to do the initial install while the stack assembly is in the horizontal position for
ease of installation. The ignition and thermocouple probes should be straightened to the best
of the user’s ability before inserting into the guide tubing. Many customers opt to use a
thermocouple straightening design for mechanical assistance during this effort.
Thermocouple Probes
The thermocouple probe should be inserted such that the lead end bottoms out in the
thermowell located in the pilot hood. Recommended practice is to install the thermocouple
6
probe in the guide tubing until the lead end bottoms out in the thermowell, mark the end of
the guide tubing on the probe (at base of stack) with a mark, then back the probe out and push
again to verify you have truly reached the end of the thermowell. Once set, tighten the
compression fitting located at the end of the guide tubing to lock the thermocouple probe in
place. The remaining probe length can then be looped over to the termination point on the
junction box assembly. Refer to project drawings for more details on wiring terminations.
Ignition (HEI) Probes
The ignition probes should be inserted such that the spark tip contacts the 90-degree bend in
the guide pipe on the pilot. Recommended practice is to install the ignition probe in the guide
tubing until the spark tip makes contact, mark the end of the guide tubing on the probe (at base
of stack) with a mark, then back the probe out and push again to verify you have truly reached
the bend in the pilot. Once finished, back the probe out such that the final mark is
approximately 1” from the end of the guide tubing. This should translate to the spark tip being
approximately 1” from the 90-degree bend in the guide pipe on the pilot. This is optimal
placement for reliable ignition. Once set, tighten the compression fitting located at the end of
the guide tubing to lock the ignition probe in place. The remaining probe length can then be
looped over to the termination point on the junction box assembly. Refer to project drawings
for more details on wiring terminations.
Stack Erection
All aspects of the erection of the system are the sole responsibility of the field installation crew
or lift contractor. The field installation crew or lift contractor should exercise good practice and
experience to decide how to safely and efficiently erect the system.
WARNING
Refer to Zeeco project drawings for designated lift and tailing points on the assembled flare
stack. Use of any other non-designated lift and tailing points could result in equipment failure
and/or personal injury.
7
After flare stack has been fully assembled, the field installation crew or lift contractor should
inspect the overall assembly and all parties should sign off prior to erection. It is also
recommended that a lift plan be drafted by the field installation crew or lift contractor,
reviewed by all parties, and sign off should occur prior to proceeding with erection.
The primary lift crane should be connected to the proper lifting trunnions on the flare stack
using acceptable lifting components at the discretion of the field installation crew or lift
contractor. Spreader bars or other acceptable means of lift alignment may be required to
successfully erect the stack.
WARNING
Lift connections on flare stack trunnions must not exceed +/- 10° from vertical at any point
during the erection process. Exceeding 10° of angle (relative to vertical centerline of trunnions)
could result in mechanical failure of the trunnion weldment.
The tailing crane should be connected to the proper tailing lug on the flare stack using
acceptable lifting components at the discretion of the field installation crew or lift contractor.
Final inspection should occur before the lift begins to ensure that lifting apparatuses will not
contact or interfere with any stack components or attachments. This is critical to ensure that no
undue damage occurs to the flare stack assembly which will require elevated repair work.
Guy Wire System (if applicable)
Refer to provided equipment drawings for guy wire information. Guy wire anchors must be
installed prior to completing the steps below.
Guy wire sockets should be connected to the appropriate guy lug locations on the flare stack
assembly prior to erection. While the stack assembly is vertical and before crane support is
released, guy wires must be installed and tensioned.
WARNING
“Never saddle a dead horse.”
CORRECT
LIVE END
LIVE END
DEAD END
DEAD END
WRONG
It is typical to tension guy wires using two common methods. One method is applicable for
stack systems with a single level of three (3) guy wires equally spaced in 120° increments
around the stack circumference. The second method is applicable for stack systems with one or
more levels of three (3) guy wires equally spaced in 120° increments around the stack
circumference. These methods are briefly outlined below.
8
Ultimate installation and tensioning practices are the responsibility of the field installation
crew.
WARNING
Do not over-tension guy wires. Increase tension slowly and deliberately. Do not go to full
tension immediately.
Method 1
Equipment: (2) Transit, (1) Tension Meter total
1. Gather all equipment necessary for tensioning including guy wires, turnbuckles, transits,
temporary wire, tension meter and chain block, winch or other tension adjuster.
2. Attach the three (3) guy wires from the flare stack to the appropriate anchors using
chain block, winch or other tension adjuster as necessary. At this time, turnbuckles
should be set in the maximum open position.
3. Set two transits, 90 degrees from each other, to ensure visual confirmation of the
verticality of the flare stack.
4. Set the tension meter on one of the three guy wires by using temporary wire and
tension adjuster, as shown in depiction below.
5. As you increase the tension on the tension meter, the stack will move from the vertical.
You will need to use the other turnbuckles located on the other two guy wires to move
the flare stack back to the vertical. The stack will be set when the tension meter reads
the required tension (refer to equipment drawings) and the stack is still vertical.
6. After the stack is set in place, make sure that the correct tension reading is shown on
the tension meter and (using the two transits) that the stack is vertical. The tension
meter can be removed by tightening the turnbuckle on the guy to which it is attached
until all tension is removed from the tension meter. Do not tension the guy wire any
more than is necessary to remove all tension from the tension meter. You may then
loosen the turnbuckle attached to the tension meter and remove all tension meter
components.
Method 2
Equipment: (0) Transit, (1) Tension Meter per guy wire
1. Gather all equipment necessary for tensioning, including guy wires, turnbuckles,
temporary wire, tension meters and chain block, winch or other tension adjuster.
2. Attach each guy wire from the flare stack to the appropriate anchor using chain block,
winch or other tension adjuster as necessary. At this time, turnbuckles should be set in
the maximum open position.
3. Set a tension meter on each guy wire by using temporary wire and tension adjuster, as
shown in depiction below.
4. Incrementally increase the tension on each tension meter, one after another, taking care
to prevent the stack from moving from the vertical. The stack will be set when all tension
meters read the required tension (refer to equipment drawings) and the stack is vertical.
9
5. After the stack is set in place, make sure that the correct tension reading is shown on all
tension meters. Each tension meter can be removed by tightening the turnbuckle on the
guy to which it is attached until all tension is removed from the tension meter. Do not
tension the guy wire any more than is necessary to remove all tension from the tension
meter. You may then loosen the turnbuckle attached to the tension meter and remove
all tension meter components from the guy wire. Repeat for each guy wire until all tension
meters have been removed.
Piping/Tie-Ins
The following steps are to be completed in conjunction with referencing provided mechanical
drawings for the specific equipment.
1. Attach pilot gas supply piping to the NPT union inlet located on the pilot gas instrument
spool at the base of the flare stack. Pilot fuel supply gas may be propane or natural gas.
a. Propane requirement is 39 Scfh @ 15 psig (approx. 1.0 gal/hour of liquid propane)
b. Natural gas requirement is 65 Scfh @ 15 psig
i. Rates listed above are PER PILOT.
NOTE: Maximum operating pressure of pilot fuel gas supply must not exceed 50 psig.
NOTE: Pilot fuel gas supply must contain less than 5 ppm H2S.
NOTE: Pilot fuel gas supply must have upstream overpressure protection of 400 psig.
NOTE: Temporary gas piping should be protected by site operators from potential of
mechanical damage. Acceptable standards include flagging, cones, protective trays, etc.
2. Attach flare waste gas header piping to one of the flanged 150 # raised-face flare gas
inlet connections located at the base of the stack. Use appropriate gasketing and
hardware for flanges.
NOTE: Temporary gas piping should be protected by site operators from potential of
mechanical damage. Acceptable standards include flagging, cones, protective trays, etc.
3. Attach steam or assist media header piping to the flanged raised-face connection on the
external piping riser attached to the main 24” flare stack body. Use appropriate
gasketing and hardware for flanges.
10
NOTE: Temporary gas piping should be protected by site operators from potential of
mechanical damage. Acceptable standards include flagging, cones, protective trays, etc.
4. It is recommended that some sort of isolation or control valve be installed at least 50
feet away from the system in the flare waste gas header piping. This will allow the
system to be controlled and isolated without requiring personnel to get too close to the
flare in the event of an emergency.
NOTE: Waste gas supply must be isolated and closed before pilot ignition. Flare purge
should be initiated at furthest point from flare system immediately downstream of
waste gas isolation valve.
Control System Set Up and Wiring
The following steps are to be completed in conjunction with referencing provided detailed
electrical schematic drawings for the specific equipment.
1. Customer power service (120VAC/1Ph/60Hz/10A) is to be connected to power supply
terminals located in enclosure on control panel skid.
NOTE: Power supply should be from either UPS or equivalent power source such that
supply cannot be interrupted while flaring.
2. Interconnect wiring must be connected in the field between the local control panel and
the stack-mounted junction box. Ensure that interconnect does not interfere with travel
paths, etc. or is kinked, pinched, flattened, or otherwise visibly damaged.
NOTE: Interconnect should be protected by site operators from mechanical damage.
Acceptable standards include flagging, cones, protective trays, etc.
3. If alarms/remote signals are being used, terminate appropriate facility interconnect
wiring to the applicable terminals.
4. Make required ground connection(s) at grounding lug(s) on both the flare base skid and
any control enclosures. Ensure bare metal/metal contact at all grounding terminations.
Once the above steps are completed, facility technicians should perform loop checks on all
appropriate circuits to ensure continuity and proper operation. The local control panel pilot
switches include a MAN option to enable manual firing of each ignitor. This can be used during
the pre-commissioning phase to verify continuity of the ignition system and proper operation.
Purging Requirements
There is danger of severe explosion in a flare system if the flare pilots are ignited before the
flare has been purged. It is important to purge the entire flare system with a volume of noncondensable gas (typical 5-10 volume changes) to ensure there is no oxygen present in the
system. The flare system includes all piping from relief valves to the riser through the elevation
of the flare at the burning point. Steam should not be used as a purge media.
11
The pilots should be ignited only after the system is thoroughly purged, and as the purge gas is
still being admitted. If the purge gas is combustible, the burning of the purge gas at the flare
will be proof of pilot ignition.
Safe operation of the flare system requires that there be no air, and thus no oxygen, present in
the flared gases as they reach the pilots. The quantity of purge gas is set to avoid entry of air
into the flare system while the flare is in operation and the pilots are burning. Ensure that the
flare system is gas tight prior to purging. Any included liquid seals must be filled with liquid to
the requisite depth prior to purging the flare system. Any manways or inspection openings to
the flare gas line must be blinded. If it is required that the flare system be opened for any
reason, extinguish the pilots before work begins and do not re-ignite them until after the
system has been thoroughly purged. The flare system must be absolutely gas tight before
ignition.
It is recommended that purge flow rate be measured, and appropriate steps taken should a low
flow condition occur during the purging process.
An oxygen-free, clean piping system is ultimately the best practice in any flaring application.
Upon completion of the stack purge, the pilot ignition sequence may be initiated.
System Operation Overview
The flare system and tip configuration is selected by Zeeco considering the various design
parameters discussed with the customer during the inquiry phase. The flare tip and relevant
combustion apparatuses will be selected such that smokeless flaring is achievable across the
designed range of operating conditions (typical); final determination of smokeless flaring needs
will be set by customer through design discussions with Zeeco. In many safety relief scenarios,
it is typical that smokeless flaring requirements do not apply. If you have questions regarding
the selection of the temporary flare system and capabilities, please contact your Zeeco
representative.
Zeeco pilot systems are the leader in industry performance and reliability. The pilots used on
the temporary flare system are the same models and components used in permanent
installations across the world. The pilots are designed to be static mounted at the flare tip for
accurate location to ensure reliable ignition. Zeeco pilot mixers are made from high quality
investment castings and precise machined components to provide reliable performance across
a wide range of operating conditions. Critical pilot components are designed to be retractable
from grade for ease of maintenance and replacement. At the base of the flare stack, the pilot
instrument spool is located for easy operator access. This spool assembly contains the
instrumentation and flow control needed for proper pilot system operation.
Dependent on the needs of the application, assist media may be used in conjunction with the
flare tip design. Using air or steam for assist is typical in most applications. The assist media is
often used to increase turbulence to entrain ambient oxygen into the waste gas to provide
12
more efficient mixing for combustion. Various methods are used for assist control – please
contact your Zeeco representative for more information on using assisted flaring.
Accompanying the flare system is a Zeeco control system with the primary function of
monitoring and controlling the pilots. This system is typically comprised of a local control panel,
stack-mounted junction box, and interconnect wiring. In some cases, additional
instrumentation may be used to satisfy the operational needs of the application.
The below table summarizes critical set points for the temporary flare system detailed in this
document:
Pilot Fuel Supply Pressure
50 PSIG Maximum (Natural Gas¥ or Propane)
PSLL-201
7 PSIG
PCV-101/PCV-201
15 PSIG
Pilot Proven Temperature
350° F
Local Alarm Horn Duration
10 Seconds
Local Alarm Beacon Duration Continuous
¥Natural gas supply must not contain more than 5ppm of H S.
2
Pilot Ignition/System Commissioning
After all appropriate power, wiring, and fuel supply connections have been completed per the
supplied drawings, the pilot system can now be commissioned. Waste flare gas is not required
for commissioning of the pilot system. The pilot system is the critical reliability path of a flare
system so this should be the primary focus of commissioning efforts regardless of waste gas
status. Waste gas can be introduced to the system at any point after the pilot system has been
commissioned, after appropriate purging steps have been completed.
Start-up Sequence
1. Confirm that fuel gas supply is available and plumbed into inlet of pilot gas spool on
flare stack
2. At the flare stack pilot spool, open all isolation valves upstream of the safety shut-off
solenoids
3. Verify that pressure gauges are reading 15 PSIG
a. Regulator adjustment may be necessary after safety shut-off solenoids open
allowing flow during commissioning
4. At the control panel rack, turn the POWER switch to the ON position
5. Turn each PILOT #X switch to the AUTO position
a. PILOT #X FAILURE light will illuminate due to low temperature on pilot
thermocouple(s) – this is ok and expected
b. PILOT GAS LOW PRESSURE light may illuminate momentarily until Low
Pressure Switch (PSL) is proven
i. Refer to 3.a above
13
c. Horn will sound and alarm beacon will illuminate reiterating low pressure
and pilot failure alarms – this is ok and expected
i. Duration is set to 10 seconds; Use ALARM SILENCE pushbutton to
silence horn if needed
6. PSL will confirm fuel gas supply pressure
a. PILOT GAS LOW PRESSURE light will de-energize
7. Safety shut-off solenoids will energize and open
8. Ignitors will begin firing to light pilots
9. Once pilots are ignited, thermocouples will heat up and prove pilots
10. PILOT #X FAILURE light will de-energize as each pilot is proven
a. Respective ignitors will cease firing as each pilot is proven
11. Horn and alarm beacon will de-energize after final pilot is proven
12. System is in steady run state and ready to receive waste gas
Alarm Conditions
• If pilot gas supply pressure drops below 7 PSIG:
o PILOT GAS LOW PRESSURE light will illuminate
o Horn will sound
o Alarm beacon will illuminate
o Alarm signal will be issued out to customer system via dry contacts (if
used)
o NOTE: If fuel gas pressure is lost, subsequent pilot failures will occur
• If pilot flame is lost and thermocouple drops below set point:
o PILOT #X FAILURE light will illuminate
o Horn will sound
o Alarm light will illuminate
o Alarm signal will be issued out to customer system via dry contacts (if
used)
If an alarm condition occurs, the system will automatically begin sparking to attempt to relight
the pilot(s). The system will continue to do so until successful re-ignition or an operator
intervenes to diagnose. Once the pilots are operational, the system is ready to accept waste
gas.
Waste Gas Introduction
Customer is responsible for the appropriate release and flow of waste gas to the flare system in
accordance with facility procedures and design conditions of the flare system.
NOTE: If the flare firing rate is in excess of the designed rate, it is possible to overheat the
surrounding area and cause combustion of nearby materials. To avoid this, we recommend the
installation of an isolation or control valve that can be used to shut the system in if an
emergency occurred (or an alternative acceptable emergency isolation method as approved by
operator).
14
Troubleshooting
Please refer to the attached emergency procedures located in the following supplemental
materials section of this document package: EMERGENCY PROCEDURE – OPERATOR RESPONSE
and EMERGENCY PROCEDURE – REIGNITION OF PILOT
ISSUE
CAUSE
Pilot fuel gas flow rate is too
low
PILOT WILL NOT LIGHT
PILOT FLAME NOT
PROVEN
Spark tip may be fouled
• Excessive sparking
• Liquid exposure
Debris or blockage in pilot
supply line
Debris or blockage in pilot
mixer and/or orifice
Blockage in pilot strainer
screen
Ignition module is not
discharging
Interconnecting wire may be
compromised
Thermocouple is reading
ambient temperature
Thermocouple leads are
damaged at potting adapter
Interconnecting wire may be
compromised
Polarity is reversed at wiring
termination points
Temperature device is sensing
temperature outside of Type K
range (-454°F to 2498°F TYP.)
Flow rate is too low/high
FLARE TIP IS SMOKING
ARRESTOR IS
HOT/SMOKING/
GLOWING/BURNT
Assist media is not being used
or rate is too low
A flashback is present or has
occurred
• Low flow rate
• Oxygen present in
waste gas stream
RESOLUTION
Adjust flow rate
Total per 1 pilot:
• 65 SCFH Natural Gas
• 39 SCFH Propane
Visual inspection
Check for continuity
Contact Zeeco for replacement
Inspect and clean as necessary
Inspect and clean as necessary
Inspect and clean as necessary
Check grounding
Contact Zeeco for replacement
Inspect and replace as necessary
Verify thermocouple is seated
properly in pilot thermowell
Contact Zeeco for replacement
Inspect and replace as necessary
Type K: Yellow (+), Red (-)
Verify continuity
Contact Zeeco for replacement
Adjust flow to match designed
operating range
Adjust rate manually until smoke
disappears
STOP OPERATION
CONTACT ZEECO
15
Flow rate is too low/high
WASTE GAS WON’T
IGNITE
Heating value of waste gas is
too low
Blockage in waste gas stream
Pilot flame has been lost
Adjust flow to match designed
operating range
Verify heating value against
design conditions; Enrich as
needed
Contact Zeeco for further options
Inspect and clean as necessary
Refer to pilot troubleshooting
section above
16
Pilot Maintenance
It is recommended that Zeeco pilot assemblies be inspected at normal facility intervals (or every
6 months) for wear, performance, and general maintenance.
1. Visually inspect pilot assembly for signs of failure or wear
1. Emphasis on evidence of weld fractures/cracking, open seams, metal
delamination, coking or deposits, etc.
2. It is common for pilots to exhibit discoloration due to the typical high
temperatures of standard operating environment
2. Inspect pilot hood and tip for signs of failure or wear in accordance with #1
3. Inspect pilot mixer assembly (located at base of pilot) for signs of failure or wear in
accordance with #1
1. Ensure mixer bell and opening of venturi are clean and clear of debris or
blockages
2. If desired, remove mixer assembly and spud orifice from mixer; ensure both are
clean and clear of debris or blockages
4. Remove and inspect ignitor probe tip and assembly (typical uppermost 10’ or 20’
section) for signs of damage and/or wear
1. If spark tip appears corroded, fouled, or pitted, replace with spare or contact
Zeeco
2. If ignitor probe cable/assembly appears damaged or blackened, replace with
spare or contact Zeeco
5. Remove and inspect thermocouple probe tip and body (typical uppermost 10’ or 20’
section) for signs of damage and/or wear
1. It is common for tip of thermocouple to exhibit discoloration due to the typical
high temperatures of standard operating environment
2. If thermocouple tip appears corroded, fouled, blackened, pitted, or otherwise
damaged, replace with spare or contact Zeeco
3. If thermocouple probe body (cable) appears damaged or blackened, replace with
spare or contact Zeeco
6. Verify integrity of all pilot mounting points including weldments or attachments to pilot
17
IF A PILOT OUTAGE OCCURS, ONCE CORRECTED, THE OUTAGE
MUST BE LOGGED IN: PILOT OUTAGE LOG
IF A PILOT SYSTEM CHANGE IS REQUIRED, THE CHANGE MUST BE
LOGGED IN: SYSTEM CHANGE LOG
SUPPLEMENTAL MATERIAL FOR FLARE INSTALLATION,
COMMISSIONING, OPERATION, AND DE-COMMISSIONING IS
ATTACHED AT THE END OF THIS DOCUMENT.
18
EMERGENCY PROCEDURE – OPERATOR ALARM RESPONSE AND TRAINING
19
Operating Manual Supplement
ZEECO RENTAL FLARE SYSTEM
PILOT EMERGENCY PROCEDURE
OPERATOR ALARM RESPONSE AND TRAINING
1. In the event of an alarm condition, an alarm signal will be output via dry contacts for customer
use and the alarm horn/beacon will be energized.
a. Refer to Alarm Conditions section in IOM for more information.
2. The OPERATOR is to respond to and monitor the Ignition System to determine if the controls
system is attempting to automatically re-light the relevant pilot.
3. Operator to note TIME.
4. If re-light is unsuccessful, the OPERATOR should inspect the system to determine cause. At this
time, it may be best to turn the system to the OFF state (isolation valves will close) and
investigate.
5. OPERATOR to complet a related entry on PILOT OUTAGE LOG.
TRAINING
Operator Training should be completed for each person responsible for the functioning of the flare as
soon as it is ready to be placed into operation. Each shift should be trained similarly. Depending on the
duration of the rental period, a refresher instruction should be conducted once per month (at least) by
plant personnel who are familiar with the system and how to troubleshoot and re-ignite the pilot(s) in
the event of failure and shutdown. ZEECO Service Technicians can be scheduled to perform this training
as well.
EMERGENCY PROCEDURE – REIGNITION OF PILOT
20
Operating Manual Supplement
ZEECO RENTAL FLARE SYSTEM
PILOT EMERGENCY PROCEDURE
OPERATOR ALARM RESPONSE AND TRAINING
1. In the event of an alarm condition, an alarm signal will be output via dry contacts for customer
use and the alarm horn/beacon will be energized.
a. Refer to Alarm Conditions section in IOM for more information.
2. The OPERATOR is to respond to and monitor the Ignition System to determine if the controls
system is attempting to automatically re-light the relevant pilot.
3. Operator to note TIME.
4. If re-light is unsuccessful, the OPERATOR should inspect the system to determine cause. At this
time, it may be best to turn the system to the OFF state (isolation valves will close) and
investigate.
5. OPERATOR to complet a related entry on PILOT OUTAGE LOG.
TRAINING
Operator Training should be completed for each person responsible for the functioning of the flare as
soon as it is ready to be placed into operation. Each shift should be trained similarly. Depending on the
duration of the rental period, a refresher instruction should be conducted once per month (at least) by
plant personnel who are familiar with the system and how to troubleshoot and re-ignite the pilot(s) in
the event of failure and shutdown. ZEECO Service Technicians can be scheduled to perform this training
as well.
SYSTEM CHANGE LOG
21
SYSTEM CHANGE LOG
FLARE UNIT NUMBER
ZEECO 52279
SITE SUPERVISOR
CUSTOMER/SITE
LOCATION
PHONE:
City, ST ZIP Code
LOCATION
First Commission
(Baseline)
PILOT FUEL SUPPLY
TYPE/SOURCE
DATE
PILOT REGULATOR
SETPOINT
PILOT PSLL
SETPOINT
ORIFICE SIZE
15 PSIG
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
7 PSIG
3/64"
PILOT OUTAGE LOG
22
FLARE PILOT OUTAGE LOG
FLARE UNIT
NUMBER
ZEECO 52279
SITE SUPERVISOR
CUSTOMER/SIT
E LOCATION
City, ST ZIP
Code
PHONE:
DATE
OUTAGE TIME
PILOT NUMBER
REIGNITION TIME
OUTAGE DURATION
OPERATOR NAME
NOTES
Example Entry
12:00
1, 2, 3
N/A
N/A
John Doe
DE-COMMISSION FOR
TRANSPORT
PROJECT DRAWINGS
23
14" S/STD
TRUNNION DETAIL
1/2" THK. PL.
GUY LUG DETAIL
M
TAILING LUG DETAIL
V
H
(12)-∅1 1/4" HOLES
UTILITY CONNECTIONS DETAILS
(2) GROUNDING LUGS
WITH 5/8" DIAMETER HOLE
@ 90 AND 270 DEGREES
BASE PLATE DETAIL
ELEVATION
(PORTIONS ROTATED FOR CLARITY)
TAG# DAP-1102
-SE-0890-BILL OF MATERIALS
TAG# DAP-1102
NOZZLE AND CONNECTIONS
EL. +190'-8"
MARK
TOP EL.+ 198'-0"
EL.+ 188'-0"
EL. +185'-6 7/8"
(FIXED) (TS-01)
EL. +185'-6 7/8"
(FIXED) (TS-01)
EL. +185'-6 7/8"
(ANCHOR) (PS-01)
EL. +175'-4 7/8"
(GUIDE) (TS-01)
EL. +175'-4 7/8"
(GUIDE) (TS-01)
EL. +175'-4 7/8"
(GUIDE) (PS-01)
SERVICE
Q'TY
SIZE
SCH.
RATING
FLG. MATERIAL PIPE MATERIAL FACING
GASKET
BOLT/NUT
INSULATION
1"
80
MNPT
UNION 3000#
A106-B
-
-
-
-
C1
PILOT GAS
1
C2~3
RETRACTABLE HEI TUBING
2
1"
-
-
-
316 S.S
-
-
-
-
C4~5
RETRACTABLE T/C TUBING
2
1/2"
-
-
-
316 S.S
-
-
-
-
REMARKS
NOTE
1. FLANGE BOLTING TO STRADDLE CENTERLINES INDICATED BY CENTERLINE UNLESS NOTED OTHERWISE.
2. ALL FLANGE SURFACE FINISHED SHALL BE 125~250 Ra.
3. ALL PIPING & CONDUIT LINES (2" AND SMALLER) WILL BE SUPPLIED IN RANDOM LENGTH FOR FIELD INSTALLATION AT JOBSITE.
4. " " MARK : 1/100 SLOPE.
EL. +167'-0 7/8"
(GUIDE) (TS-01)
EL. +167'-0 7/8"
(GUIDE) (PS-01)
EL. +167'-0 7/8"
(GUIDE) (TS-01)
U-BOLT
EL. +157'-9 7/8"
(GUIDE) (TS-01)
EL. +149'-8 13/16"
(GUIDE) (TS-01)
EL. +149'-8 13/16"
(GUIDE) (TS-01)
EL. +147'-6 11/16"
(GUIDE) (TS-01)
EL. +147'-6 11/16"
(GUIDE) (TS-01)
SUPPORT ANGLE
EL. +149'-8 13/16"
(GUIDE) (PS-01)
GUIDE ANGLE
U-BOLT
SLIDE
TYPE
3'-0"
EL. +147'-6 11/16"
(GUIDE) (PS-01)
EL. +145'-0"
EL. +142'-0"
EL. +137'-4 11/16"
(GUIDE) (PS-01)
EL. +137'-4 11/16"
(GUIDE) (TS-01)
FIXED
TYPE
C.L 1.5
EL. +157'-9 7/8"
(GUIDE) (TS-01)
EL. +157'-9 7/8"
(GUIDE) (PS-01)
THIN-NUT SHALL BE
USED FOR PIPE SIDE
EL. +137'-4 11/16"
(GUIDE) (TS-01)
EL. +129'-0 11/16"
(GUIDE) (PS-01)
EL. +129'-0 11/16"
(GUIDE) (TS-01)
EL. +129'-0 11/16"
(GUIDE) (TS-01)
EL. +119'-9 11/16"
(GUIDE) (TS-01)
EL. +119'-9 11/16"
(GUIDE) (TS-01)
EL. +110'-8 5/8"
(GUIDE) (TS-01)
EL. +110'-8 5/8"
(GUIDE) (TS-01)
EL. +108'-6 1/2"
(GUIDE) (TS-01)
EL. +108'-6 1/2"
(GUIDE) (TS-01)
EL. +98'-4 1/2"
(GUIDE) (TS-01)
EL. +98'-4 1/2"
(GUIDE) (TS-01)
EL. +90'-0 1/2"
(GUIDE) (TS-01)
EL. +90'-0 1/2"
(GUIDE) (TS-01)
EL. +80'-9 1/2"
(GUIDE) (TS-01)
EL. +80'-9 1/2"
(GUIDE) (TS-01)
EL. +71'- 8 7/16"
(GUIDE) (TS-01)
EL. +71'- 8 7/16"
(GUIDE) (TS-01)
EL. +69'-6 5/16"
(GUIDE) (TS-01)
EL. +69'-6 5/16"
(GUIDE) (TS-01)
SLIDE TYPE
EL. +119'-9 11/16"
(GUIDE) (PS-01)
FIXED TYPE
U-BOLT/4NUTS
EL. +110'-8 5/8"
(GUIDE) (PS-01)
EL. +108'-6 1/2"
(GUIDE) (PS-01)
EL. +98'-4 1/2"
(GUIDE) (PS-01)
EL. +90'-0 1/2"
(GUIDE) (PS-01)
EL. +80'-9 1/2"
(GUIDE) (PS-01)
EL. +71'- 8 7/16"
(GUIDE) (PS-01)
3'-0"
EL. +69'-6 5/16"
(GUIDE) (PS-01)
EL. +67'-0"
EL. +64'-0"
EL. +59'-4 5/16"
(GUIDE) (PS-01)
EL. +59'-4 5/16"
(GUIDE) (TS-01)
EL. +59'-4 5/16"
(GUIDE) (TS-01)
EL. +32'-8 1/4"
(GUIDE) (PS-01)
EL. +32'-8 1/4"
(GUIDE) (TS-01)
EL. +32'-8 1/4"
(GUIDE) (TS-01)
EL. +30'-6"
(GUIDE) (TS-01)
EL. +30'-6"
(GUIDE) (TS-01)
EL. +30'-6"
(GUIDE) (PS-01)
EL. +17'-8"
(GUIDE) (PS-01)
EL.+ 35'-0"
EL. +17'-8"
(GUIDE) (TS-01)
EL. +17'-8"
(GUIDE) (TS-01)
EL. +7'-6"
(GUIDE) (TS-01)
1/2 "PILOT GAS INLET
EL. +7'-6"
(ANCHOR) (PS-01)
EL. +7'-6"
(GUIDE) (TS-01)
1" RETRACTABLE HEI TUBING
T/C JUNCTION BOX
EL. +5'-8 3/4"
1" RETRACTABLE HEI TUBING
1/2" RETRACTABLE T/C TUBING
1/2" RETRACTABLE T/C TUBING
EL. +5'-8 3/4"
HEI JUNCTION BOX
TAG# DAP-1102
C1
BRUNO PAQLIAI VERACURZ , MEXICO
PEMEX
S.O. NO.:
51180
P.O. NO.:
PHONE: (918) 258-8551
FAX: (918) 251-5519
www.zeeco.com
sales@zeeco.com
0 21MAR22
NO
DATE
INITIAL ISSUE
REVISION DESCRIPTION
YHC
HMC
CAH
BY
CKD
APP.
PROPRIETARY DATA IS INCLUDED IN THE INFORMATION
DISCLOSED HEREIN AND IS THE PROPERTY OF ZEECO,INC.
THIS INFORMATION IS SUBMITTED IN CONFIDENCE AND
MUST BE USED IN CONNECTION WITH WORK DONE FOR
ZEECO, INC. AND ALL RIGHTS OF DESIGN OR INVENTION
ARE RESERVED. UNAUTHORIZED DISCLOSURE OR USE IS
PROHIBITED BY LAW.
FOR:
APP
640851807
SELF SUPPORTED
FLARE STACK SYSTEM
PIPING ARRANGEMENT
ZEECO, INC.
22151 EAST 91st STREET
BROKEN ARROW, OK 74014
BASE EL.+ 0
ELEVATION
JOBSITE:
END USER:
NUVOIL / COST OIL
DRAWN
DATE
CHK
APP
YHC
LMG
28FEB22
HMC
SCALE
REV
NONE
CAH
0
DRAWING NUMBER
KD-1086
SHT. 1 OF 1
BILL OF MATERIALS
CODE
DESCRIPTION
MATERIAL
WEIGHT (lb)
REV.
1
11
PIPE
PIPE (PILOT GAS) 1" SCH.80x20'-0"LG. (PC)
A106-B
363
0
2
2
UNION
THREADED UNION 1" 3000# FNPT.
A105
4
0
3
11
COUP
FULL COUPLING 1" #3000 SW
A105
2
0
4
11
ELBO
90° ELBOW 1" #3000 SW
A105
6
0
5
1
VALVE
NEEDLE VALVE 1" FNPT
6
0
6
1
STRAIN
STRAINER 1" FNPT
6
0
7
1
SWITCH
PRESSURE SWITCH 1"
6
0
8
1
GAUGE
PRESSURE GAUGE 1"
6
0
387
0
90°
"
"A
AIL
T
EL.
+19
0
TOTAL WEIGHT
9/16"
8"
DE
1" NPT
'-8"
NOTE
1. UTILITY PIPING 2" AND SMALLER WILL BE SUPPLIED IN RANDOM LENGTH FOR FIELD INSTALLATION AT JOB SITE.
PIPING DETAILS PER THIS DRAWING ARE APPROXIMATE ONLY. PIPING TO BE FIELD FIT TO MATCH EQUIPMENT.
DETAIL "A"
EL
.+1
9
2. "
" MARK : 1/100 SLOPE.
3. ALL GAS-WETTED MATERIAL IS REQUIRED TO HAVE EN-10204 3.1 CERTIFICATIONS.
ALL NON-GAS-WETTED MATERIAL IS REQUIRED TO HAVE EN-10204 2.2 CERTIFICATIONS.
0'-0
"
1/16"
3'
1/16"
1/8"
3'
3'
"
1'-6
2'-7
EL
.+1
45'0"
4
3/1
6"
PIPES TO ELBOWS
EL
.+1
42'0"
3'
TYP.
1/8"
1/16"
184'-9 1/4"
"
1'-6
3'
EL
.+
3/1
67'-
6"
EL
.+
64'-
0"
1/16"
2'-7
0"
PIPES TO COUPLINGS
3
TYP. WELD JOINT DETAILS
(* ALL WELDS ARE FIELD WELD)
PRESSURE
GAUGE
8
PRESSURE
SWITCH
7
6
1
IL "
TA
DE
9/16"
1" NPT
5
B"
TAG# DAP-1102
DETAIL "B"
2
1" PILOT GAS
°
180
NO.
PCS.
0°
3'
270
°
PART
NO.
EL
.+5
'-2
3/4
JOBSITE:
BRUNO PAQLIAI VERACURZ , MEXICO
END USER:
PEMEX
S.O. NO.:
51180
P.O. NO.:
SELF SUPPORTED
FLARE STACK SYSTEM
UTILITY PIPE DWG.
ZEECO, INC.
22151 EAST 91st STREET
BROKEN ARROW, OK 74014
C1
PHONE: (918) 258-8551
FAX: (918) 251-5519
www.zeeco.com
sales@zeeco.com
0 21MAR22
NO
DATE
INITIAL ISSUE
REVISION DESCRIPTION
YHC
HMC
CAH
BY
CKD
APP.
PROPRIETARY DATA IS INCLUDED IN THE INFORMATION
DISCLOSED HEREIN AND IS THE PROPERTY OF ZEECO,INC.
THIS INFORMATION IS SUBMITTED IN CONFIDENCE AND
MUST BE USED IN CONNECTION WITH WORK DONE FOR
ZEECO, INC. AND ALL RIGHTS OF DESIGN OR INVENTION
ARE RESERVED. UNAUTHORIZED DISCLOSURE OR USE IS
PROHIBITED BY LAW.
APP
640851807
DRAWN
DATE
CHK
APP
YHC
28FEB22
HMC
SCALE
REV
NONE
FOR:
NUVOIL / COST OIL
LMG
CAH
0
DRAWING NUMBER
KD-1087
SHT. 1 OF 1
BILL OF MATERIALS FOR RETRACTABLE TUBING
PLANT NORTH
0°
PART
NO.
TYPE/MODEL
REMARKS
1
40
-
HEI TUBING O.D1" x 0.065" WALL - 20'-0"LG.
316 S.S ID-033-005-2213
SEE NOTE 4
2
2
-
BULKHEAD UNION 1" (BORE 0.504" I.D. +0.002 & -0.000")
HOKE #8BUT-316 or BI-LOK
#DSU-16-SS/ZEECO
ID-085-006-1209
-
TUBING UNION 1" (BORE 0.504" I.D. +0.002 & -0.000")
HOKE #8UT-316 or BI-LOK
#DUA-16-SS/ZEECO
ID-085-006-1011
-
HOKE #8BCF8-316 or BI-LOK
#DUR-16-8-SS/ZEECO
ID-085-006-1125
-
316 S.S ID-086-009-0059
SEE NOTE 3
WC-9091
-
90°
270°
180°
3
1" HEI RETRACTABLE TUBING
(T/S-01)
10
-
4
2
-
TUBING CONNECTOR 1"T x 1"P
5
2
-
HEX. HEAD BUSHING 1" x 1/4" - 3000#
6
1
-
JUNCTION BOX
NOTE
2
2
RT
PO
UP
D S 6 7/8"
E
FIX 18 5'.+
EL
RT
PO
UP
D S 6 7/8"
E
FIX 18 5'.+
EL
1. SEE GENERAL ARRANGEMENT DRAWINGS FOR ALL REQUIREMENTS.
2. TUBING UNION FITTINGS TO BE UNBROKEN
3. HOKE OR BI-LOK FITTINGS
4. HEI TUBING WITH 15RA ROUGHNESS MAX. TUBING.
5. DETAIL DWG. NUMBERING SYSTEM.
* T/S - 01
1'-8 5/16"
MEMBER SERIAL NO.
T/C TUBING SUPPORT
90°
1'-8 5/16"
270°
3
3
180°
1" HEI RETRACTABLE TUBING
(T/S-01)
EL.+188'-0" ~ TOP
1
BULKHEAD UNION
1" TUBING
HOKE#8BUT-316
1" TUBING
TUBING UNION
HOKE#8UT-316
2
1" MYERS HUB
1
3
JUNCTION BOX
1" THERMOCOUPLE
MOUNTING FITTING
THERMOCOUPLE
DETAIL "A"
DETAIL "B"
NO GAP
DETAIL "C"
6
"D"
4
"D"
5
4
5
J/B
TUBING CONNECTOR
1" TUBING
HOKE#8CF8-316
4
MIN. R5
'-0"
(TYP.)
5
1"x1/4" HEX.
HEAD BUSHING
"A"
TAG# DAP-1102
15°
.)
(MAX
MIN. R5
'-0"
(TYP.)
DETAIL "D"
JOBSITE:
BRUNO PAQLIAI VERACURZ , MEXICO
END USER:
PEMEX
S.O. NO.:
51180
APP
TUBING BENDING DETAIL
P.O. NO.:
ZEECO, INC.
22151 EAST 91st STREET
BROKEN ARROW, OK 74014
(TYP.)
SELF SUPPORTED
FLARE STACK SYSTEM
PHONE: (918) 258-8551
FAX: (918) 251-5519
www.zeeco.com
sales@zeeco.com
18APR22
18APR22
0 21MAR22
NO
DATE
REVISED AS MAKRED
INITIAL ISSUE
REVISION DESCRIPTION
YHC
YHC
HMC
HMC
CAH
CAH
BY
CKD
APP.
640851807
RECTRACTABLE HEI DETAIL DWG.
LMG
DRAWN
DATE
YHC
28FEB22
CHK
APP
HMC
CAH
SCALE
REV
NONE
FOR:
NUVOIL / COST OIL
PROHIBITED BY LAW.
1
DRAWING NUMBER
KD-1089
SHT. 1 OF
BILL OF MATERIALS FOR RETRACTABLE TUBING
PLANT NORTH
0°
90°
270°
PART
NO.
NO.
PCS.
CODE.
TYPE/MODEL
REMARKS
1
40
-
T/C TUBING O.D1/2" x 0.049" WALL - 20'-0"LG.
316 S.S ID-033-007-0001
SEE NOTE 4
2
2
-
BULKHEAD UNION 1/2" (BORE 0.504" I.D. +0.002 & -0.000")
HOKE #8BUT-316 or BI-LOK
#DSUZ-8-SS/ZEECO
ID-085-006-0001
-
-
180°
1/2" RETRACTABLE TUBING
(T/S-01)
0°
"B"
2
T
OR
PP
SU 8"
ED 6 7/
FIX 185'.+
EL
T
OR
PP
SU 8"
ED 6 7/
FIX 185'.+
EL
10
-
TUBING UNION 1/2" (BORE 0.504" I.D. +0.002 & -0.000")
4
2
-
TUBING CONNECTOR 1/2"T x 1/2"P
HOKE #8BCF8-316 or BI-LOK
#DSA-8-8-SS/ZEECO
ID-085-005-0001
-
5
2
-
HEX. HEAD BUSHING 1/2" x 1/4" - 3000#
316 S.S ID-086-009-0053
SEE NOTE 3
6
1
-
JUNCTION BOX
WC-9091
-
NOTE
"B"
2
3
HOKE #8UT-316 or BI-LOK
#DUAZ-8-SS/ZEECO
ID-085-006-0002
1. SEE GENERAL ARRANGEMENT DRAWINGS FOR ALL REQUIREMENTS.
2. TUBING UNION FITTINGS TO BE UNBROKEN
3. HOKE OR BI-LOK FITTINGS
4. T/C TUBING WITH 15RA ROUGHNESS MAX. TUBING.
5. DETAIL DWG. NUMBERING SYSTEM.
* T/S - 01
MEMBER SERIAL NO.
1'-5 13/16"
T/C TUBING SUPPORT
90°
1'-5 13/16"
270°
3
"C"
3
"C"
180°
1/2" RETRACTABLE TUBING
(T/S-01)
EL.+188'-0" ~ TOP
1
BULKHEAD UNION
1/2" TUBING
HOKE#8BUT-316
1/2" MYERS HUB
1/2" TUBING
2
1
TUBING UNION
HOKE#8UT-316
3
JUNCTION BOX
1/2" THERMOCOUPLE
MOUNTING FITTING
THERMOCOUPLE
DETAIL "A"
DETAIL "B"
NO GAP
DETAIL "C"
6
"D"
J/B
TUBING CONNECTOR
1/2" TUBING
HOKE#8CF8-316
5
"D"
5
4
5
4
MIN. R5
'-0"
(TYP.)
1/2"x1/4" HEX.
HEAD BUSHING
4
"A"
TAG# DAP-1102
15°
.)
(MAX
MIN. R5
'-0"
(TYP.)
DETAIL "D"
TUBING BENDING DETAIL
JOBSITE:
BRUNO PAQLIAI VERACURZ , MEXICO
END USER:
PEMEX
S.O. NO.:
51180
P.O. NO.:
SELF SUPPORTED
FLARE STACK SYSTEM
ZEECO, INC.
22151 EAST 91st STREET
BROKEN ARROW, OK 74014
(TYP.)
PHONE: (918) 258-8551
FAX: (918) 251-5519
www.zeeco.com
sales@zeeco.com
0 21MAR22
NO
DATE
INITIAL ISSUE
REVISION DESCRIPTION
YHC
HMC
CAH
BY
CKD
APP.
PROPRIETARY DATA IS INCLUDED IN THE INFORMATION
DISCLOSED HEREIN AND IS THE PROPERTY OF ZEECO,INC.
THIS INFORMATION IS SUBMITTED IN CONFIDENCE AND
MUST BE USED IN CONNECTION WITH WORK DONE FOR
ZEECO, INC. AND ALL RIGHTS OF DESIGN OR INVENTION
ARE RESERVED. UNAUTHORIZED DISCLOSURE OR USE IS
PROHIBITED BY LAW.
APP
640851807
RECTRACTABLE TC DETAIL DWG.
DRAWN
DATE
CHK
APP
YHC
28FEB22
HMC
SCALE
REV
NONE
FOR:
NUVOIL / COST OIL
LMG
CAH
0
DRAWING NUMBER
KD-1089
SHT. 1 OF 1
1102
1102
1102
IJB
IJB - 1102
LCP-1102 / IJB-1102
Download