TRACK WORKS PROGRESS No: WORK DESCRIPTION 1 SUB BALLAST LAID COMPLETED 2 BALLAST LAID COMLETED 3 SLEEPERS LAID 4 RAILS LAID COMPLETED 5 RAILS WELDING 6 2ND LAYER OF BALLAST Main line completed remain on turnouts makutupora station some marshalling yards Mostly areas Completed 7 TAMPING 1ST & 2ND PASSES Completed 8 DISTRESSING Completed mainline and remain some areas makutupora stations 9 FINAL TAMPIND AND DYNAMIC TRACK STABILIZATION Completed main line and some areas not finished at marshalling and makutupora station 10 FINAL GRINDING Compted to makutupora station km529 11 DRESSING AND PROFILING BALLAST Completed mainline and makutupora station not yet 14 TURNOUT INSTALLATION (Pcs) COMPLETED All installed and welded exept makutupora station Pre-Commissioning completed from km 201+819-529 and stations such as Mkata, Kilosa, passing loop1, passing loop2, kidete, gulwe igandu and bahi. Challenges Contractor financial crisis and fuel El nino rain