Uploaded by Fatael Pallangyo

track status progress

advertisement
TRACK WORKS PROGRESS
No:
WORK DESCRIPTION
1
SUB BALLAST LAID
COMPLETED
2
BALLAST LAID
COMLETED
3
SLEEPERS LAID
4
RAILS LAID
COMPLETED
5
RAILS WELDING
6
2ND LAYER OF BALLAST
Main line completed remain on turnouts makutupora station some marshalling
yards
Mostly areas Completed
7
TAMPING 1ST & 2ND PASSES
Completed
8
DISTRESSING
Completed mainline and remain some areas makutupora stations
9
FINAL TAMPIND AND DYNAMIC TRACK
STABILIZATION
Completed main line and some areas not finished at marshalling and makutupora
station
10
FINAL GRINDING
Compted to makutupora station km529
11
DRESSING AND PROFILING BALLAST
Completed mainline and makutupora station not yet
14
TURNOUT INSTALLATION (Pcs)
COMPLETED
All installed and welded exept makutupora station
Pre-Commissioning completed from km 201+819-529 and stations such as Mkata, Kilosa,
passing loop1, passing loop2, kidete, gulwe igandu and bahi.
Challenges
Contractor financial crisis and fuel
El nino rain
Download